Figure 2.4 – Lot 2 RP 64750, roof downpipe draining towards northern boundary.
Roof run-off from the dwelling on Lot 2 RP 153798 is similarly collected in downpipes
however no outlet could be located within the property nor within the street drainage. It is
assumed that this water must be discharged as overland flow on site as surface levels along
the frontage are typically higher than within the property making gravity drainage to the
street unlikely.
Roof water from the garage on this property is collected and conveyed to a water tank on
site of approximately 10,000L, with overflows discharged as overland flow within the
property.
2.2.1.1. Upstream Catchments
Contour maps of the locality indicate that upstream surface run-off from the adjacent
property on Lot 1 RP 153798 may enter Lot 2 RP 153798 as overland flow along the
boundary, however no evidence of this was able to be observed on site. Roof water from
the dwelling on the upstream property appears to discharge directly to the table drain on
pearl street through a piped outlet.
Surface run-off from the road reserve is typically collected in the table drains along the street
frontage and does not appear to enter the site.
Page 4 of 26
P +61 7 5211 1003 A 37 Mary St, Noosaville Qld 4566 E [email protected] recorconsulting.com
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Att 4 - SWMP.pdfRelated documentApplication case desk ↗
About this file
- File size
- 5.7 MB (large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take up to a minute.