investigations (including engaging appropriately qualified plant locators at your
expense to locate nbn Facilities during any activities you carry out on site).
2. You acknowledge that nbn has specifically notified you above that the Indicative Plans
are likely to be more accurate in showing location of fibre optics and
telecommunications cables than power cables. There may be a variation between the
line depicted on the Indicative Plans and the location of any power cables.
3. You should not assume that nbn Facilities follow straight lines or are installed at
uniformed depths along their lengths, even if they are indicated on plans provided to
you. Careful onsite investigations are essential to locate the exact position of cables.
4. In carrying out any works in the vicinity of nbn Facilities, you must maintain the
following minimum clearances:
• 300mm when laying assets inline, horizontally or vertically.
• 500mm when operating vibrating equipment, for example: jackhammers or
vibrating plates.
• 1000mm when operating mechanical excavators.
• Adherence to clearances as directed by other asset owner's instructions and
take into account any uncertainty for power cables.
5. You are aware that there are inherent risks and dangers associated with carrying out
work in the vicinity of underground facilities (such as nbn fibre optic,copper and coaxial
cables,and power cable feed to nbn assets).Damage to underground electric cables
may result in:
• Injury from electric shock or severe burns, with the possibility of death.
• Interruption of the electricity supply to wide areas of the city.
• Damage to your excavating plant.
• Responsibility for the cost of repairs.
6. You must take all reasonable precautions to avoid damaging nbn Facilities. These
precautions may include but not limited to the following:
• All excavation sites should be examined for underground cables by careful
hand excavation. Cable cover slabs if present must not be disturbed. Hand
excavation needs to be undertaken with extreme care to minimise the likelihood
of damage to the cable, for example: the blades of hand equipment should be
aligned parallel to the line of the cable rather than digging across the cable.
• If any undisclosed underground cables are located, notify nbn immediately.
• All personnel must be properly briefed, particularly those associated with the
use of earth-moving equipment, trenching, boring and pneumatic equipment.
• The safety of the public and other workers must be ensured.
• All excavations must be undertaken in accordance with all relevant legislation
and regulations.
7. You will be responsible for all damage to nbn Facilities that are connected whether
directly, or indirectly with work you carry out (or work that is carried out for you or on
your behalf) at the Location. This will include, without limitation, all losses expenses
incurred by nbn as a result of any such damage.
8. You must immediately report any damage to nbn™ network that you are/become
aware of. Notification may be by telephone - 1800 626 329.
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalVery large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.