STEP 3 – POTHOLE
Validation as defined in AS5488-2013 (QL-A).
After utilising a Telstra Accredited Plant Locator and prior to commencing construction, any
electronically detected underground network must be positively identified (validated) by
physically sighting it. This can be done by careful hand digging or using non-destructive water
jet methods to expose the network.
Manual potholing needs to be undertaken with extreme care and by employing techniques least likely to damage
cables. For example, align shovel blades and trowels parallel to the cable rather than digging across the cable.
Some Telstra Accredited Plant Locators are able to provide or assist with non-destructive potholing methods to
enable validation of underground cables and ducts.
If you cannot validate the underground network then you must not proceed with construction.
Telstra will seek compensation for damages caused to its property and losses caused to Telstra
and its customers.
Important note: The construction of Telstra’s network dates back over many years. Some of Telstra’s pits and
ducts were manufactured from asbestos-containing cement. You must take care in conducting any works in the
vicinity of Telstra’s pits and ducts. You must refrain from in any way disturbing or damaging Telstra’s network
infrastructure when conducting your works. We recommend that before you conduct any works in the vicinity of
Telstra infrastructure that you ensure your processes and procedures eliminate any possibility of disturbing,
damaging or interfering in any way with Telstra’s infrastructure. Your processes and procedures should incorporate
appropriate measures having regard to the nature of this risk. For further information -
http://ucm.in.telstra.com.au/about/media/emergencies-incidents/asbestos/index.htm?ssSourceSiteId=consumer-advice
_______________________________________________________________________------____________________
STEP 4 – Protect:
You must maintain the following minimum clearance distances between construction activity
and the validated position of Telstra plant.
Jackhammers/Pneumatic Not within 1.0m of actual validated location.
Breakers
Vibrating Plate or Wacker Not within 0.5m of actual validated location of Telstra
Packer Compactor ducts.
300mm compact clearance cover before compactor can
be used across Telstra ducts.
Boring Equipment Not within 2.0m of actual validated location.
(in-line, horizontal and vertical) Constructor to hand dig or use non-destructive water jet
method (pothole) and expose plant.
Heavy Vehicle Traffic (over 3 Not to be driven across Telstra ducts (or plant)
tonnes) with less than 600mm cover.
Constructor to check actual depth via hand digging.
Mechanical Excavators, Farm Not within 1.0m of actual validated location.
ploughing and Tree Removal Constructor to hand dig or use non-destructive water jet
method (pot-hole) and expose plant.
For blasting or controlled fire burning please contact Telstra Plan Services.
If conducting roadworks all existing Telstra pits and manholes must be a minimum of 1.2m in from the back of
kerb after the completion of your work.
After the completion of any ground work in footways or roadway whereby the existing levels are being
changed the depth of cover of the existing Telstra asset at the completion of work must not be less than the
existing level before work commenced or of that of the recommendations of the ‘Road Opening Conference’,
TELSTRA CORPORATON ACN 051 775 556 DOC Version 28 (20th October 2017)
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalVery large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.