The requirements for acid sulphate testing shall be confirmed by a geotechnical engineer prior to the detailed design stage of this proposed development. Should acid sulphate soils be identified during construction or preliminary site investigations, a geotechnical engineer should be consulted for further guidance. Project number 20210216 Page 8 of 13 File RECOR Preliminary Stormwater Management Report - 20210216.docx, 2022-02-01 Revision 0 P +61 7 5211 1003 A 37 Mary St, Noosaville Qld 4566 E [email protected] recorconsulting.com