MCU220051_Information Request Response_v1.2_130323 · MCU22/0051
Our ref: 102995-10
• Include roofwater harvesting and reuse, consistent with the requirements of the Sustainable Building Design
Code. This may include capture of roofwater for irrigation of site landscaping.
• Please note that stormwater infrastructure is not permitted within the front landscaped setback.
Response
The SWMP and MUSIC modelling has been updated to incorporate:
• A catchment size of 0.415ha.
• Corrected the rainfall station to the Cooroy Composite data.
• Confirmation that the extended storage was calculated on equal surface area method.
• Inclusion of a rainwater tank in the MUSIC model.
In addition, the stormwater infrastructure (being the bio-retention basin) is not located within the front
landscaped setback. This is shown on the Landscape Concept Plan and updated Architectural Plans.
Refer to Attachment E for further details.
Stormwater Drainage
Information Required
13. Provide a preliminary design section for the detention/bioretention basin showing:
• Surveyed level of existing drainage network which the site proposes to connect to;
• Design level of adjacent pavement levels within the site and outlet level of internal site drainage network into
the basin; and
• Detention storage depth, extended detention depth for bioretention, filter media depth and demonstrate that
sufficient fall is available to accommodate all these depths and that the bioretention sub-soil drains will be
free draining.
Response
The SWMP has been amended to incorporate:
• The updated survey which shows the existing drainage network.
• Updated plan to show the proposed connection location.
• Updated plan to show a section of the bio-retention/detention basin and proposed SLs with a minimum
grade of 0.5% to connect to existing stormwater infrastructure.
Refer to Attachment E for further details.
Information Required
14. Update the design of the detention basin proposed for the site to include allowance for increased rainfall intensity
due to climate change (i.e. analysis of the 1%AEP event at end of planning period 2100).
Response
The SWMP has been amended to ensure the detention has been sized for both current rainfall events and
the increase of rainfall due to climate change.
Refer to Attachment E for further details.
RPS Australia East Pty Ltd. Registered in Australia No. 44 140 292 762
rpsgroup.com Page 16
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
MCU220051_Information Request Response_v1.2_130323.pdfRelated documentApplication case desk ↗
About this file
- File size
- 1.9 MB (small file)
- File type
No other editions are linked here.