09/0940 - Op works - Jetty [As Published] · 142009.940
Sunshine Coast Checklist - Applications Involving Land
Regional Council Development & Land Use Sections
IDAS APPLICATION
This checklist should be used for any IDAS application. Please check each of the following items before accepting an
application at the counter.
1. APPLICATION FORMS. 0 3
1.1. Form1PartA
1.1.1 Ensure that the form is fully completed and is a current version.
1.1.2 In the case of an MCU or Op Works below the. high-water mark, owner's consent is required.
1.1.2.1 If there are multiple owners, the consent of each owner is required.
1.1.2.2 If the owner of the land is a company, either ACN No, Company name clearly indicated by
signatory) or Company Seal required.
4.2. Form1 Part B-R Supporting Information
t 41.2 Ensure that for each box checked on Form A, the relevant additional Forms B-R are attached.
= 1.1.2.1 . Ensure that each of Forms B-R which are att ched are fully completed. ra
= SS eet
"2, »IDAS:ASSESSMENT CHECKEI
2.1. Ensure that relevant sections have been checked and/or completed with regard to referrals C7
2.2 Ensure correct parts of Form 1 are provided where required (ie most common are Part J for :
Clearing Vegetation, Part N for Contaminated land and Part P for Prescribed Tidal Works) , Fry
ENVIRONMENTALLY RELEVANT:AGTIVITIES: a
3.1. Ensure that Part G is completed if EPA referral is required.
3.2 Where EPA is delegated to Council (see * in ERA checklist), ensure that the correct application
fee is paid and recorded on the application. (Refer Environmental Health for fees)
4°: FORM 2 “REQUEST TO'CH: ARPROVAL
4.1 Ensure that relevant items have been ‘checked and/or completed including
applicant details along with owners consent if hot current owner of land as shown on Council records. |
If over multiple properties on one or more sites, consent of Body Corporate is required. ‘
$8 PLANS T3007 CO ars ye Pets LE bees \
@ 5.1 Ensure that generally at least 6 sets of the Plan of Development (5 for Reconfiguration and Operational f #
—_ Works) accompany the application. In addition ensure that each set is complete. t
5.2 Ensure that 1 of the copies of the Plan of Development is in an A3 or A4 format and is . : Y
unbound.
6. SUPPORTINGAINFORMATION
6.1. Ensure that generally at least 6 copies of any report accompanies the application (5 for Reconfi iguration -
and Operational Works). If the application is accompanied by a covering letter, ensure that it is |
capable of reproduction. .
6.2 In the case of reports, ensure that 1 of the copies is in an A3 or A4 format and is unbound,
6.3 Additionally an electronic version is preferred where possible for ease of electronic record keeping ~
7.1. Ensure that the application fee, as determined from the Council’s adopted scale of fees,
accompanies the application or has been paid.
_ #
« Land Use MCU applications; MCU applications including a Lot reconfiguration; Prescribed Tidal Works; Operational
Work if Jetty or if including Landscaping.
e Land Development Lot Reconfiguration applications and Operational Work not including Landscaping
Please DO NOT leave the application at the counter and OO NOT deliver the application to Records.
NSC g:\landuse\administrative processes\application checklist.doc
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalFull text of the other 17 pages
Page 2
“|B “YES : © COMMENT. - ‘ Please tick: Te, Department of Main Roads (Concurrence or Advice) « State Controlled Road Dept Natural Resources & Water e Acid sulphate soils (Advice) e Clearing of native vegetation on freehold land (Concurrence) Environmental Protection Agency (Concurrence) « Contaminated land « Environmental Management/Contaminated Land Register *= UXO = Land recently used as a ‘notifiable activity’ = Industrial land changed to sensitive uses (eg school) e Coastal related development. e Koala habitat e Wetlands (Advice-only) e Environmentally Relevant Activity (for non-devolved Council as EPA) Queensland Transport (Concurrence) ° Railway . Public Passenger Transport Energex or other responsible entity (Advice) ° Electricity Easements/Substations DIP (Concurrence) ° SEQ Regional plan VARIOUS s . Conservation estate (Advice) Department of Natural Resources and Mines EPA For further clarification refer to IDAS Guides prepared by Department of Infrastructure & Planning. NSC g:\landuse\administrative processes\application checklist.doc
Page 3
ee
Oo
INTEGRATED PLANNING ACT 1997 Part A, Version 3.4, 3 March 2008
SCKo
Fo,
“Oat cog tii
NOTE: Answer all questions unless directed to go to a particular question. Refer to the end of the form for athiefo! to wo
information provided on the IDAS Application Form is correct. This information is retied upon by the Assessment Manager and any y referral agencies winen 1 assessing arid
deciding this application.” By lodging this application, the Applicant it incurs the obligations and responsibilities prescribed te the IPA, Any development pet or, preliminary”
approval ial may be issued as a consequence of this application will be issued to the Applicarit.) “te
Company/organisation name {if applicable) [Pite-t Pty Ltd Va Noosa Jetty Builders |
individual applicant/Contact person {if there is more than one applicant, provide additional applicant details on an attachment to this form)
Title Mrs Firstname {Emma Last name
Postal address [Po Box 299 Noosaville QLD 4566 ‘|
Contact telephone number Mobile phone number
Facsimile number 07 5474 3480 e-mail address [email protected]
(Details. of the: premises (ie. the land on which the development is proposed - refer to the advice at the end of the form) boned ‘ ee}
1, Identify the premises by completing Table A, or Table B and/or Table C (ensure adequate information is given to identify the premises)
Table A _ If the application is for a mobile and temporary Environmentally Relevant Activity (ERA), complete Table A only. Then go to Q2.
i o_— Name of each local govemment area in which the mobile and temporary ERA is proposéd to operate *
| 1
OR
Table B Street address for the premises (tick applicable box/es below and insert property description i in the table. Identify each lot in a separate row.)
() [£] Street address / lot on plan for the premises (Appropriate for most applications including building applications): Of
(i) JX] Street address /lot on plan for the land adjoining or adjacent to the premises (Appropriate for development in water e.g. jetty,
Pontoon etc) (Note: Loton plan details may be obtained from title documents, a ‘Rate’ notice, or from the local government.)
‘ “yt . StreetAddress et ke Lot on plan description, .
“nt Tsreatl — Plan type and Local govemment area (e.g. Logan.
No. | No.’| “street Name and official suburb/ocality name...) Post Code | Lot No. Pian Number | Cairns) oe a
[ 1 3 Watreside Crt, Noosaville QLD 4566 759 RP906962 Sunshine Coast Regionat Council
AND/OR
Table C Coordinates and/or a map of the premises (Appropriate for development in remote areas, over part of a lot, in water (e.g. channel dredging in Moreton
Bay) etc.)
Aw Coordinates . wos .
(Note: place each set af coordinates ina separate row) Zone Daturri ' Local government area
|. Easting. -|° -Northing- }- Latitude | Longitude | Reference Tak | ft appeal)
pear elie ie i
ot
2. Identify if any of the following apply to the premises by completing Tables D, E, or F. (Note: in most instances, the premises will not involve any of
the following characteristics, however some applications may involve one or more of these characteristics - complete only if applicable)
Page 4
INTEGRATED PLANNING ACT 1997 Part A, Version 3.1, 3 March 2008
Table D Complete if the premises are adjacent to or associated with a water body, watercourse or aquifer (e.g. river, creek, take, canal)
Name of water body, watercourse or aquifer (if known)
[ 1 Noosa Waters Canal
Table £ Complete if the premises are on Strategic Port Land under the Transport Infrastructure Act 1994
Lot on plan description for strategic port land Port Authority for the fot
[7
Table F Complete if the premises are in tidal water
fi
3. Indicate the total area of the premises on which the development is proposed: (Note: The total area may include tand both above and below water)
Name of local government for the tidal area (if applicable) Name of port authority for the tidal area (if applicable}
Total area of premises
820.00 (lm? []hectares (Tick applicable unit)
‘Existing use of the premises
4. Current use/s of the premises: (e.g. vacant land, house, townhouses, apartment building, shop, service station, school, sugar cane farming etc.)
[Tine ]
5. Are there any existing easements on the premises? (e.g. for vehicular access, electricity, overland flow, water etc.)?
4] No Cc Yes - Ensure the type, location and dimensions of each easement are included in plans, submitted with the application
[Proposal details
6. Brief description of the proposal (e.g. 6 unit apartment building, 30 lot residential subdivision, a bore, aquaculture)
Timber jetty
7. Does the poposal include new buildings or operational work (including any services) on the premises?
[No [XI Yes - Ensure the nature, location and dimensions of the proposed works are included in plans, submitted with the application
[Resource entitlement (i applicable} - further information is provided in the advice section at the end of the form ]
8. Does the application involve taking or interfering with a State resource and therefore require a resource entitlement? (e.g. the application
involves State land (leased and freehold), declared Fish Habitat areas, taking quarry material, taking or interfering with water under the Water Act 2000, etc.)
kK No -Go10Q9 oO Yes - Complete Table G - provide details for each evidence required on a separate row, if applicable. Evidence of resource
allocation or entitlement must be submitted with the application. You do not need to answer Q9 - go to the next section.
‘Owner's consent (i applicable) - further information is provided in the advice section at the end of the form
9. Complete Table H for applications involving a material change of use; reconfiguration of a lot; work on land below high-water mark and
not within a canal as defined under the Coastal! Protection and Management Act 1995; or work on rail corridor land defined under the
Transport Infrastructure Act 1994 - provide detaits for each owner on a Separate row, or on an attachment to this form if applicable.
Premises Owner's name/s Details of the premises owned | * Date consent
Table H and postal address (street address of fot on plan description) Owner's signature was obtained
1 Clifton Sim Ci- PO Box 299, Noosaville QLD 4566 23/06/2009
* Owner's signature cannot be provided on the form if you intend to submit the application electronically. Owner's consent bbs be provided to the assessment manager on an
attachment containing appropriate written documentation of the owner's consent. If the owner is a company, $127 of the Corporations Act 2007 (Cwealth) details how a
company may sign as owner. Templates for the provision of owner's consent afe available on the [PA website .
‘Attachments and supporting information (Complete Table! - Use a separate row for each type of attachment or information, including information required
under this Part) Please ensure all documentation submitted with this form, including other Parts of Form 1, or owner's consent, etc, are securely attached to this Part of the Form.
Description of attachment or information ‘Title fa ; 1 ars
‘ i ipplicable) Method of delivery to
Table { | feg. Pas c at Far 3 owner consent ovkionce of resource (e.g, General Authorty James Sireet Trai Report Date assessment manager
1 Part E 23-Jun-2009 | over the counter
2 Checklist 30-Jun-2009 | over the counter
Page 5
INTEGRATED PLANNING ACT 1997 Part A, Version 3.1, 3 March 2008
j3 | John Norden Plans |. 23-Jun-2009 ‘over the counter |
(Portable Long Service Leave (PLSL) levy (Applicable for centam dunking and construction work valued over $60,000 onl) |
10. The Portable Long Service Leave Levy (PLSL) is not applicable to this application if any of the following apply: ( Tick box if appticable)
[C1 the application seeks a preliminary approval onty;
(1 the application is not for building and construction work under the Building and Construction Industry (Portable Long Service
Leave) Act 1997, section 3AA (e.g. the application is only for a change of use. or for the foltowing types of work carried out solely for
farming purposes: land clearing, site preparation, earthworks, fences, fodder harvesting, clearing of encroaching vegetation, clearing of
regrowth, thinning vegetation or controlling weeds or pests);
{X] all costs, that relate to the work both directly and indirectly, are less than $80,000, inclusive of GST; or
(the work is being carried out under an owner-builder permit issued under the Queensiand Building Services Authority Act 1997 -
Complete and submit a QLeave Notification and Payment Form {no payment required if owner-builder permit number stated). The receipted form must be
Sighted by the assessment manager before a development permit can be given.
11. ls payment of a PLSL levy applicable to this application? (Refer to Q10 and the Advice below for more information)?
EX] No - Endof Pan A
(1 Yes - Answer Q12 below
OFFICE USE ONLY (For use by the Assessment Manager / Private Certifier) (Optional)
Receiving officer's Reference
Fee ($) a De | Datereceived| '5]7(o4 name PS n numbers OA /Ipo
Oo T
_ NOTIFICATION OF ENGAGEMENT OF PRIVATE CERTIFIER
To: Council. | have been engaged as the private certifier for the building work referred to in this application.
~ Date of
' = > :
engagement . Name ro BSA Certification number Building classification/s
QLEAVE NOTIFICATION AND PAYMENT (for completion by assessment manager or private centifier if applicable)
. Date receipted
Description of the work QLeave Project Number |Amcunt paid ($)] Date paid | rm Sahled by | Name ofofmcet who sighted te
ah managet.- fo. 9 eye
1
Privacy Statement
The information collected on Form 1 will be used by the Department of Infrastructure and Planning (DIP) in accordance with the processing and assessment of your Application,
Your personal details will not be disclosed for a purpose outside of the IDAS process, except where required by tegistation (including the Freedom of information Act 1992) or as
required by Parliament. This information may be stored in 2 DIP database. The information collected will be retained as required by the Public Records Act 2002,
Advice for completing Part A
General advice
. Part A of IDAS Development Application Form 1 must be completed and accompany all development applications. The applicant is responsible
for answering all questions fully and correctly, unless following a response there is a statement to go directly to another question. The
Assessment Manger may refuse to receive an application that is not properly made.
° The IDAS Assessment Checklist must also be completed for all development applications, other than those requiring assessment against the
Building Act 1975 only, i.e. those applications requiring the completion of Parts A and B only.
‘Applicant details
° \f the applicant is a company or organisation, a contact person must be nominated. The applicant's signature is not required to be provided
under the IPA.
Page 6
INTEGRATED PLANNING ACT 1997 Part A, Version 3.1, 3 March 2008 Details of the premises The term ‘premises’ is defined by the IPA, schedule 10 to mean a building or other structure, and land (whether or not a building or other structure is situated on the land). The term ‘land’ is also defined to include the estate in, on, over or under the land. Deiails of the land are not required if the application involves a mobile and temporary Environmentally Relevant Activity only. Instead complete Table A. The premises may be identified in a number of ways — « Street address and lot on plan are most common and will apply to most applications. » Coordinates may provide the best means of accurately identifying the location of development proposed in waters, or on a relatively small development site distant from property boundaries on a large tot. Sufficient coordinates need to be provided to identify the boundary of the premises the subject of the application. Eastings and northings using GDA94 datum is preferred, but longitude and latitude and other (specified) datum such as Zone Reference or GS84 may be provided. The definition of ‘water body’ and ‘watercourse’ can vary from Act to Act. StrategicPortLandis within a local government area but a local government's planning scheme does not apply onStrategicPortLand. StrategicPortLandis declared under the Transport infrastructure Act 1994. For further information go to IDAS Guide 11 (Development on strategic port land) and the Queensland Transport (Ports) website. “Tidal water is defined in the Coastal Protection and Management Act 1995 (Schedule) and ‘tidal area’ for a local government and for strategic port land is defined in the IPA (schedule 10). Generally, the area below “high-water mark’ (defined by the Coastal Act in relation to high water mark at spring tides) establishes the boundary of a tidal area. Land below high water mark is not within a local government's area unless provided for under the Local Government Act 1993. Unless otherwise provided for by legislation, a local government has no jurisdiction below high water mark. A tidal area for strategic port land is within the jurisdiction of the relevant port authority, while the Environmental Protection Agency generally has jurisdiction for a local government tidal area. However, the !PA gives local governments jurisdiction for assessing and deciding applications for prescribed tidal works within the local government tidal area, and the planning scheme may be applied to that assessment (to the extent provided for in the code for prescribed tidal work}. Resource entitlement Section 3.2.1(5) of the IPA requires evidence of resource entitlement be given for applications if they invoive taking or interfering with a prescribed State resource. Schedule 10 of the /ntegrated Planning Regulation 1998 (IPR) prescribes the State resources, including State- owned land, where evidence is required to be given, and the evidence required to support the application. Link to In Regulation. Section 3.2.1(10)(a)(i) states an application cannot be taken to be properly made without the required evidence. For applications involving the taking or interfering with water under the Water Act, the development application may be made at the same time as the request for resource entitlement, and the Department of Natural Resources and Water will accept the application as properly made. For State-controlled roads, a resource entitlement is not required for an activity that is exempt ancillary works or encroachment (identified by gazette notice under the Transport infrastructure Act 1994, section 50), or if the activity requires referral to the Department of Main Roads. Evidence may be required from more than one Department responsible for a State-owned resource, e.g. from the Environmental Protection Agency for quarry material below high water mark, and the Depariment of Naturat Resources and Water in relation to the State-owned land above high water mark. Owner's consent Section 3.2.1(3) of the IPA prescribes that an application must contain, or be supported by, the written consent of the land owners, if the application involves: a material change of use; reconfiguration of a lot; work on fand below high-water mark and not within a canal as defined under the Coastal Protection and Management Act 1995, or work on rail corridor land defined under the Transport infrastructure Act 1994. Evidence of this consent may need to be provided before the application will be accepted as properly made by the Assessment Manager, during the processes of the application or in the event of an appea! about the outcome of the application. “Owner for the purpose of a lodging an IDAS development application means the person at the time of lodging the application, entitled to receive the rent for the land (or would be entitled to receive the rent for it if it were let to a tenant at a rent). Templates are available from the IPA website for the provision of owner's consent as an attachment to this form. However other documentation may be used for providing owner's consent provided it is clear the documentation relates to the development application for the premises. Owner's consent, if required, must be provided even if the applicant is the owner. Owner's consent is not required for a mobile and temporary ERA. Portable Long Service Leave (PLSL) Levy The Building and Construction Industry Portable Long Service Leave Scheme provides long service leave entitlements to workers in the building and construction industry who would be unlikely to accrue enough service with one employer to qualify for ong service leave. To fund the scheme, a Portable Long Service Leave Levy (PLSL levy) is collected on certain building and construction work carried out inQueensiand. The PLSL levy amount and other prescribed percentages and rates for calculating the levy are stated in the Building and Construction Industry (Portable Long Service Leave) Regulation 2002. included in the amount collected by QLeave is the Workplace Health and Safety Fee and the Building and Construction IndustryTrainingLevy. The Building and Construction industry (Portable Long Service Leave) Act 1991 (PLSL Act) defines the building and construction work subject to the PLSL levy and includes renovating, relocating, constructing, altering, demolishing, maintaining or repairing buildings, pools, roads, jetties, pipelines, fences or earthworks, and works for subdividing, irrigating or draining land. The PLSL levy need not be paid when the application is made, but the PLSL Act requires the levy to be paid before a development permit may be issued. The Assessment Manager must sight an approved form Issued by QLeave advising of the status of the payment of the PLSL levy. Building and Construction Industry Notification and Payment Forms are available from anyQueensiandpost office or agency, on request from QLeave, or can be completed on the QLeave website at www.qleave.ald.gov.au. For further information contact QLeave (Tel: 1800 803 481 Web: www gleave.ald.gov.au )
Page 7
INTEGRATED PLANNING ACT 1897
[Nature of the works
4. Nature of work that requires assessment against a planning scheme:
Part E, Version 3.2
bx <<
RECEIVED
15 JUL 2099
“SCRO™ igwantin
= Front mr, “
Building &/or operational works assessa|
against a planning scheme!’
[LJ Building work - Complete Table A (XJ Operational work - Complete Table 8
Table B
(i) Whatis the nature of the operational work?
(CJ Roadworks (J Stormwater (2) Water infrastructure ([] Sewerage infrastructure
7] Landscaping ( Earthworks (C1 Drainage Works ([] Signage
[] Clearing vegetation under the planning scheme [X] Other - Specify below
Jetty
(ii) What type of approval is being sought? (NOTE: if you have indicated multiple operational works in question (i) above and your answers to this,
question would be different for different operational work, it may be more appropriate to provide these details in an attachment to this form)
[X] Development Permit (7) Preliminary approval (] Both (Specify below)
(iil) Is the operational work necessary to facilitate the creation of new lots (ie. subdivision)?
EX} No [Yes - Specify the number of lots being created
(iv) Are there any current approvals associated with this application? (e.g. Development Permit or Preliminary Approval for MCU or reconfiguring
alot)
DB No [[] Yes - Complete Table B(a)
@ 2. Whatis the dollar value of this operational work? (ie. the total value including GST, materials and labour) 1$ 15000
[Mandatory Information °°” oo ; — ]
3. Confirm that the following mandatory information accompanies this application
Confirmation of: .
lodgément ~~ Method of lodgement
vane if applicable, showing the nature and tocation of the proposed works finctuding the Confirmed _ | over the counter
OFFICE USE ONLY
Date Received Reference Numbers |
Advice for completing Part E
General advice
Part A must also be completed for alt IDAS development applications.
The applicant is responsible for answering all questions fully and correctly, untess following a response there is a statement to go directly to another question.
Qt
A development penmit authorises development to occur, while a pretiminary approval is a step in the approval process and does not authorise development to occur
Page 8
INTEGRATED PLANNING ACT 1997 Part E, Version 3.2 1 This form is also used for building or operational work assessable against the land use plan for Caims airport land or Mackay airport land. Wherever planning scheme is mentioned, take it to mean the land use plan for the airport land.
Page 9
INTEGRATED PLANNING ACT 1997 IDAS Assessment Checklist, Version 22
RECEIVED
LSE sur 2099
A. sere
—— front ae
>
wy
wn
a0)
Wn
a
3
CD
—
~~
CS
_"
@
wantin
1997 IPA}. Form 1 is made up of various Parts.
Part A (Common details) of Form 1 must be compfeted for all apptications. The relevance of other Parts of Form 1 depends on
the nature of the application.
Farm 1 also includes this IDAS Assessment Checklist, which is used to assist in determining State assessment and referral
requirements, and the Parts of Form 1 relevant to the application.
Section 1 and all other relevant sections of the IDAS Assé&shent Checklist; as-identified-in-the-Fable-below,.must be... _|
completed for all development applications except those proposed on land in an urban development area, or for building work
requiring assessment against the Building Act 1975 only.
For more information about development applications on land in an urban development area, refer to www-ulda.qid,gov.au.
For more advice about building applications refer to Part B of the IDAS Application Form.
Answering the following questions will assist you in determining which sections of the checklist must be completed for your application. If
unsure, phone or visit your local government or log onto the DIP website www.dip.qid goy.au for help
For all IDAS development applications (except those for building work requiring assessment against the Building Act 1975 only) - complete Section 1 of this
checklist
Does the application seek approval to make a material change of use of the premises?
if yes - complete Section 2 of this checklist
Yes |JNo
Does the application seek approval to reconfigure a lot?
if yes - complete Section 3 of this checklist and Part F of IDAS Application Form 1. If the premises are completely within a single |[_] Yes |—XJNo
local government area assessment is by the local government.
Does the application seek approval to carry out operational work?
if yes - complete Section 4 of this checklist IxlYes |LINo
Does the application seek approval to carry out building work requiring assessment against the Fisheries Act 1994?
Yes [[X]No
if yes - complete Section 5 of this checklist q w
Have you received a referral agency response under section 3.3.2.of the IPA, in relation to this development application?
if yes - complete Section 6 of this checklist Des }fJNo
Does the application seek approval to carry out building work requiring assessment against a local government planning
scheme? {Yes |CINo
if yes - complete Form 7 Part E of IDAS Application Form 1. Assessment is by the local government.
Does the application seek approval to carry out building work requiring assessment against the Building Act 1975?
if yes - go to Appendix 1 of this checklist for advice on building referrals. Complete Part B of IDAS Application Form 1. (Yes |RINo
Assessment is by a building certifier
Do you wish the application to be assessed against a superseded planning scheme?
if yes - complete Form 1 Attachment 1 CYes |fJNo
is the application for development completely or partly on Cairns and Mackay airport land under the Airport Assets
(Restructuring and Disposal) Act 2008?
if yes - Assessment is by the Department of Infrastructure and Planning. Complete Form 1 Part D of IDAS Application Form 1 ifthe |[1Yes |XINo
application is for a material change of use, and Part E if for building or operational work. Also, the application must be referred to the
local gavemment as Advice Agency.
Page 10
INTEGRATED PLANNING ACT 1997 IDAS Assessment Checklist, Version 22
s SEC } TON 1 Section 1 must be completed for all applications that require completion of the IDAS Assessment Checklist.
a a ane
HERITAGE
141A {s any part of the proposal intended to be cared out o ona Queensland heritage place under the Queensland Heritage Act 1992?
IX] No-Gotor78 =] Yes
IPA schedule 8 pac 1 table 5, item 7 1 Regulation schedule 2, table 2. wern 18.
1.1B Does the proposal involve development intended to be carried out on a place entered in a local heritage register under part 11 of
the Queensland Heritage Act 1992, other than if the place is on Caims or Mackay airport land?
[X] No-Gotoarz2 [[] Yes
IPA, schedule 8, part 1, table 5, tom 2A, IP Regulavon, schedule 7. part 2 table $, tem 2
iREMOVING QUARRY MATERIAL; WILD RIVER AREA \
4.2 Does the proposal involve removing quarry material from a watercourse or lake as defined under the Water Act 2000?
[X] No -Gotoar3 (] Yes
IPA, schedule 8, part 1, table 5, item 1; IP Regulation, schedule 2, table 2, item 11; 1P Requlation, schedule 1, table 5, item 2 (wild river area): Water Act 2000,
section 966C, Wild Rivers Act 2005, section 43A
[ENVIRONMENTALLY RELEVANT ACTIVITY; WILD RIVER AREA
i
po
4.3 Does the proposal involve an environmentally relevant activity (ERA), other than a mining activity or a petroleum activity?
[XK] No-Gowai4 [J Yes
IPA, schedule 8, part 1, table 2, tem 1; IPA, schedule 8, part }, table 5, items 3 and 4: IP Regulation, schedule 2, table 2, items 7 and 23; Environmental Protection Act 1994, section
73AA (enld nver area): Wild Rivers Act 2005, section 43A, relevant wild river declaration: Wild Rivers Code.
[WITHIN THE LIMITS OF A PORT ]
14 Is any part of the premises within the limits of a port under the Transport Infrastructure Act 1994?
No - Got0.Q1.5
(I Yes
IP Regulation, schedule 2, table 2. items 15 and 16
\DECLARED FISH HABITAT AREA |
15 Does any part of the premises adjoin a declared fish habitat area under the Fisheries Act 1994?
[X] No - Goto 01.6
(Yes - if answers to questions in other sections of this checklist indicate that the proposed development is assessable under IPA, schedule
8, this application requires assessment by the Department of Primary industries and Fisheries (DPI&F). If DPI&F is not the
Assessinent Manager for the application, the agency has jurisdiction as Advice Agency.
JP Regulation, schedule 2, lable 2, tem 26
COMMUNITY INFRASTRUCTURE
‘ . we ree ee
1.6 \s any part of the premises designated for community infrastructure?
IX] No -Got0.a1.7
(Yes
IP Regulation, schedule 2, table 3. item 7
WASTE WATER MANAGEMENT ~ — “j
17 Does the proposal involve the establishment or expansion of a waste water disposal system?
No - End of Section? [_] Yes
IP Regulation, schedule 2, table 3, tem 5
Page 11
INTEGRATED PLANNING ACT 1997 IDAS Assessment Checklist, Version 22
ECTION 4. Section 4 must be _— when the arena seeks approval to carry out operational work,
PLANNING SCHEME ee 7
44 Is the proposed operational work assessable under any State planning regulatory provisions?
No [] Yes
If no, is the proposed operational work assessable under the planning scheme?
O No - Goto O42 {X] Yes - Complete Form 1, Part € and answer Q4.1.1- 4.1.7 below
'STATE-CONTROLLED ROAD oT - ~ 7
4.1.1 Is any part of the premises located i in part of a future State-controlled road, or within 400m of a State-controlled road?
[XJNo [] Yes
If no, is the proposed operational work for filling or excavating listed in integrated Planning Requiation 1998,
schedule 5 and does it exceed the threshold?
BX] No -Got00422
oO Yes - This application must be referred to the Department of Main Roads (DMR) as Concurrence Agency.
IP Regulation, schedule 2, table 3, item 3; 1P Regulation, schedule 2, table 3, tem 1(b)
(ACID SULFATE SOILS ~~ ~ SS SSS = ——
ee ae
1
4.1.2 Is any of the operational work proposed in a !ocal government area listed*! in State Planning Policy 2/02: Planning and Managing
Development Involving Acid Sulfate Soils
—X] No -Go10 04.1.3 OO Yes
4 \purukun, Bowen, Brisbane, Broadsound, Bundaberg, Burdekin, Burke, Bumett, Caboolture, Cairns, Calliope, Caloundra, Cardwell, Carpentaria, Cook, Cooloola, Douglas,
Fitzroy, Gladstone, Gold Coast, Hervey Bay, Hinchinbrook, Isis, Johnstone, Livingstone, Logan, Mackay, Maroochy, Maryborough, Mirium Vale, Momington, Noosa, Pine Rivers,
Reddiiffe, Redland, Rockhampton, Sarina, Thuringowa, Tiaro, Torres, Townsville, Whitsunday
IP Regulation, schedule 2, table 3, item 4; State Planning Policy 2/02: Planning and Managing Devetopment involving Acid Sulfate Soils, section 3.6
‘EASEMENTS AND SUBSTATIONS Wee ee ]
41.3 |s any of the proposed operational work for filling or excavation?
No -GotoQ4.1.4
C] Yes
IP Regulation, schedule 2, table 3 item T0(a); IP? Regulation, schedule 2, table 3, tem 10(b)
4.1.4 |s any part of the premises subject to an easement in favour of the holder of Pipeline Licence Number 1 issued under the
Petroleum Act 1923 for the construction or operation of the Moonie to Brisbane strategic pipeline under that Act?
BX] No -Gowas15 [_] Yes
IP Regulation. schedule 2, table 3, item 17
‘PUBLIC PASSENGER TRANSPORT
4.1.5 Is any of the proposed operational work listed i in schedule 13C of the integrated Planning Regulation 1998 and does it exceed the
specified threshold?
DX] No- Goto 04.7.6 (1 Yes - This application must be referred to QueenslandTransport (QT) as Concurrence Agency.
IP Regulation, schedule 2, table 3, item 14
[RAILWAY SAFETY AND EFFICIENCY ~]
4.1.6 ts any of the proposed operational work listed in schedule 13D of the integrated Planning Regulation 1998 and does it exceed the
specified threshold?
DX] No- Go to 04.1.7 (1 Yes - This application must be referred to QueenslandTransport (QT) as Concurrence Agency.
IP Regulation, schedule 2, table 3, lem 15
KOALA CONSERVATION (outside SEQ urban footprint) “]
4.1.7 Is any part of the premises in a koala conservation area or koala sustainability area, other than in an SEQ urban footprint area?
No -Gotas2 {[—] Yes
IP Regulation, schedule 2, table 3, item 19
Page 12
INTEGRATED PLANNING ACT 1997 IDAS Assessment Checklist, Version 22
WILD RIVER AREA - - Although legislation provides for assessment of operational works for residential, “commercial and industrial
‘development for the purposes of the Wild Rivers Act 2005, currently no declarations for any of the wild river areas apply the Wild Rivers
code to that type of f development.
‘ASSOCIATED WITH RECONFIGURING A LOT; RESIDENTIAL, COMMERCIAL OR INDUSTRIAL DEVELOPMENT IN A WILD RIVER
|AREA
42 is any of the proposed ‘operational work ‘associated with reconfiguring alot and the reconfiguration i is also assessable?
[XJ No -Gotoas3 ([]} Yes
IPA, schedule 8, part 1, table 4, tem 2 IP Regulation. schedule 1, part 2. table 3, tem Tc}
Wild Rivers cade (Note: the code does nat currently contain applicable provisions for residential, ndusirial or commercial developmeni inside a designated urban
area)
(KOALA CONSERVATION (Inside SEQ urban footprint) oT eee “]
4.3A Is any part of the premises in an interim koala habitat protection area?
EX} No -Go10438 [] Yes
IP Regulation, schedule 2, table 2. item 34A
VEGETATION CLEARING; KOALA CONSERVATION; WILD RIVER AREA |
4.3B Is any of the proposed operational work for the clearing of native vegetation to which the Vegetation Management Act 1999
applies?
DX] No -Goroas4 [_] Yes
IPA, schedule 8, part 1. table 4, items 1A-1G; IP Regulation, schedule 2, table 2, item 5 (vegetation clearing); IP Regulation, schedule 2, table 2, item 34 (koala
conservation); IP Regulation, schedule 1, part 3. table 4, item (vegetation clearing/wild river area); Vegetation Management Act 1999, section 22A (vegetation
clearing/wild river area); Wild Rivers Act 2005, sections 31F and 43A
iTAKING OR INTERFERING WITH WATER; WILD RIVER AREA . |
44 Is any of the proposed operational work for any thing constructed or installed that allows, under the Water Act 2000, for taking or
interfering with water from a watercourse, lake or spring (other than using a water truck to pump water, and other than under
the Water Act 2000, section 20(2), (3) or (5)), or from a dam constructed on a watercourse or lake?
[X} No -Gotoass [_] Yes - Answer (a) and (b) below
IPA, schedule 8, part 1, table 4, items 3(a); IP Regulation, schedule 2, table 2, item 8; IP Regulation, schedule 1, part 3, table 4, itemns 3 and 3A; Water Act 2000. section 966A (wild river
area); Wild Rivers Act 2005, section 43A; relevant wild river declaration; Wild Rivers Code
45 Is any of the proposed operational work for any thing constructed or installed that allows, under the Wafer Act 2000, for taking or
interfering with artesian water (other than using a water truck to pump water)?
i] No Goto Q4.6 Oo Yes - (Complete Form 1, Part K,) This application requires assessment by the Department of Natural Resources and Water
(NRW). if NRW is not the Assessment Manager for the application, the agency has jurisdiction as Concurrence Agency.
IPA, schedule 8. part 1, table 4, item 3(b}; 1P Requlation, schedule 2, table 2, item 8; iP Regulation, schedule 1. part 3, table 4, item 3
Wild Rivers code (Note: the code does not currently contain applicable provisions for taking or interfering with artesian water)
46 Is any of the proposed operational work for any thing constructed or installed that allows, under the Water Act 2000, for taking
overland flow water (other than using a water truck to pump water)?
[EX] No -Gotoas7 [[] Yes - Answer (a) and (b) below
IPA, schedule 8, part I, table 4, item 3(¢}{i): iP Regulation, schedule 2, table 2, itein 8: IP Regulation, schedwle 1, part 3, table 4. tem 3: Water Act 2000, section 966A (wild river area):
Wild Rivers Act 2005, section 43A; relevant wild river declaration; Wild Rivers Code.
47 Is any of the proposed operational work for any thing constructed or installed that allows, under the Water Act 2000, for taking or
interfering with subartesian water (other than using a water truck to pump water}?
[EX] No -Gowoss [(] Yes
IPA, schedule 8, part 1, table 4, item 3{c}{il); iP Regulation, schedule 2, table 2, item 8: IP Regulation, schedule 1. part 3, table 4, item 3
Water Act 2000, section 966A {wild river area)(Note: no current Wild River declaration identifies taking or intertering with subartesian water as assessable}
Witd River code (Note: the code does not currently contain applicable provisions for sub artesian water)
48 Does any of the proposed operational work for any thing constructed or installed that allows, under the Water Act 2000, for
interfering with overland flow water (other than using a water truck to pump water)?
[XJ] No -Gotoas9 [_] Yes - Answer both (a) and (b) below
IPA, schedule 8, part 1. table 4, items 3(c}fi) and 3{d}: IP Reguiation, schedule 2. table 2, tem 9: IP Regulavon, schedule 1, part 3. table 4, item 3A, Water Act 2000, section 9668 {wilt
fiver afea), relevant wild iver declaration, Wild Rivers Cade.
Page 13
INTEGRATED PLANNING ACT 1997 IDAS Assessment Checklist, Version 22 49 is the proposed operational work for the following? (i) For the construction of a referable dam as defined under the Water Supply (Safety and Reliability) ‘Act 2008 & No C Yes (ii) To increase the storage capacity of a referable dam by more than 10% No [ Yes If yes to either or both (i) or (ii) above - (Complete Form 7, Part Ks) This application requires assessment by the Department of Natural Resources and Water (NRW). if NRW is not the Assessment Manager for the application, the agency has jurisdiction as Concurrence Agency. IPA, schedule 8, part 7 table 4, iter 4 IP Regulauon. schedule 2. table 2. tem 10 (TIDAL WORK; WILD RIVER AREA 4.10 Is any of the proposed operational work tidal work, other than excluded work defined under the IPA? [XJ No -Gotoa4.11 ((] Yes - Answer (a) and (b) below IPA, schedule 8, part 1, table 4, item 5; IP Regulation, schedule 2, table 2, items 12, 14 and 17; IP Regulation, schedule 1, part 3, table 4, items 4A and 5 Coastal Protection and Management Act 1995, section 104A (wild river area) COASTAL MANAGEMENT DISTRICT; WILD RIVER AREA i 4.14 Is any of the operational work proposed to be carried out within a coastal management district? [] No -Gotoas12 [_] Yes IPA, schedule 8, part 1, table 4, item 5; IP Regulation, schedule 2, table 2, items 12 and 14; iP Regulation, schedule 1, part 3, table 4, items 4A and § Coastal Protection and Management Act 1995 Act 1995, section 104A (wild river area); Wild Rivers Act 2005, section 43A |WATERWAY BARRIER WORKS; WILD RIVER AREA | 4.12 Is any of the proposed operational work for constructing or raising waterway barrier works under the Fisheries Act 1994? BX] No -Gotoas13 ([] Yes IPA, schedule 8, part 1, table 4 item & IPA. schedule 8, part 7, table 4. item 2. Fisheries Regulation 195 $113A (self assessable codes); IP Reguiation, schodule 2, table 2. tem 28, IP Reguiauon, schedule J, part 3, table 4, item 6; Fisheries Act 1994, section 76D (wild aver area); Wild Rivers Act 2005, secinn 13. DECLARED FISH HABITAT AREA; WILD RIVER AREA 43 Is any of the operational work proposed to be carried out completely or partly within a declared fish habitat area under the Fisheries Act 1994? DX] No - Gotoa4.t4 C1 Yes IPA, schedule 8, part 1, table 4, item 7: IPA, schedule 8, part 2, table 4, item 3; Fisheries Regulation 1995 113A (sell-assessable codes); IP Regulation, schedule 2, table 2, itom 25; IP Regutation, schedule 1, part 3, table 4, itein 7; Wild Rwers Act 2005, sections 43A; Fisheries Act, section 76DC (wild river area). Fone ey |REMOVAL, DESTRUCTION OR DAMAGE OF A MARINE PLANT; WILD RIVER AREA 4.14 Is any of the proposed operational work removing, destroying or damaging marine plants under the Fisheries Act 19947 [X] No -Gowa415 ((] Yes IPA, schedule 8 part 1. table 4, item 8 IPA, schedule 8. part 2, table 4. fer 4: Fishenes Regulation 1995 $113A (self-assessabie codes): IP Regulation, schedule 2, table 2. tem 79: 1P Regulation schedtle 1. part 3. table 4, item 8, Fishones Act 1994, section 7608 (wld nver areay: Wild Rivers Act 2008, section 43A° retevanl wild river declaration, Wild Rivers Code (WILDRIVERAREA } 4.15 \s any of the operational work proposed to be carried out in a wild river area declared under the Wild River Act 2005? [X] No -Gowoas1e [7] Yes IPA, schedule 8, part 1, table 4, lem 10; iP Regulation, schedule 2, table 2, item 37; Wild Rivers Act 2005, sections 42, 43A STATE-CONTROLLEDROAD ] 4.16 Is any part of the premises located in pat of a future State-controlled road, or within 100m of a State-controlled road? [X] No -Endofsection 4 [] Yes IP Regulation, schedule 2, table 2, tem 3
Page 14
INTEGRATED PLANNING ACT 1997 IDAS Assessment Checklist, Version 22
Disclaimer:
While the Department of Infrastructure and Planning (DIP) believes that this information contained on this form and provided as part of
this process will be of assistance to you, it is provided on the basis that you will not rely on the information without first making your own
enquiries regarding the interpretation and application of the applicable legislation to your circumstances.
To the full extent permitted by law DIP expressty disclaims all liability (including but not limited to liability for negligence) for errors or
omissions of any kind or for any loss {including direct and indirect losses), damage or other consequence which may arise from your
reliance on this process and the information contained on this form.
Page 15
Su nshine Coast LAND USE SECTION FEES
Regional Council
RECEIPT TYPE
SALE OF DOCUMENTS
Superseded Planning Scheme Documentation 520
Copy of Permit/Approval Letter 110
The Noosa Plan Documentation . 111
APPLICATION FEES
: { — Material Change of Use - Code/lmpact /
\ . ¢ Consistent - a §21
Inconsistent : st 521
Assessment under Superseded Planning Scheme mo 521°
. Modification to a Development Permit | 824
‘i : Extension of a Currency Period / . : , 521°
ve : Operational ‘Works - Landscaping . - 524
Ot _.Bldg Work assessable against the Planning Scheme — : 521
PRE LODGEMENT REVIEW , . ” .
Half Hour , / ae a . 522
One Hour -- poe : ws : 522:
ADVERTISING vl. ut
Purchase Advertised Applications: - . : . $23 i
eee ay : . re ey ec) ~ . . . , , . : ey
JeTTies) 7
“Jetty ApplicationFee . D2. 524
JettyBond + ‘ Se a . _Se 2. 51
Bo, / cor Stas a : , , (Category 4)
BONDS oe yo, ‘ ‘ . -
* Performance Bond. : . : , 1,
os : oo (Category 9) .
’ SIGNS : . . f° ;
Registration Fee oo : : ' . 222 .
. . . . . %
s RCH FEE’ . . . . ,
Search of Land Use Section'file. . 112 a
, / Liquor Licensing Request mo : oo 1130; 4
’ . * \
ve TOTAL $ JizZo . . y
“NAME: (© Sune NI Catuvadvra
ADDRESS: of ~~ KeBes0. feAha Bre chet |
* : PO Bore 2h moO Sele
.-FILENO: OF Fun DATE: 222 [09 ro.
RECEIPTNO: <S.2- 2-7 ~7—f ,-_ Signature of TP Officer: (> rene nne _
- AUTHORITY NO: . a
; . hes 2 Wat nde Ch.
l4{ 209 / Ayo [i
Page 16
CALCULATION OF FEES
arn “,
APPLICATION FEE
TOTAL
FEES
MCU - CODE ASSESSMENT
Details of Development
1 {Consistent 1.0
Inconsistent 3.0
FEE CALCULATION
Details of Development
Consistent 1.0
Inconsistent 3.0
FEE CALCULATION
{OPERATIONAL WORKS
Details of Development
FEE CALCULATION
e
TOTAL FEES. —..
- a ee -
Page 17
NOTES:
1. UNLESS NOTED OTHERWISE ALL TIMBER SHALL BE
DURABILITY CLASS 1 OF APPROVED SPECIES AND HAVE
A STRESS GRADE OF F14 MIN.
2. UNLESS NOTED OTHERWISE ALL CONSTRUCTION SHALL
COMPLY WITH THE ENVIRONMENTAL PROTECTION AGENCYS'
OPERATIONAL POLICY - "BUILDING AND ENGINEERING
STANDARDS FOR TIDAL WORKS."
3. ALL STAINLESS STEEL BOLTS, RODS, ETC., SHALL BE
APPROVED MARINE GRADE 316. ALL OTHER STEELWORK
DETAIL - : - INCLUDING NUTS, BOLTS, WASHERS, SCREWS, NAILS, ETC.,
5 SHALL BE HOT DIPPED GALVANISED OR STAINLESS STEEL.
4. TOP OF PILES SHALL BE SEALED AND FULLY CAP FLASHED
OR RINGED.
5. DIMENSIONS AND LEVELS SHALL NOT BE SCALED FROM
SECTION/A) THE DRAWINGS.
etn)
160 x 75 HW
10 PL. ANGLE BRACKET
R 20416 846 TO EACH MEMBER
200 x 75 HWO
DETAIL ( 2 \
LOT 759
No.3
WATERSIDE COURT
NOOSA WATERS
RABRINK PTY LTD T/A
John Norden
& Associates
£04010 269 07_
Stresteel | Crd Design Enginewe
JETTY USE:
SINGLE USER, PRIVATE
NO VEHICULAR ACCESS
WALKWAY DECK VERTICAL
DESIGN LIVE LOAD - 2.0 kPa
MAXIMUM MOORED VESSEL - 5m DETAIL
BERTHING VELOCITY - 0.5 m/sec
2M16 SS
150 x76 HWO ——_—___
woven ons
"o086.2 [
Page 18
L-98/60 +—}+_} oe
oud ONDRIOM ~ | LONOAVI
ONINVYS
a NV1d ALIS : .
woe ane NOLHEV 8 — HOU ALNNOS ALL 5
VaASM Sted aasodoud ——=—I
ava weaved 796906deY
wes 652 LOT > EAE ofRS j |
CLLAOPHG £0 PS LELLOPOD £0 Ad .
emer Set EF qn NOuanoeaa we) we g
ereuiug eteeg he) | PeueRAS
sezyejoossy PF Sa10d OM
uepionuyor ane
SYSLVM VSOON ona waais
LYNOD AGISUSLVM SSTINIVIS OMAL HLM y
CON GMA ria S01 x oC ; I
6$2 101 DNOau | §
ALLar aasodoud | : 4p ;
WIS ‘DS af more a8 '. .
fai ao ore een % 682 101 : g 8 |
"esezs oncom cao Ns GUO a 4 | :
suaqiina | SNOIS 40 UVINO 38 O1 SIT ;
ALLSf VSOON ~~ _H f
sv ormcvre ry
QL Ald 1rd | 5
he _ woe he |
i ames som ner sinew:
: i" i orn
_ @NOMLVASITS ° hee *°
3 LUNOD 3aQisuaivm L NOILVAS 14
| 8
r
—{ | " 3009 ONMid - 6912 SV HLIM
| ——~S2v BONVTYOOOV NI CaTIVSN! 39 TVS sate ay
| ¥ GOOMGYVH G3AONddY 38 TIVHS S31d Tv
‘S3Nd
: ae : , GHV 990 Ta NALLY WNWININ |
—«wvom SX = GHV OT Ta
OHV 0" TY OHV 0'L Td 30
(venemard 3088 3NO 01 TIWM 30 dOL TIVM 40 dOL
” OHV 007 TY T3A31 dOO1s GacuOose WANIXVN |
Used in these records
09/0940 - Op works - Jetty [As Published]Related documentApplication case desk ↗
About this file
- File size
- 1.1 MB (small file)
- File type
No other editions are linked here.