2212-32645 SRA_Response with conditions__MCU22-0207_OPW22-0314

Attached to the e-mail MCU22/0207 and OPW22/0314 - SRA application correspondence - SARA referral agency response—24 Wesley Court, Noosa Heads.

of 6

Page text shows just the words. Original shows the document exactly as it was published.

RA6-N




SARA reference:        2212-32645 SRA
Council reference:     MCU22/0207 and OPW22/0314
Applicant reference:   DA0009/22

15 March 2023

Chief Executive Officer
Noosa Shire Council
PO Box 141
Tewantin QLD 4565
[email protected]

Attention:       Mark Lewis


Dear Mr Lewis


SARA referral agency response—24 Wesley Court, Noosa
Heads
(Referral agency response given under section 56 of the Planning Act 2016)

The development application described below was confirmed as properly referred by the State
Assessment and Referral Agency (SARA) on 24 February 2023.


Response
Outcome:                            Referral agency response – with conditions
Date of response:                   15 March 2023
Conditions:                         The conditions in Attachment 1 must be attached to any
                                    development approval
Advice:                             Advice to the applicant is in Attachment 2
Reasons:                            The reasons for the referral agency response are in Attachment 3


Development details

Description:                        Development permit         Operational work for tidal works or works in
                                                               a coastal management district (jetty)

SARA role:                         Referral agency
SARA trigger:                      Schedule 10, Part 17, Division 3, Subdivision 2, Table 1 (Planning
                                   Regulation 2017)

                                                                             South East Queensland (North) regional
                                                                             office
                                                                             Level 4, Foundation Place 3 South Sea
                                                                             Islander Way, Maroochydore
 Page 1 of 6                                                                 PO Box 1129, Maroochydore QLD 4558
Log in to download the original file

2212-32645 SRA_Response with conditions__MCU22-0207_OPW22-0314.pdf · 230 KB (small file)

Full text of the other 5 pages

Page 2

                                                                                                2212-32645 SRA




                                        Operational works for maritime safety and development
SARA reference:                         2212-32645 SRA
Assessment manager:                     Noosa Shire Council
Street address:                         24 Wesley Court, Noosa Heads
Real property description:              Lot 45 on N21844
Applicant name:                         Robert & Catherine Matyr
Applicant contact details:               PO BOX 404
                                         Aspley QLD 4034
                                         [email protected]
Human Rights Act 2019                   A consideration of the 23 fundamental human rights protected under
considerations:                         the Human Rights Act 2019 has been undertaken as part of this
                                        decision. It has been determined that this decision does not limit
                                        human rights.


Representations
An applicant may make representations to a concurrence agency, at any time before the application is
decided, about changing a matter in the referral agency response (s.30 Development Assessment
Rules). Copies of the relevant provisions are in Attachment 4.

A copy of this response has been sent to the applicant for their information.

For further information please contact Rosanna Nobile, Graduate Planner, on 07 5352 9777 or via email
[email protected] who will be pleased to assist.

Yours sincerely




Garth Nolan
Manager (Planning)

cc      Robert & Catherine Matyr, [email protected]

enc     Attachment 1 - Referral agency conditions
        Attachment 2 - Advice to the applicant
        Attachment 3 - Reasons for referral agency response
        Attachment 4 - Representations about a referral agency response provisions
        Attachment 5 - Documents referenced in conditions




 State Assessment and Referral Agency                                                              Page 2 of 6

Page 3

                                                                                                    2212-32645 SRA




Attachment 1—Referral agency conditions
(Under section 56(1)(b)(i) of the Planning Act 2016 the following conditions must be attached to any development
approval relating to this application) (Copies of the documents referenced below are found at Attachment 5)


 No.     Conditions                                                                     Condition timing
 Development Permit – Operational Works
 Schedule 10, Part 17, Division 3, Subdivision 2, Item 1 – Tidal works or work within a coastal
 management district. The chief executive administering the Planning Act 2016 nominates the Director-
 General of the Department of Transport and Main Roads to be the enforcement authority for the
 development to which this development approval relates for the administration and enforcement of any
 matter relating to the following conditions:
 1.      The works must be carried out generally in accordance with the                 For the duration of
         following plans:                                                               works.

              (a) plans prepared by Lindsay Consulting dated 16/02/2023,
                  reference 22-0632-F3, revision B.
 2.      Internal user note: this condition applies for lighting during                 For the duration of
         construction and operation.                                                    works and for operation
                                                                                        to be maintained at all
              (a) Light/mark all vessels, structures, plant and equipment
                                                                                        times.
                  associated with:
                  i.       the works, in accordance with the following
                           specifications:
                           - any anchors deployed must be marked with
                               yellow buoys and fitted with FL yellow lights
                               fitted.
                  ii.      operations, in accordance with the following
                           specifications:
                           - provide pedestrian style lighting for jetty or
                               retroreflective tape to outer beacon pile or jetty
                               face
              (b) Lighting provided must not obscure, disguise or otherwise
                  interfere with the safe navigation of other vessels, including
                  the effectiveness of navigational lighting.




 State Assessment and Referral Agency                                                                   Page 3 of 6

Page 4

                                                                                         2212-32645 SRA




Attachment 2—Advice to the applicant

General advice
1.      Terms and phrases used in this document are defined in the Planning Act 2016, its regulation
        or the State Development Assessment Provisions (SDAP) (version 3.0). If a word remains
        undefined it has its ordinary meaning.
Ref.    PO4 – Obstruction to navigation
2.      Any vessel moored to jetty must not encroach on navigation corridor.




State Assessment and Referral Agency                                                         Page 4 of 6

Page 5

                                                                                       2212-32645 SRA




Attachment 3—Reasons for referral agency response
(Given under section 56(7) of the Planning Act 2016)

The reasons for the SARA’s decision are:
 The proposal is for a development permit for operational works to construct a jetty
 The subject site is located in maritime safety and development.
 SARA assessed the development application against State code 7: Maritime safety of the SDAP,
   version 3.0 and determined that with conditions, the development achieves compliance with the
   performance outcomes of the State code.

Material used in the assessment of the application:
 the development application material and submitted plans
 Planning Act 2016
 Planning Regulation 2017
 the SDAP (version 3.0), as published by SARA
 the Development Assessment Rules
 SARA DA Mapping system
 section 58 of the Human Rights Act 2019



Attachment 4—Representations about a referral agency response
provisions
(page left intentionally blank)




 State Assessment and Referral Agency                                                     Page 5 of 6

Page 6

                                                  2212-32645 SRA




Attachment 5—Documents referenced in conditions
(page left intentionally blank)




 State Assessment and Referral Agency                Page 6 of 6

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.