4. ASSESSMENT MANAGER CONDITIONS
Approved Plans
1. Development undertaken in accordance with this approval must generally comply with the
approved plans of development. The approved plans are prepared by DBI Architecture and
are listed in the following table:
Plan No. Rev. Plan / Document Name Date
9.1 - Lower Ground Level - Site Plan -
9.2 - Ground Level - Site Plan -
9.3 - Level 2 - Site Plan -
9.4 - Level 3 - Site Plan -
9.5 - Level 4 - Site Plan -
9.6 - Survey & Building Heights Detail – Site Plan -
9.12 - Elevations -
9.12 - Elevations -
and as may be amended by the conditions herein.
General
2. All relevant conditions of Development Permit 23118 DA and the approved Management
Plans for the site shall be complied with prior to the commencement of the approved use.
3. The development must be undertaken and operated in a manner that causes no detrimental
effect upon the amenity of the neighbourhood by reason of the creation of excessive noise,
lighting nuisance or other emissions.
4. The buildings shall be finished in natural, muted tones as generally indicated on the
architectural renderings - Drawings “9.12 Elevations”.
Building Height
5. The finished height of the building, including any rooftop plant or structures, shall not exceed
15 metres above natural and finished ground levels.
6. A verification survey of the building is to be carried out by a Licensed Surveyor and a
certificate lodged with Council at completion of work confirming compliance with the
maximum allowable building height as required by either the conditions of approval or the
Planning Scheme.
Energy & Water Efficiency
7. All hot water systems installed shall be either solar systems; electric heat pump systems; or
gas systems (LPG or natural).
8. All new kitchen, laundry and bathroom fittings shall comply with the AAA Water Conservation
Rating System as defined by the AS/NZS 6400 (Water Efficient Products - Rating and
Labelling 2003) and AS/NZS 3500 (National Plumbing and Drainage Standard Part 1.2), or
current equivalent standards as may apply, with toilets to comply with the AAAA Water
Conservation Rating System. All new tap ware and shower roses shall not exceed a
maximum flow of 9 litres per min. Dishwashers and washing machines are excluded from
this requirement.
Page 2 of 24
Document Set ID: 20945331
Version: 4, Version Date: 07/08/2019 Print Date: 8 August 2019, 8:59 AM
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Attachment A - Existing Approval.pdfRelated documentApplication case desk ↗
About this file
- File size
- 2.3 MB (large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take up to a minute.