Appendix 2 - Code Assessment

of 53

Page text shows just the words. Original shows the document exactly as it was published.

  Water management
  PO6                                                            AO6                                                          Compliant
  Waste storage areas are designed to contain and                The waste storage area is constructed of impermeable and     The proposed waste storage area will be connected to
  appropriately dispose of leakage from bins and wastewater      durable surfaces and:                                        sewer for appropriate drainage.
  from bin washing.                                               a) is bunded and graded so that washwater and bin
                                                                      leakage are drained to the sewer or an on-
                                                                      site effluent disposal system via a gully within the
                                                                      storage area;
                                                                  b) has a bund wall with a maximum height of 100
                                                                      millimetres;
                                                                  c) is serviced by a conveniently located hosecock and
                                                                      backflow prevention device, and connected to a
                                                                      water supply; and
                                                                  d) is roofed or otherwise covered if the storage area
                                                                      is—
                                                                      (i) more than 1m²; or
                                                                      (ii) storing wet waste; or
                                                                      (iii) storing other waste with a high potential to
                                                                            cause pollution if washed or leaked from the
                                                                            bins, including waste oil or putrescibles.

  Safety and protection of infrastructure when demolishing or removing buildings
  PO7                                                           AO7.1                                                         Compliant
  Demolition, removal, relocation or associated works do not    Infrastructure including reticulated water, sewerage,         All services and infrastructure will be protected during
  result in:                                                    stormwater, and electricity are protected from damage         demolition and construction.
  a) 'live' or 'active' infrastructure that may present risk to and made safe to the standard required by the regulatory
      people using the site or surrounding areas; or            authority.
  b) damage to infrastructure or other works.
                                                                AO7.2                                                         Compliant
  Editor's note— An approval will be required from              Infrastructure is disconnected, capped or sealed including:   Infrastructure will be disconnected when required during
  Council's Building and Plumbing Services for decommissioning   a) electricity meters are removed and electrical wires       demolition and construction.
  plumbing apparatus including:                                     disconnected;
   a) sanitary drains or reticulated water supply; and           b) telephone lines are disconnected; and
   b) septic tanks, holding tanks or on-site treatment systems.  c) data cables are disconnected and removed.

                                                                 AO7.3                                                        Compliant
                                                                 A temporary crossing is provided to protect road             Where required, temporary crossing will be installed during
                                                                 reserve infrastructure including kerb and channel.           construction.

                                                                 AO7.4                                                        Compliant
                                                                 Any damage to footpaths, street plantings,                   Any damage to footpaths, street planting, natural
                                                                 natural vegetation, kerb and channel, bridges or             vegetation, kerb and channel and roadways during
                                                                 roadways at the removal site, the new site or between        demolition and construction will be repaired or reinstated.


Ref: 204099.T003                                                                                                                                                                   Page     3
214 David Low Way
PEREGIAN BEACH QLD 4573
Log in to download the original file

Appendix 2 - Code Assessment.pdf · 950 KB (small file)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.