                                                  Colleen Keegan, 07 5449 5183
                                                  Email: [email protected]
                                                  Application Ref: 2007/386




30 March 2007


Ausmar Homes
PO Box 418
COOROY QLD 4563




Dear Sir or Madam,

Re: Application for a Development Permit for Operational Works - Landscaping,
    Carparking & Access, Frontage Works, Stormwater & Drainage and Fill
    situated at 26 Orealla Crescent Sunrise Beach described as Lot 161 on
    RP220508

I refer to the above application for Operational Works - Landscaping, Carparking &
Access, Frontage Works, Stormwater & Drainage and Fill and wish to advise that
following preliminary examination of the plans, the following information is required to
be submitted:-

Land Use
1.      An amended Landscaping Layout Plan in accordance with Condition 3 of
        (04/5103) Material Change of Use – Duplex Dwelling and detailing the following:-

        1.1. Compliance with Council’s Policy on Landscaping Guidelines; and

        1.2. A landscape plan with a plant schedule that clearly indicates the location
             and size of each species to be planted on the site. It is noted that the
             current plan does not clearly identify the location and size of the species of
             plants on site.

        1.3. Compliance with Condition 4 of the corresponding Material Change of Use
             04/5103 illustrating the location and species of the 2 X 100L native canopy
             trees within the front setback; and

        1.4. Compliance with Condition 6 of the corresponding Material Change of Use
             illustrating the location of fencing on the site and the landscaping to be
             provided on the area of land between the fence and the front property
             boundary; and

        1.5. Compliance with Condition 7 illustrating the densely vegetated buffer to be
             provided along the rear property boundary; and

        1.6. Compliance with Condition 8 by clearly illustrating the height and location of
             the required fencing on the site; and



     Award Winner - Australian Clean Beach
       Challenge 2004 Litter Prevention
Full text of the other 3 sections

Section 2

        1.7. Details of any existing trees on the site to be retained or removed and
             within road reserve that are to be retained in accordance with Condition 9
             of the corresponding Material Change of Use.

2.      Amended plans that demonstrate:-

        2.1. Compliance with Land Use Condition 5 with regard to further articulation to
             be provided along the northern, southern, and eastern elevations of the
             duplex; and

        2.2. Compliance with Condition 10 by clearly illustrating the proposed colour
             scheme and materials and finishes for the development.

        2.3. Reduction in the size of the decks in accordance with Condition 11 to
             ensure that a 0.5 metre landscaped area is provided to the adjoining
             properties.

Land Development
Stormwater
3.      Please revise the design plan Drawing No. 16115-OW-1A prepare by SCG
        Consulting Engineers to include the following:

        3.1. Each lot (Lots 1 & 2 on SP189331) are to be separate systems,

        3.2. The revised design is to include that each system is to connected within the
             site and have a single outlet point in the kerb and channel,

        3.3. Indicate on the plans the levels of the proposed drainage system and the
             finished levels of the floors and landscaping.

        3.4. Indicate on the design plans the calculated pre-development and post-
             development stormwater runoff amounts for the site and the proposed
             outlet flow rate at the kerb and channel in accordance with Condition 36 of
             the Decision Notice File No. 2004/5103 dated 1 August 2005, and

        3.5. Please provide additional detail on the proposed drainage system for the
             driveway and carparking area in accordance with Condition 38, 39, 40 and
             41 of the Decision Notice File No. 2004/5103 dated 1 August 2005.
Access/Carparking
4.      Please provide a revised design plan for the access driveway that is in
        accordance with Conditions 22 and 23 of the Decision Notice File No. 2004/5103
        dated 1 August 2005 and the Noosa Plan’s Driveways and Carparking Code.

5.      Please provide a Longitudinal Section of the access driveway. The longitudinal
        section shall extend from the centreline of the existing formation to the carparking
        area and shall include a section of for the pedestrian footpath 1.5m wide with a
        maximum crossfall of 2.5% and be in accordance with and the Noosa Plan’s
        Driveways and Carparking Code..

6.      Please ensure that all relevant plans, landscaping, drainage etc, is in accordance
        with the access driveway design plans.



     Award Winner - Australian Clean Beach
       Challenge 2004 Litter Prevention

Section 3

7.      Indicate on the plans the available headroom at the entrance to the carparking
        area and at the garage doors.

8.      Indicate on the plans the location and type of the required signposting in
        accordance with Condition 28 of the Decision Notice File No. 2004/5103 dated 1
        August 2005.
Frontage Works
9.      Please provide additional detail, width, materials, levels etc of the required
        footpath across the frontage of the site.
Site Works
10.     It is noted that the submitted plan, drawing No. 16115-OW-1A prepare by SCG
        Consulting Engineers, indicates that sheet piling and other works are to take
        place on the adjoining properties. Please revise the drawing to indicate that all
        works are to be wholly contained within the subject site. Should any temporary
        structures be placed on and/or works need to be undertaken on the adjoining
        properties a letter of approval signed by the adjoining property owners shall be
        submitted to Council with the revised plans.

11.     Please provide comment from a suitably qualified engineer regarding the impacts
        of the proposed site works and the construction of the proposed pools will have
        on the Council sewer main located on the adjoining properties at the rear of the
        site. Should this comment indicate that the proposed works would have an
        adverse affect on the sewer main the proposed works shall be modified to ensure
        that no adverse affects will occur to the sewer main.
Please provide four (4) copies of all information that you are providing. In addition, it
would assist Council if you could also provide an electronic copy of your response.
Pursuant to the conditions of the Development Permit for a Material Change of Use
please note that all bonds and contributions are required to be paid prior to the issue of
the Operational Works approval.

Please be aware that under Section 3.2.12 of the Integrated Planning Act, the applicant
is to respond to any information request within 12 months of the request or otherwise,
the application lapses.
Under the provisions of the Integrated Planning Act 1997, you as the applicant, have
three options available in response to this Information Request. You may give the
assessment manager (in this instance Council) and each referral agency (if any):-

1.      all of the information requested; or

2.      part of the information requested together with a letter asking the assessment
        manager and each referral agency to proceed with the assessment of the
        application; or

3.      a letter:-

        3.1. stating that you do not intend to supply any of the information requested;
             and

        3.2. asking the assessment manager and each referral agency to proceed with
             the assessment of the application.


     Award Winner - Australian Clean Beach
       Challenge 2004 Litter Prevention

Section 4

The above information is required to be submitted, prior to assessment of the
application. If any further matters arise as part of assessment of this application, you
will be advised accordingly.

Should you have any further queries in relation to the above, please do not hesitate to
contact a on the above number.

Yours faithfully,



Colleen Keegan
PLANNING OFFICER




  Award Winner - Australian Clean Beach
    Challenge 2004 Litter Prevention

Used in these records

About this file

File size
13 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

00156933.001.pdf · 13 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.