2019-12-16 Special Meeting Agenda

of 25

Page text shows just the words. Original shows the document exactly as it was published.

Page text read automatically using OCR, there may be inaccuracies

Text sections have not been matched to the original PDF pages. Use the original document to check page numbers.

                       AGENDA


              Special Meeting


          Monday, 16 December 2019

                  commencing at 3.30pm
          Council Chambers, 9 Pelican Street, Tewantin



Crs Tony Wellington (Chair), Jess Glasgow, Ingrid Jackson, Joe Jurisevic,
Frank Pardon, Brian Stockwell, Frank Wilkie



                    “Noosa Shire – different by nature”
Log in to download the original file

2019-12-16 Special Meeting Agenda(PDF, 2MB).pdf · 2.0 MB (large file)

Large file: the download may take up to a minute.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

Full text of the other 24 sections

Section 2

SPECIAL MEETING AGENDA                                     16 DECEMBER 2019


TABLE OF CONTENTS

ITEM                                                                     PAGE

ATTENDANCE & APOLOGIES                                                      -

REPORTS                                                                     3

1      1920T013 STORMWATER INFRASTRUCTURE CCTV INSPECTIONS – TENDER
       AWARD                                                                3

2      1920T037 – CONSTRUCTION OF BLACK MOUNTAIN ROAD, BLACK MOUNTAIN
       CORRIDOR UPGRADE – TENDER AWARD                                      7

3      1920T048 – GYMPIE TERRACE STORMWATER AND CORRIDOR RENEWAL,
       NOOSAVILLE – TENDER AWARD                                           12

4      1920T072 – OREALLA CRESCENT, SUNRISE BEACH BRIDGE REPLACEMENT –
       TENDER AWARD                                                        18

MEETING CLOSURE                                                             -




                                                                 Page 2 of 25

Section 3

SPECIAL MEETING AGENDA                                                                    16 DECEMBER 2019


REPORTS
1                        1920T013 STORMWATER INFRASTRUCTURE CCTV INSPECTIONS – TENDER
                         AWARD
Document i nformati on




Author                             Technical Officer Capital Planning, Alex Neville
                                   Infrastructure Services Department

Index                              ECM/ Projects (T1) / Whole of Shire–Stormwater CCTV–CAP.WORK –
                                   50059
                                   ECM / Subject / Contracting / Contracts / Projects

Attachments                        1.    1920T013 – Evaluation Workbook


EXECUTIVE SUMMARY
Not applicable.

RECOMMENDATION
That Council note the report by the Technical Officer - Capital Planning to the Special Meeting
dated 16 December 2019 and:
A.                       Award Tender 1920T013 Stormwater Infrastructure CCTV Inspections to Pipe Management
                         Australia Pty Ltd under a Schedule of Rates contract; and
B.                       Authorise the CEO to approve three (3) optional extension periods of up to twelve (12)
                         months each.



REPORT
This report considers the provision of stormwater CCTV inspection services for the accurate
condition assessment of Council’s stormwater assets.

Tender Process
The invitation of public tenders for Stormwater Infrastructure CCTV Inspections was advertised on
VendorPanel Public Tenders 4 October 2019, in the Sunshine Coast Daily on 5 October 2019 and
the Noosa News on 8 October 2019. The tender closed on 5 November 2019. Fourteen (14)
conforming, two (2) alternatives and one (1) non-conforming tender submissions were received,
from contractors listed below in alphabetical order:
     Aussie Hydrovac Services Pty Ltd (Conforming & Alternative)
     Drain Medics
     Drain Tech Australia
     Dynamic Hydro Excavations Pty Ltd
     Environmental Services Group Pty Ltd
     FlowPro Pty Ltd (Conforming & Alternative)
     Interflow Pty Limited
     Lambert Locations Pty Ltd
     Pipe Management Australia Pty Ltd
     Pipe Vision Australia Pty Ltd


                                                                                                  Page 3 of 25

Section 4

SPECIAL MEETING AGENDA                                                         16 DECEMBER 2019


     Proterra Group Pty Ltd
     Relining Solutions Pty Ltd
     Smith Brothers Plumbing/Pipeline Technology Services

These tenders were assessed by the assessment panel in accordance with the following
procurement probity plan evaluation criteria:
    Capability & Resourcing
    Contract Experience & Capacity
    Methodology
    Quality
    Health & Safety
    Environment & Sustainability
    Contribution to Local Economy
    Price

The evaluation methodology considered both non-price elements (70% of the score) and a price
component (30% of the score).

As the contract is a schedule of rates, pricing was assessed by the application of a relevant
operational scenario to complete network assessment for both “rapid” and “detailed” assessment
scenarios; and innovation and efficiencies were assessed favourably. The outcome demonstrated
a number of strong submissions, and as such, a best and final offer was sought of these
contractors.

Pipe Management Australia Pty Ltd demonstrated a clear ability to meet both the price and non-
price elements, also specifying that they are not required to utilise the services of a sub-contractor
to undertake inspection works. Although the company does not have a head office in the immediate
Noosa region, they are in the process of securing a satellite depot on the Sunshine Coast, also
stating that the procurement of goods and labour will be purchased from the Noosa Shire area as
required.

As a result, Pipe Management Australia Pty Ltd is recommended as most advantageous to Council
for contract 1920T013 Stormwater Infrastructure CCTV Inspections, demonstrating value for
money, expertise and innovation.

Previous Council Consideration
Ordinary Meeting Minutes, 16 August 2018, Further Report
That Council note the report by the Technical Officer – Asset Management to the General
Committee Meeting dated 13 August 2018 and the further report by the Director Infrastructure
Services to the Ordinary Meeting dated 16 August 2018 and:
A.    Defer consideration of the matter to a future Council meeting; and
B.    Agree to the appointment of an independent evaluation panel to conduct an internal
      administrative review of the tender evaluation.

Following the Council resolution on 16 August 2018, an independent review by Findex (Aust) Pty
Ltd was conducted and recommended that the panel reconvene and conduct a fresh evaluation of
the original submissions, with procurement to oversee the process and provide a recommendation
to Council.




                                                                                        Page 4 of 25

Section 5

SPECIAL MEETING AGENDA                                                         16 DECEMBER 2019


Upon implementing Findex’s recommendation, it was identified that the respondents would all
benefit from detailed data that had become available during the tender close/review period. As
such, tender 1718T146 was withdrawn and this new tender released to the open market with this
new information (data) informing a revised specification. All respondents were notified of the
withdrawal and provided a courtesy notification upon release of this new tender.

Finance
The contract will be a Schedule of Rates.

The contract has an initial twenty-four (24) month term with the option to extend up to three (3)
periods of up to twelve (12) months each, at Council’s sole discretion.

Risks & Opportunities
Pipe Management Australia Pty Ltd have demonstrated their competency in providing the skills to
carry out stormwater CCTV inspections in a safe and effective manner, with the provision of all
mandatory qualifications and in conjunction with a very thorough methodology to reduce Work
Health and Safety risks during works.

Pipe Management Australia Pty Ltd have not previously been awarded a contract with Noosa
Council; however, their provided work history illustrates the company has carried out and delivered
similar work for multiple local government authorities. Referee checks from Brisbane City Council
and Paroo Shire Council stated their professionalism and confirmed that their previous work was
of a high standard. Additionally, Pipe Management Australia Pty Ltd is familiar with Council’s
reporting and inspection standards due to the company’s recent works for other local government
organisations.

Consultation
External Consultation - Community & Stakeholder
Nil.

Internal Consultation
This tender process was conducted in conjunction with Council’s Procurement Team, and
evaluated by officers within the Infrastructure Services Department.

Departments/Sections Consulted:

       Chief Executive Officer    Community Services                      X   Corporate Services
       Executive Officer          Director                                    Director
       Executive Support          Community Development                       Financial Services
                                  Community Facilities                        ICT
                                  Libraries & Galleries                   X   Procurement & Fleet
                                  Local Laws                                  Property
                                  Waste & Environmental Health                Revenue Services

       Executive Services         Environment & Sustainable Development   X   Infrastructure Services
       Director                   Director                                X   Director
       Community Engagement       Building & Plumbing Services            X   Asset Management
       Customer Service           Development Assessment                      Buildings and Facilities
       Governance                 Economic Development                        Civil Operations
       People and Culture         Environmental Services                      Disaster Management
                                  Strategic Land Use Planning             X   Infrastructure Planning,
                                                                              Design and Delivery




                                                                                           Page 5 of 25

Section 6

SPECIAL MEETING AGENDA                                                                                                                                                                                                                                                                                                                                                                                                                                                         16 DECEMBER 2019


                                                                                                                                                                                                                                                                                                                                                                                                                                                                                        ATTACHMENT 1
                                                                                 1                                2                            3                               4                             5                               6                            7                            8                           9                            10                             11                            12                             13                          14                          15

                                                                   Lambert Locations Pty Ltd        Drain Tech Australia Pty        Pipe Management              Aussie Hydro-Vac Services                                     Aussie Hydro-Vac Services       FlowPro Pty Ltd -                                                                     Environmental Services                                                                     Pipe Vision Australia Pty      Pipeline Technology           Dynamic Hydro
                      PART A - Non price elements                                                                                                                                                Interflow Pty Limited                                                                         Dain Medics                FlowPro Pty Ltd                                          Relining Solutions Pty Ltd     ProTerra Group Pty Ltd
                                                                      t/as 1300B4UDIG                         Ltd                        Australia                Pty Ltd - ALTERNATIVE                                                 Pty Ltd                  ALTERNATIVE                                                                             Group Pty Ltd                                                                                     Ltd                       Services              Excavations Pty Ltd

                                                                                       Resultant                        Resultant                    Resultant                       Resultant                     Resultant                       Resultant                    Resultant                    Resultant                   Resultant                     Resultant                      Resultant                     Resultant                      Resultant                   Resultant                   Resultant
Evaluation Criteria                                Weighting (%)      Score             score x        Score             score x    Score             score x       Score             score x     Score             score x       Score             score x    Score             score x    Score             score x    Score            score x      Score            score x       Score            score x      Score            score x       Score            score x    Score            score x    Score            score x
                                                                                       weighting                        weighting                    weighting                       weighting                     weighting                       weighting                    weighting                    weighting                   weighting                     weighting                      weighting                     weighting                      weighting                   weighting                   weighting

Capability & Resourcing                                 15%            55                8.25          75.5              11.33      79.5              11.93          77               11.55       78.5              11.78          77               11.55      76.5              11.48       74               11.10      76.5             11.48        77.5             11.63          75              11.25         85              12.75          72              10.80       56               8.40       76              11.40

Contract Experience & Capacity                          15%           40.2               6.03           77               11.55      80.8              12.12         80.8              12.12       82.6              12.39         80.8              12.12      75.2              11.28      68.2              10.23      75.2             11.28         81              12.15          75              11.25         85              12.75         74.2             11.13       55               8.25       75              11.25

Methodology                                             15%            41                6.15          78.5              11.78       80               12.00         81.5              12.23        79               11.85         80.5              12.08      71.5              10.73       70               10.50      71.5             10.73         80              12.00         69.5             10.43         88              13.20          61               9.15       54               8.10       64               9.60

Quality                                                 10%            57                5.70           85                8.50      80.5               8.05          82                8.20        86                8.60          82                8.20       56                5.60      50.5               5.05       56               5.60        83.5              8.35          57               5.70        86.5              8.65          48               4.80      60.5              6.05      56.5              5.65

Health & Safety                                         5%             67                3.35          82.5               4.13       81                4.05          85                4.25       85.5               4.28         82.5               4.13       55                2.75       60                3.00       55               2.75         82               4.10          59               2.95         81               4.05          60               3.00      59.5              2.98      56.5              2.83

Environment & Sustainability                            5%             84                4.20           89                4.45       87                4.35          87                4.35        87                4.35          87                4.35       50                2.50       50                2.50       50               2.50         87               4.35          50               2.50         90               4.50          50               2.50       85               4.25       53               2.65

Contribution to Local Economy                           5%            49.05              2.45           56                2.80      58.6               2.93         56.25              2.81       53.1               2.66         56.25              2.81      69.9               3.50      67.45              3.37      69.9              3.50        45.9              2.30         53.3              2.67        53.9              2.70         53.4              2.67      40.85             2.04      68.75             3.44

Total Technical Score                                   70%                    36.13                            54.53                        55.43                           55.51                         55.90                           55.23                        47.83                        45.75                       47.83                         54.87                          46.74                         58.60                          44.05                       40.07                       46.81

                    Normalised Technical Score (Tn)                            43.17                            65.14                        66.21                           66.31                         66.77                           65.98                        57.13                        54.66                       57.13                         65.55                          55.84                         70.00                          52.62                       47.87                       55.92


                                                                   Lambert Locations Pty Ltd        Drain Tech Australia Pty        Pipe Management              Aussie Hydro-Vac Services                                     Aussie Hydro-Vac Services       FlowPro Pty Ltd -                                                                     Environmental Services                                                                     Pipe Vision Australia Pty      Pipeline Technology           Dynamic Hydro
                          PART B - Price element                                                                                                                                                 Interflow Pty Limited                                                                         Dain Medics                FlowPro Pty Ltd                                          Relining Solutions Pty Ltd     ProTerra Group Pty Ltd
                                                                      t/as 1300B4UDIG                         Ltd                        Australia                Pty Ltd - ALTERNATIVE                                                 Pty Ltd                  ALTERNATIVE                                                                             Group Pty Ltd                                                                                     Ltd                       Services              Excavations Pty Ltd
Total Fees (Pc)                                         30%                   $405,000                         $434,060                     $453,600                        $518,738                      $533,500                        $567,818                     $762,500                     $960,960                   $1,000,000                    $1,046,332                     $1,140,000                    $1,228,950                     $1,241,565                  $1,251,000                  $2,885,200

Average Fees (Pav) $.........................         $961,948

Price Score                                                                     158                              155                          153                             146                           145                             141                          121                          100                         96                            91                             81                            72                             71                          70                         -100

Normalised Price Score (Pn)                                                     100                              98                           97                              93                            92                              89                           76                           63                          61                            58                             52                            46                             45                          44                           1

Weighted Price Score (Pw)                                                      30.00                            29.43                        29.04                           27.75                         27.46                           26.78                        22.94                        19.02                       18.25                         17.33                          15.48                         13.73                          13.48                       13.29                        0.30


            Total Score of price and non price elements                        73.17                            94.56                        95.25                           94.07                         94.24                           92.77                        80.07                        73.68                       75.38                         82.88                          71.32                         83.73                          66.10                       61.16                       56.22



                             Assessment Panel                                                      Position Title

     Contract Administrator & Assesment Panel Member 1                         Asset Planning Manager, Infrastructure Services
                      Assesment Panel Member 2                          Technical Officer - Capital Planning, Infrastructure Services
                      Assesment Panel Member 3                                 Designer - Capital Works, Infrastructure Services
                      Assesment Panel Member 4                           Workplace Health and Safety Advisor, Executive Services




                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                    Page 6 of 25

Section 7

SPECIAL MEETING AGENDA                                                                16 DECEMBER 2019



2                        1920T037 – CONSTRUCTION OF BLACK MOUNTAIN ROAD, BLACK MOUNTAIN
                         CORRIDOR UPGRADE – TENDER AWARD
Document i nformati on




Author                             Project Manager, Mark Poynter
                                   Infrastructure Services Department

Index                              ECM \Projects(T1) \Black Mountain Road Priority Sections – CAP.WORK -
                                   500840
                                   ECM \Subject \Contracting \Contracts \ Projects
                                   ECM \ Projects and Contracts \ 1920T037 Construction of Black Mountain
                                   Road Corridor Upgrade \ Council Reports

Attachments                        Nil



EXECUTIVE SUMMARY
This report provides a recommendation for the contract award of the preferred contractor for
1920T037 Construction of the Black Mountain Road, Black Mountain Corridor Upgrade.

RECOMMENDATION
That Council note the report by Project Manager to the Special Meeting dated 16 December 2019
and award Portion A, C & D of tender 1920T037 – Black Mountain Road Corridor Upgrade to
Bellwether Pty Ltd for the value of $1,230,934; and approve the total project budget of $1,425,152.



REPORT
The proposed contract is for the construction of road widening, renewal of pavement and other
safety improvements (namely signage) on Black Mountain Road, starting Stanfield Lane and
continuing approximately 3.2km west. This section of road has been identified as a priority via road
safety audits and the reseal program.

1.                       Design

The design for these works has been undertaken by both the Council’s internal design team and
external consultants, with reviews to seek the most economical outcome. The aim of the project is
to improve road safety within the budget by maintaining the existing road pavement while
undertaking minor alignment modifications and installing additional signage.

2.                       Project Scope

The project and contract has been broken into the following scope portions:




                                                                                              Page 7 of 25

Section 8

SPECIAL MEETING AGENDA                                                           16 DECEMBER 2019




    Portion A (purple)
     Reseal of existing surface and installation of additional safety signage.

    Portion B (orange outline)
     Land slip repair previously completed by Council. Not part of this contract.

    Portion C (red outline)
     Widening of existing pavement, pavement rehabilitation, improved drainage and installation of
     additional safety signage.

    Portion D (blue outline)
     Re-profiling of the vertical alignment to improve sight lines (visibility), widening of existing
     pavement, pavement rehabilitation, reinstatement of resident driveways, improved drainage
     and installation of additional safety signage.

This project was originally designed in portions/stages which have been combined into a single
contract to achieve economies of scale and attract qualified contractors to participate in the tender
process.

3.    Tender Process

Due to the value of the works being greater than $200,000 the works have been tendered in
accordance with the Local Government Act 2009. The Invitation to tender 1920T037 was released
via VendorPanel Public Tenders on 28 October 2019. The tender was advertised in the Noosa
News (29 October 2019) and closed on 19 November 2019.

4.    Tender Assessment

An initial review was undertaken to identify any non-conforming tender responses. A number of
responses were considered to be non-confirming and were eliminated on the basis that they were
marketing material and not true submissions. No late tender responses were received. As a result,
a total of four responses were accepted and progressed to the evaluation process, which are listed
in alphabetical order:
     Bellwether Contractors Pty Ltd
     Carruthers Contracting

                                                                                       Page 8 of 25

Section 9

SPECIAL MEETING AGENDA                                                       16 DECEMBER 2019


      Hazell Brothers
      Koppens Developments Pty Ltd

Each member of the evaluation team undertook an independent review and analysis of the
respondent’s technical submissions and rated them according to established criteria. The
evaluation team then met to review and discuss each team member’s evaluation and agree scoring
for each respondents criteria, ultimately informing the evaluation outcome.




5.     Access during construction

The project will cause disruption to traffic requiring one-way alternate traffic management to allow
works to proceed safely. Specific requirements have been placed on the contractor to ensure
access to residences is maintained and any delays to motorists minimised.

6.     Program

The contract works are proposed to commence onsite late January 2020 with the works taking
approximately five months, weather permitting.

Previous Council Consideration
Nil.

                                                                                      Page 9 of 25

Section 10

SPECIAL MEETING AGENDA                                                                16 DECEMBER 2019


Finance
Council has allocated a total of $1,318,214 in the current (FY2019/20) budget. The below table
identifies the estimated project costs.

 Item                                                                            Cost (excl. GST)

 Costs to date (November 2019)                                                              $19,659
 Tendered Contract Value (ex. GST)                                                       $1,230,934
 Staff and other project costs                                                              $45,000
 SUB TOTAL                                                                               $1,295,593
 Contingency                                                                              $129,559
 TOTAL BUDGET                                                                            $1,425,152

A budget review submission will be required at BR3 to reflect the $106,938 shortfall in the current
approved budget, should the full contingency amount be required.


Risks & Opportunities
                  RISKS                                                MITIGATION
 Finance
 Council request for scope increases.         This will be mitigated through the Capital Works Project
                                              Control Group and Capital Works Executive management and
                                              limitation of client requested scope variations.
 Geotechnical conditions give rise for        Previous site conditions have been considered and significant
 contractor claiming variation costs.         latent conditions are not expected.
 Clashes with underground services give       There are no major underground services expected within the
 rise for contractor claiming variation       area of work. The contractor is required to identify and protect
 costs.                                       those that are discovered.
 Contingency amount being insufficient        This risk may be mitigated through the adoption of further
                                              value engineering to occur during the construction phase
                                              process.
 Program
 There is the potential that the project is   The contractor is required to include “wet weather” allowances
 delayed due to wet weather                   into their schedule.
 Construction takes longer due to site        In the event of delays the contractor is able to mobilise
 being more constrained than allowed.         additional equipment to bring the program on track.
 Resource risk                                The contractor is utilising local subcontractors and is confident
                                              in their ability to resource effectively from the local market.
 Safety
 This is a medium risk project due to         Prior to construction commencing, work place health and
 proximity to rural traffic environment.      safety and traffic management plans will be required to be
                                              submitted to Council for review. Regular audits on contractor
                                              compliance with these approved plans will be undertaken by
                                              Council throughout construction.
 Environmental Harm
 There is risk that the works impact on       The works are in the existing road corridor which is typically
 existing vegetation.                         clear of mature trees.
 Risk of sedimentation/run-off.               Contractors are required to have an environment management
                                              plan which will be reviewed and approved by Council prior to
                                              commencement.

                                                                                               Page 10 of 25

Section 11

SPECIAL MEETING AGENDA                                                                 16 DECEMBER 2019


                  RISKS                                                 MITIGATION
 Scope and Quality
 Risk of not meeting project objectives         To be managed through Council staff ensuring the original
                                                design and specifications are met.
 Public   Disruption       and       Council
 Reputation
 Noise from plant and equipment may be          This will be minimised where ever possible.
 a cause of disruption to local residents.
 Vibration                                      Contractors will be required to meet established specifications
                                                regarding vibration works.
 Amenity of the site reduced by                 Contractor is required to keep work areas clear and tidy.
 construction process and not acceptable
 for the location.

Consultation
External Consultation - Community & Stakeholder
Local residents will be informed via letter drop of the timing and impact of the construction activities
and be provided ongoing updates as the project progresses.

Internal Consultation
    Chief Executive Officer           Community Services                          X   Corporate Services
    Executive Officer                 Director                                    X   Director
    Executive Support                 Community Development                           Financial Services
                                      Community Facilities                            ICT
                                      Libraries & Galleries                       X   Procurement & Fleet
                                      Local Laws                                      Property
                                      Waste & Environmental Health                    Revenue Services

    Executive Services           X    Environment & Sustainable Development       X   Infrastructure Services
    Director                          Director                                    X   Director
    Community Engagement              Building & Plumbing Services                    Asset Management
    Customer Service                  Development Assessment                          Buildings and Facilities
    Governance                        Economic Development                        X   Civil Operations
    People and Culture           X    Environmental Services                          Disaster Management
                                      Strategic Land Use Planning                 X   Infrastructure Planning,
                                                                                      Design and Delivery




                                                                                                 Page 11 of 25

Section 12

SPECIAL MEETING AGENDA                                                                           16 DECEMBER 2019


3                          1920T048 – GYMPIE TERRACE STORMWATER AND CORRIDOR RENEWAL,
                           NOOSAVILLE – TENDER AWARD
Document i nformati on




Author                                Project Coordinator, Scott Anderson
                                      Infrastructure Services Department

Index                                 ECM \Projects (T1) \ Noosaville Gympie Terrace Stormwater Ren –
                                      CAP.WORK - 500920
                                      ECM \Subject \Contracting \Contracts\Projects

Attachments                           Nil


EXECUTIVE SUMMARY
Not applicable.


RECOMMENDATION
That Council note the report by the Project Coordinator to the Special Meeting dated 16 December
2019 and award portion 1 to 5 of Tender 1920T048 - Gympie Terrace Stormwater and Corridor
Renewal, Noosaville to Hall Contracting Pty Ltd for the value of $1,728,406 (ex GST); and approve
the total project budget of $2,052,896.



REPORT
Recent asset inspections have identified deteriorating stormwater culverts (and associated
infrastructure) at a number of sites along Gympie Terrace between Robert and Edward Street,
Noosaville. The proposed contract is for the renewal of these identified stormwater culverts. Work
under this contract also includes the road corridor renewal between Cloudsley Street and Albert
Street providing dedicated on-road cycle lanes, pedestrian crossing improvements and asphalt
overlay.

The program of works is proposed to commence onsite in early February 2020 with all works to be
finalised in June 2020, weather permitting.

1.                         Design

The work can be categorised into the three broad work activities of stormwater renewal, road
corridor renewal and necessary water main relocation works. The design of each of these elements
has been through multiple iterations in order to provide effective and economical design outcomes.
To stagger the works, five separable portions have been applied to the contract. These separable
portions have been described within Section 2 - Project Scope.

2.                         Project Scope

The following scope portions apply to this project:

                        Portion 1 (Albert Street & Regatta Noosa Sites)
                         Reconstruction of existing reinforced concrete box culverts (RCBC) as indicated by Figure 1 at
                         the Albert Street intersection and area fronting ‘Regatta Noosa’.

                         Portion includes necessary minor water main lowering works.


                                                                                                        Page 12 of 25

Section 13

SPECIAL MEETING AGENDA                                                      16 DECEMBER 2019


   Portion 2 (Thomas Street Site)
    Reconstruction of existing reinforced concrete RCBCs at the Thomas Street intersection, as
    indicated in Figure 1 below.

    Portion includes new pedestrian refuge and crossing opportunity at the western roundabout
    approach and associated works.

   Portion 3 (The Cockleshell Site)
    Reconstruction of existing reinforced concrete RCBCs at The Cockleshell intersection as
    indicated in Figure 1.

    Portion includes pedestrian crossing improvements to the existing raised pedestrian crossing
    to the east of The Cockleshell intersection and associated works.

   Portion 4 (Robert Street Site)
    Reconstruction of existing reinforced concrete RCBCs at the Robert Street intersection as
    indicated by Figure 1.

    Portion includes new raised pedestrian crossing to the east of Robert Street, improvements to
    the existing pedestrian crossing to the west of Robert Street and associated works and
    necessary water main lowering works.

   Portion 5 (Corridor Renewal)
    Profiling and asphalt resurfacing of road corridor between Cloudsley Street and Albert Street
    as indicated by Figure 2, provision of on-street bicycle lanes and minor line marking and on-
    street parking alterations.




                                 Figure 1 - Stormwater Renewal Sites




                              Figure 2 - Corridor Renewal Extent of Works




                                                                                  Page 13 of 25

Section 14

SPECIAL MEETING AGENDA                                                     16 DECEMBER 2019


3.   Tender Process

Due to the value of the works being greater than $200,000, the works have been tendered in
accordance with the Local Government Act 2009. The Invitation to Tender for 1920T048 was
released via VendorPanel on 14 October 2019. The tender was advertised in the Noosa News (15
October 2019) and the Sunshine Coast Daily (19 October 2019) publications, and closed on 12
November 2019. Four (4) conforming and two (2) non-conforming tender submissions were
received from contractors.

The four conforming responses received, are listed below in alphabetical order:
     Exceed Concrete Pty Ltd
     GCE Contractors Pty Ltd
     Hall Contracting Pty Ltd
     Koppens Developments Pty Ltd

4.   Tender Assessment

A tender assessment meeting was held on 14 November 2019 by a panel of five members and
overseen by an internal Procurement and Contracts Advisor. This panel evaluated the conforming
tender submissions based on set evaluation criteria.




                                Table 1 - Tender Assessment Summary

The tender assessment processes has identified Hall Contracting Pty Ltd as the preferred
contractor.



                                                                                  Page 14 of 25

Section 15

SPECIAL MEETING AGENDA                                                         16 DECEMBER 2019


5.      Access during construction

The Gympie Terrace project will cause disruption to traffic and pedestrian movements on and
around Gympie Terrace during the life of the project. Specific requirements have been placed on
the contractor to communicate with, and ensure access to businesses and residences is
maintained throughout the project.

Through traffic will be maintained for the duration of work, however motorists will be encouraged
to use alternate routes as delays are expected. Night works are proposed for critical elements of
the road crossing work to further minimise traffic flow and access restrictions. This night work will
be structured such that impacts to adjacent land uses is minimised.

The contractor must also consider the impact of work to community events and take appropriate
action to mitigate any impact. To assist this, the contractor will be provided with a copy of the event
calendar.

6.      Program

The preferred contractor has nominated a construction period of 4 months commencing in
February 2020 subject to favourable conditions during construction. It is proposed that night work
be undertaken for critical road crossing work to provide an accelerated works program.

7.      Previous Council Consideration
Nil.

8.      Finance
A combined budget allocation of $1,964,000 has been provided in the 2019/2020 budget.

This combined work allocation is comprised of $1,200,000 Council funding for stormwater renewal,
$632,000 Council funding and $132,000 State Government funding for corridor renewal works.

The below table identifies the estimated project costs and total budget.

 Item                                                                      Cost (excl. GST)

 Costs to date (November 2019)                                                    $47,149.18
 Tendered Contract Value (ex. GST)                                            $1,728,405.83
 Consultant and staff costs                                                          $95,000
 SUB TOTAL                                                                    $1,870,555.01
 CONTINGENCY                                                                    $182,340.58
 TOTAL BUDGET                                                                 $2,052,895.59


A budget review submission will be required at BR3 to address a shortcoming of $88,896 if the full
value of contingency is required.




                                                                                       Page 15 of 25

Section 16

SPECIAL MEETING AGENDA                                                                16 DECEMBER 2019


9.    Risks & Opportunities
                    RISKS                                                MITIGATION
 Finance
 Council request for scope increases.              This is to be mitigated through the Capital Works Project
                                                   Control Group and Capital Works Executive management
                                                   and limitation of client requested scope variations.
 Scope    changes   once    construction           Council acceptance of scope as awarded with intention of
 commences and project becomes publically          not increasing scope.
 visible.
 Geotechnical conditions give rise           for   Previous geotechnical investigations have been
 contractor claiming variation costs.              considered and allowance for adverse latent conditions is
                                                   included in the contingency.
 Contractor claims for variations based on         As above, this has been mitigated through the lump sum
 costs for environmental impact mitigation         procurement method.
 exceeds allowances.
 Clashes with underground services give rise       All known underground services have been located, and
 for contractor claiming variation costs.          necessary relocation included in scope of works. Scope
                                                   has been limited to placement of new infrastructure within
                                                   existing infrastructure envelopes.
 Contingency amount being insufficient             This risk may be mitigated through the adoption of further
                                                   value engineering to occur during the construction phase
                                                   process.
 Program
 There is the potential that the project is        The contractor is required to include “wet weather”
 delayed due to wet weather                        allowances into their schedule.
 Construction takes longer due to site being       In the event of delays the contractor is able to mobilise
 more constrained than allowed.                    additional equipment at no additional cost to bring program
                                                   on track.
 Resource risk                                     Hall Contracting have nominated a capable team and
                                                   combining two work fronts at one time reduces the
                                                   resourcing risks to this project. The appointment of an
                                                   internal superintendent mitigates the resourcing risk for
                                                   Council.
 Safety
 This is a high risk project due to proximity to   Prior to construction commencing, work place health and
 traffic and pedestrians.                          safety and pedestrian and traffic management plans will be
                                                   required to be submitted to Council for review. Regular
                                                   audits on contractor compliance with these approved plans
                                                   will be undertaken by Council throughout construction.
 Environmental Harm
 There is risk that the works do impact on         Council has engaged an independent arborist to ensure
 existing mature vegetation.                       that mature trees are protected and the construction
                                                   methodology to ensure impacts are minimised
 Risk of spills from materials.                    Contractors are required to have an environment
                                                   management plan which will be reviewed and approved by
                                                   Council prior to commencement.
 Sediment and erosion control                      Contractor is required to prepare and implement a certified
                                                   Erosion and Sediment Control Plan. Works methodology
                                                   will be applied that minimises the duration/extent of
                                                   exposed areas.
 Scope and Quality
 Risk of not meeting project objectives            To be managed through Council staff ensuring the original
                                                   design and specifications are met.

                                                                                              Page 16 of 25

Section 17

SPECIAL MEETING AGENDA                                                                16 DECEMBER 2019


                    RISKS                                                MITIGATION
 Public    Disruption         and      Council
 Reputation
 Noise from plant and equipment may be a           This will be minimised where ever possible.
 cause of disruption to local businesses and
 residents.
 Vibration                                         Contractors will be required to meet established
                                                   specifications regarding vibration works. Sourcing of
                                                   dilapidation reports for adjacent properties.
 Amenity of the site reduced by construction       Propose to appropriately screen construction fencing and
 process and not acceptable for the location.      work areas.
 Disturbance to adjacent            land   uses    To be migrated through engagement and communication
 (commercial and residential)                      with stakeholders in accordance with prepared
                                                   communication plan. Works methodology conducive to an
                                                   accelerated works program to minimise duration of
                                                   disturbance.

Consultation
External Consultation - Community & Stakeholder
Local residents have and will continue to be informed via letter drop, door-knocking and electronic
communication of the timing and impact of the construction activities.

Internal Consultation
Departments/Sections Consulted:

    Chief Executive Officer          Community Services                         X   Corporate Services
    Executive Officer                Director                                       Director
    Executive Support                Community Development                      X   Financial Services
                                     Community Facilities                           ICT
                                     Libraries & Galleries                      X   Procurement & Fleet
                                     Local Laws                                     Property
                                     Waste & Environmental Health                   Revenue Services

    Executive Services               Environment & Sustainable Development      X   Infrastructure Services
    Director                         Director                                   X   Director
    Community Engagement             Building & Plumbing Services               X   Asset Management
    Customer Service                 Development Assessment                         Buildings and Facilities
    Governance                       Economic Development                       X   Civil Operations
    People and Culture               Environmental Services                         Disaster Management
                                     Strategic Land Use Planning                X   Infrastructure Planning,
                                                                                    Design and Delivery




                                                                                                 Page 17 of 25

Section 18

SPECIAL MEETING AGENDA                                                               16 DECEMBER 2019


4                        1920T072 – OREALLA CRESCENT, SUNRISE BEACH BRIDGE REPLACEMENT –
                         TENDER AWARD
Document i nformati on




Author                             Project Coordinator, Dennis Luinstra
                                   Infrastructure Services Department

Index                              ECM\ Projects (T1)\ Orealla Crescent Bridge Replacement
                                   ECM\ Subject\ Funding/Grants Donations\Roads (State & Federal Funding
                                   Schemes/Programs)
                                   ECM\ Subject\ Contracting\ Road Construction

Attachments                        1.     Tender evaluation summary
                                   2.     Preliminary design sketch


EXECUTIVE SUMMARY
This report provides a recommendation for the contract award of the preferred contractor for
1920T072 Orealla Crescent, Sunrise Beach bridge replacement.

RECOMMENDATION
That Council note the report by the Project Coordinator to the Special Meeting dated 16 December
2019 and award tender 1920T072 for the Design and Construction of the Orealla Crescent Bridge
replacement situated in Sunrise Beach to SGQ Pty Ltd for a value of $2,619,227 and approve the
total project budget of $3,716,432.


REPORT
The proposed contract is for the replacement of the Orealla Crescent Bridge situated on the David
Low Way at Sunrise Beach.

1.                       Project Scope

The design and construction of a new bridge will allow for two traffic lanes, on road cycle lanes and
a separated/off-road shared pathway. The contractor is to minimise impacts to Orealla Crescent
with the existing bridge height clearance maintained. The bridge will meet current design
specifications and standards with a target design life of 100 years. Project proposals have included
some allowances for improvements to bridge aesthetics and landscaping.

2.                       Tender Process

In late 2018, a previous tender was called to remediate the bridge and therefore extend technical
life by 50 years. This tender was not awarded as it did not provide value for money for Council,
only providing a limited warranty on the cathodic protection system and repairs, with a project cost
of around two thirds that of fully replacing the bridge. Remediation also did not provide
improvements such as meeting current design specifications, a separated shared footpath,
improved aesthetics and a 100 years design life.

Due to the value of the works being greater than $200,000 the works have been tendered in
accordance with the Local Government Act 2009. The tender process was broken down into 2
phases, being;
    Phase 1 - 1920E050 - Expression of Interest - Orealla Crescent Bridge replacement
    Phase 2 - 1920T072 - Closed tender – Orealla Crescent Bridge Replacement, Sunrise
     Beach.

                                                                                           Page 18 of 25

Section 19

SPECIAL MEETING AGENDA                                                        16 DECEMBER 2019


Phase 1
The expression of interest was released via Vendor Panel on 2 September 2019 and closed 24
September 2019. Five (5) conforming and one (1) non-conforming responses were received.

Phase 2
The Invitation to (closed) tender was released via Vendor Panel on 22 October 2019 and closed
on 20 November 2019. Four (4) conforming and one (1) alternate tenders were received.

3.    Tender Assessment

The tender evaluation panel undertook an assessment of the tender submissions in the closed
tender from the following respondents (listed in alphabetical order);
    ARK Construction Group Pty Ltd
    Davbridge Properties Pty Ltd T/A Davbridge Constructions
    CRAGCORP Pty Ltd T/A Queensland Bridge & Civil
    SGQ Pty Ltd (conforming bid)
    SGQ Pty Ltd (conforming alternate bid)

Each evaluation panel member undertook an independent review and analysis of the respondent’s
technical submission and rated them according to established criteria. The evaluation panel then
met to review and discuss each panel member’s evaluation and agree scoring for each
respondents criteria, ultimately informing the evaluation outcome.

A summary of the scoring (combined price and non-price elements) as agreed by the evaluation
panel is provided in the table below. For further details including pricing refer to attachment 1.

 Respondent                                         Total
 ARK Construction Group                             83.85
 Davbridge Constructions                            93.57
 Queensland Bridge & Civil                          71.61
 SGQ Pty Ltd                                        95.71
 SGQ Pty Ltd (alternate bid)                       100.00

The tender evaluation panel finalised tender evaluations and considered the tender (alternate bid)
of SGQ Pty Ltd to be the most advantageous to Council and presenting the best value for money.
This tender submission is favourable on the following basis:
     They were able to demonstrate previous experience with successful construction of several
      similar projects in the recent past;
     The proposed methodology responded to the requirement to minimise the impact to motorists
      by reducing the duration of the closure of David Low Way.
     SGQ’s alternate bid provides a cost saving compared to SGQ’s conforming tender due to the
      use of modified precast deck units which will provide improved inspection access during the
      future maintenance of the structure.
     Further, SGQ’s alternate proposes an advanced foundation system, which should deliver a
      shorter construction duration. This will ultimately reduce the impact and nuisance to residents
      by shortening the duration of the detour by a few days and reduce the amount and/or duration
      of heavy machinery required on site during the construction phase.
     They demonstrated a considered methodology and bridge design, offering high quality and
      minimising Work Health and Safety risks;


                                                                                     Page 19 of 25

Section 20

SPECIAL MEETING AGENDA                                                       16 DECEMBER 2019


    They demonstrated that they have the necessary resources to meet Council’s contractual
     timeframes for practical completion;
    The project team is located within the Noosa Shire and greater Sunshine Coast and has local
     experience with bridge design and construction.

The tender evaluation panel considers this alternate tender submission to be the most
advantageous to Council and presents the best total score of combined price and non-price
elements.

4.   Access during construction

The project will cause some disruption to traffic and pedestrian movements on and around David
Low Way and Orealla Crescent. Very specific requirements have been developed and set through
the tender phase by Council in consultation with experienced traffic consultants. The contractor
must ensure access to businesses and residences is maintained throughout the works. Motorists
will be encouraged to use alternate routes via Facebook and mobile message boards at major
intersections to prevent potential lengthy delays through the detour route.

5.   Program

SGQ propose to design and construct the project (pending adverse weather) in approximately six
months. The design process is planned to commence in January 2020. Site establishment and
construction will commence in May 2020 with expected completion in late July 2020.

This aggressive timeframe is required to comply with the Federal Grant funding requirements
applicable to this project.

In the design phase, Council’s project team will work with the contractor to determine the
aesthetics, such as curved bridge railings, patterns on the vertical abutment wall and will look for
opportunities to improve the current amenity.

6.   Previous Council Consideration

Ordinary Meeting Minutes, 15 August 2019, Item 7, Page 18
That Council note the report by the Project Officer to the General Committee Meeting dated 12
August 2019 and authorise staff to call for Expressions of Interest for the Design and Construction
of the Orealla Crescent Bridge, Sunrise Beach.

7.   Finance

Council has provisionally allocated a total of $1,754,514 for the project, comprising $754,514 in
this current 2019/20 financial year and $1,000,000 in the 2020/21 financial year.

The Federal Government through its Bridge Renewal Program will contribute 50% of the project
cost up to a maximum of $3,180,840. UnityWater is covering expenses related to temporary
relocation and reinstatement of their water main asset due to the planned renewal aligning with the
bridge replacement timing.




                                                                                     Page 20 of 25

Section 21

SPECIAL MEETING AGENDA                                                                  16 DECEMBER 2019


The below table identifies the estimated project costs.

 Item                                                                          Cost (excl. GST)
 Costs Year to Date (November 2019)                                                     $97,800
 Tendered Contract Value                                                             $2,619,227
 Consultants, superintendent and staff costs                                           $170,000
 Provision for relocation of services (Telstra)                                        $210,000
 Subtotal                                                                            $3,097,027
 Contingency                                                                           $619,405
 Total project cost                                                                  $3,716,432

A budget submission will be provided for the $1,961,918 shortfall across BR3 (2020) and the 2021
capital works program to reflect the expected project cash flows as provided by the successful
tenderer.

8.      Risks & Opportunities

                  RISKS                                                 MITIGATION
 Finance
 Council request for scope increases.         This is to be mitigated through the Capital Works Project Control
                                              Group and Capital Works Executive meetings and limitation of
                                              client requested scope variations.
 Scope changes once construction              Council acceptance of scope as awarded with intention of not
 commences and project becomes                increasing scope.
 publically visible.
 Geotechnical conditions give rise for        A preliminary Geotechnical investigation has been completed
 contractor claiming variation costs.         by Council and the report provided as part of the tender
                                              documentation.
                                              The contractor has confirmed they have allowed for
                                              comprehensive geotechnical investigations during the design
                                              phase.
                                              There is a risk that soil conditions may not allow for the
                                              proposed foundation method and the contractor will need to
                                              revert to the specified pile solution. This risk sits with the
                                              Contractor but the project team has considered it as part of its
                                              contingency allowance.
 Contractor claims for variations based       This has been mitigated through the lump sum procurement
 on changes required for design.              method with further mitigation through post tender clarifications
                                              tying the contractor firmly into the agreed scope of works.
 Clashes with public utility providers give   Prior tender phase, Council staff had extensive collaboration
 rise for contractor claiming variation       with utility providers UnityWater and Telstra to lock in the scope
 costs.                                       and work method. The contractor is aware of the requirements.
                                              The contractor will coordinate activities around these
                                              relocations. While Telstra will invoice Council directly for the
                                              relocation works, UnityWater will pay for the renewal of the
                                              water main attached to the bridge as the asset was already
                                              identified as end of life.
 Contingency amount being insufficient.       This risk may be mitigated through the adoption of further value
                                              engineering to occur during the design and construction phase
                                              process as well through appointment of experienced contractor
                                              and contract supervision of an internal experienced
                                              Superintendent.



                                                                                                Page 21 of 25

Section 22

SPECIAL MEETING AGENDA                                                                 16 DECEMBER 2019


                 RISKS                                                MITIGATION
Program
There is the potential that the project is   Construction during the typically dry season aims to mitigate
delayed due to wet weather.                  this. Expected wet weather days are included in the tenderers
                                             timeline.
Resource risk.                               The contractor has nominated a capable team to undertake
                                             construction.
Construction takes longer than allowed       The contractor is well resourced and has the available
for.                                         resources to deliver this project successfully in conjunction with
                                             current works on hand. The use of precast materials such as
                                             concrete abutment panels and deck units reduce the risk of
                                             construction delays.
Safety
Site safety                                  The contractor has extensive experience with similar works and
                                             would be appointed as the Principal Contractor responsible for
                                             all Workplace Health and Safety of the site.
                                             Prior to construction commencing, a safety in design report,
                                             work place health and safety and final traffic management plans
                                             will be required to be submitted to Council for review.
                                             Regular audits on contractor compliance with these approved
                                             plans will be undertaken by Council and WH&S teams
                                             throughout construction.

High-risk work using machinery and           The contractor is accredited to AS 4801 (Occupational Health
hoisting involved.                           & Safety Management Systems) and the contractor has
                                             demonstrated their capability through the tender process.
                                             The contractor is experienced having successfully completed
                                             several similar type bridge projects within the past years.
Environmental Harm
There is risk that the works impact on       The contractor is responsible for the development and
the environment                              implementation of strategies to minimise impact such as noise,
                                             dust and vibration.
                                             The superintendent and Council staff will closely monitor the
                                             design and construction phase to ensure impacts are
                                             minimised.
Scope and Quality
Risk of not meeting project objectives.      To be managed through reviews performed by experienced
                                             Superintendent and Council staff, supported by a specialist
                                             consultant.
Public Disruption        and     Council
Reputation
Traffic disruption due total road closure    An external consultant has prepared a traffic management
at the site location.                        impact feasibility report including recommendations to minimise
                                             the impact to motorists. These recommendations have been
                                             translated to specific requirements for contractor.
                                             A detour will be required through local roads. Enabling works,
                                             temporary speed limits and additional signage will be installed
                                             to improve safety. These works are to be addressed by the
                                             contractor in preparing traffic management plans.
                                             Council has engaged an experienced communication /
                                             community engagement consultant who will closely work with
                                             Council’s Communications and Infrastructure departments, as
                                             well with the contractor to inform affected residents and
                                             businesses in advance and to act as the point of contact during
                                             construction.

                                                                                               Page 22 of 25

Section 23

SPECIAL MEETING AGENDA                                                              16 DECEMBER 2019


                  RISKS                                              MITIGATION
 Noise from plant and equipment may be       This will be minimised wherever possible by working during
 a cause of disruption to local residents.   normal working hours.
 Vibration during piling and demolition      The piling method has been chosen to minimise vibration. A
                                             noise and vibration mitigation plan will be in implemented to
                                             minimise nuisance.

Consultation

External Consultation – Community & Stakeholder
 Telstra
 Unity Water
Internal Consultation


Departments/Sections Consulted:

     Chief Executive Officer    X   Community Services                        X   Corporate Services
     Executive Officer              Director                                      Director
     Executive Support              Community Development                     X   Financial Services
                                    Community Facilities                          ICT
                                    Libraries & Galleries                     X   Procurement & Fleet
                                    Local Laws                                    Property
                                X   Waste & Environmental Health                  Revenue Services

 X   Executive Services         X   Environment & Sustainable Development     X   Infrastructure Services
     Director                       Director                                  X   Director
 X   Community Engagement           Building & Plumbing Services              X   Asset Management
 X   Customer Service               Development Assessment                        Buildings and Facilities
     Governance                     Economic Development                          Civil Operations
     People and Culture         X   Environmental Services                        Disaster Management
                                    Strategic Land Use Planning               X   Infrastructure Planning,
                                                                                  Design and Delivery




                                                                                             Page 23 of 25

Section 24

ATTACHMENT 1




 Page 24 of 25

.       .         .              .        .                  ATTACHMENT 1
  NOOSA SHIRE COUNCIL Weighted Attribute Evaluation Spreadsheet - Final Evaluation
       conte
       conan

                                    ALTERNATIVE              Constructions
                                        Resultant    Resultant    Resultant    Resultant    Resultant
 Evaluation Criteria   Weighting (%)    score x      score x      score x      score x      score x
                                        weighti      weighting    weighting    weighting   weighti
 a
bom                                   | ee [om [ow fe |               |     fe |          |
  mosis              | we | me | om | as |               |» | am | mm | om | o | om
fom fT |                                    |     fm |         fs]          |      | © |
fomamooacomy          [| © | >» |                  [o |       [=| |= |» | os
    cchniatscore fom]                smote                 ||               soe    |e

                                    ALTERNATIVE              Constructions
 Total Fees (Pc)          30%       $2,619,227   $2,959,674   $2,985,310   $2,986,080   $4,110,714
 Average Fees (Pav) $..cccccccccesseessesesee $3,132,201
ree                              a
 nomad Se)                       a
  Weighted Price Score (Pw)

                                                                                       Page 24 of 25

Section 25

ATTACHMENT 2




Page 25 of 25

ti
                                                                                    i
                                                                                         3
                                                                              Lal        t
                                                                              Li
                                                                   5a           1)|
                                                                   ;       CS |        i
                                    Hl                                 Ki     iy
                                     3                             i          \  { \ \\
                                    a                              .          \        bie
                                    i i                            4           4  || | aa?
                               at”         |i                                 iui      Wi
                          Hi  4! iL                                             1 ||
                           fie                                                    |!
                           SS            ; F                  fa               ‘ 1]
              i              bie         i                    i           mE      ii
                              a    ——                                          .      -)?
              g              aj                             ff 2               NS   14)
                             ee                               4                    nl
                             H   I        ;                   i      2         “\  | |
                                 i                    P        |     H              (|
    a                       A                       a
      e%                     |     5                ‘                          SS ttt
      :                     7                       EY               OW
    if. Cp                  I                       are *            i         NA
    a                      HT                       ly   fg           i        Ee
                           4                                         i         4 |       i
                           1                                                       |     i
                          bi | | |-a>                           i              > ||
                              (I                               i               Sa        |
                           :                                t  |                   II
                           i  !                                                 yi
                                                         [~    i                Xs | 1
                          ‘of                            Hy    |                Pat
                          !                              tc  Tih)
                                eS                       i                           iW
                          i|f                            i   NG                 ml
                         ai | -o-—                                              AS
                          |         i                                            .
                         *                                          /            SX
                         me                                                      i
                         ut   i      i                            i              .
                         te                                       Hl             . att i
                                                                  i                  My
                          !                                                      ay   tii!
                                                                                      |
                                                                                   i Wi
                                                                                   z ra
                                                                                   Lull  Sf
:                                                                                        |
a                                                                                    >
e                                                                                    >
ol
2                                                                                    g
                                                                                     =
o                                                                                    mn
                                                                                     =
                                                                                     =
                                                                                     i)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.