Further Advice Letter Response_FINAL
Rational Method Peak Flow Calculations
Job No: 17155
Job Type: Proposed Residential Development
Address: Precinct E2 Noosa Springs, Noosah
Council: Noosa Council
IFD Data: 26.8625 (S),152.9625 (E) Minor Storm: Q10 Designed: WB
1
I10 71mm/hr Major Storm: Q100 Checked: HM
Pre Development Post Development
Time of Concentration
Standard Inlet Time Standard Inlet Time
Standard Inlet Time 5 mins Standard Inlet Time 5 mins
Sheet Flow (Friends Equation) Sheet Flow (Friends Equation)
Sheet flow length (L) m Sheet flow length (L) m
roughness (n) short grass roughness (n) short grass
Fall of NSL m Fall of NSL m
Slope of Surface (S) % Slope of Surface (S) %
total 0.0 mins total 0.0 mins
Concentrated Overland Flow Concentrated Overland Flow
Flow distance m Flow distance m
velocity 1.5 m/s velocity 1.5 m/s
mins 0.0 mins mins 0.0 mins
Surface type multiplier 3.0 Surface type multiplier 3.0
total 0.0 mins total 0.0 mins
Total tc 5.0 mins Total tc 5.0 mins
Runoff Volume Calculations
Name Area (ha) tc fi C10 Name Area (ha) tc fi C10
0.092 0.57 0.81 0.092 0.61 0.82
Total 0.092 5.0 0.81 Total 0.092 5.0 0.82
Frequency Frequency
ARI Cy Iy Qy ARI Cy Iy Qy
Factor A (Ha) Factor A (Ha)
(years) (Fy*C10) (mm/h) (m3/s) (years) (Fy*C10) (mm/h) (m3/s)
(Fy) (Fy)
3 mth 0.010 3 mth 0.010
1 0.800 0.651 124 0.092 0.021 1 0.800 0.658 124 0.092 0.021
2 0.850 0.691 139 0.092 0.025 2 0.850 0.699 139 0.092 0.025
5 0.950 0.773 186 0.092 0.037 5 0.950 0.781 186 0.092 0.037
10 1.000 0.813 219 0.092 0.045 10 1.000 0.822 219 0.092 0.046
20 1.050 0.854 251 0.092 0.055 20 1.050 0.863 251 0.092 0.055
50 1.150 0.935 295 0.092 0.070 50 1.150 0.945 295 0.092 0.071
100 1.200 0.976 329 0.092 0.082 100 1.200 0.987 329 0.092 0.083
Page 1 of 1 9/02/2022