“Adamson Town Planning, specialising in providing higher order town planning advice”
In summary, the changes made to the proposal are in direct response to the issues raised in
the request for further information. Following further deliberations with the ecology, koala,
bushfire experts and the arborist, the applicant has reduced the number of units being
proposed and relocated Unit 1 to above the carpark.
This change reduces the overall impact on the site, in particular, near the riparian area to the
northwest with no bushfire mitigation now required in this area. The onsite inspection with the
cabin locations surveyed has also resulted in more confidence about the trees that can be
retained. Overall, there is a net increase in the number of koala habitat trees being retained on
the site and less site disturbance with ongoing tree and weed management (refer Attachment
3).
It should be noted that under the Tourist Accommodation Zone Code, performance outcome
PO7 specifically identifies the site (Lot 203 on SP267424) to be used for a resort complex and
short-term accommodation, which is currently the case. The proposed development
adjoins/extends across land included within the same zone and is to be integrated and
amalgamated with the existing RACV Resort.
Request for Further Information
Issue – Stormwater Quality Targets and Treatment Device Details
Information Required:
1. Provide an updated SWMP, MUSIC model and preliminary engineering plans which address
the following:
1.1. Provide geotechnical borehole and test results demonstrating that the proposed ‘pipeless’
bioretention will function at the proposed location by providing the following for the
bioretention location: In-situ Soil classification, Groundwater level (BGL and mAHD), and
In-situ saturated hydraulic conductivity test results at proposed level of bioretention base
1.2. Demonstrate that the In-situ saturated hydraulic conductivity results have been correctly
applied to the MUSIC model. These rates should be applied as the bioretention design
saturated hyd cond
1.3. Provide updated plans showing the spatial requirements for the updated (enlarged) pipeless
bioretention system
1.4. Provide details of the rainfall-runoff and pollutant export parameters adopted for the source
nodes in the MUSIC modelling (pre-development and post-development scenarios)
1.5. Show how the rainwater tank overflows and the runoff from the raised walkways will
physically be able to drain to the proposed bioretention device, as assumed in the MUSIC
model
4|Page
18006 – RACV Noosa Resort, July 2023
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Response to 2nd Council Information Request.pdfRelated documentApplication case desk ↗
About this file
- File size
- 740 KB (small file)
- File type
No other editions are linked here.