Project No. PG-9236                                                                                                                  Page | 4
November 2022
Ref: PG-9236, 2022-11-01, ASSMP VER 1
Looroo Property Trust – Acid Sulfate Soil Management Plan – Proposed Residential Development, 128-132 Gympie Terrace, Noosaville




                                       Water
                                       Compliance failures regarding specified performance criteria shall
                                       be recorded including the date, time, nature of failure and actions
                                       taken to rectify the situation. Monitoring results should be reviewed
                                       in relation to site management practices on a regular basis and
                                       improvement strategies should be developed as required.
Responsibility                         The satisfactory implementation of the ASSMP will be the
                                       responsibility of the Earthworks Contractor. The ASS Consultant will
                                       ensure that:
                                       • the contractor is made aware of site specific conditions and
                                           implications for the management of ASS within the site; and
                                       •     correct methods for the collection of samples and testing are
                                             employed and the reporting of results to the relevant site
                                             authorities.
                                       The Earthworks Contractor’s responsibilities will include:

                                       •     awareness of site conditions                             and       requirements       for   the
                                             implementation of the ASSMP;
                                       •     modifying earthworks/construction procedures to comply with
                                             the ASSMP and erosion control plan;
                                       •     propose any corrective action measures to be approved by the
                                             ASS Consultant; and
                                       •     implementing approved correction actions.
Reporting                              The ASS Consultant shall report to the Project Manager on a regular
                                       basis on the performance of the site management plan.

                                       The Contractor’s Representative shall report to the Project Manager
                                       and to the ASS Consultant on:

                                       •     the effectiveness of the operating strategies;
                                       •     problems in implementing the ASSMP management strategies;
                                       •     compliance with testing requirements run-off control and
                                             materials handling; and
                                       •     effectiveness of any corrective action adopted.
Log in to download the original file

PG-9236, 2022-10-31, ASR VER 1.pdf · 2.9 MB (large file)

The download may take up to a minute.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.