CAPITAL PROGRAM 2022/23 DELIVERY STATUS · Report
SERVICES & ORGANISATION COMMITTEE MEETING 8 AUGUST 2023
6.1 CAPITAL PROGRAM 2022/23 DELIVERY STATUS
Author Acting Director Infrastructure Services, Shaun Walsh
Infrastructure Services Department
Index ECM\Subject\2022-2023 Capital Works Program
Attachments None
EXECUTIVE SUMMARY
This report provides a status update for the Capital Works Program as at 30 June 2023.
• The total proposed expenditure for capital works for 2022/2023 financial year is ($54.1m),
inclusive of carry forwards ($11m), expenditure in direct control of Infrastructure Delivery
($49.8m), and other such as community projects, ICT and fleet ($4.3m).
• As at 30 June 2023, Council has expended a total of 79% of the 2022/2023 financial year
budget with another $6.7m in commitments.
• The ongoing reduced availability of labour, equipment and materials and a ‘hot’ construction
industry is proving challenging however works are currently being managed within overall
budget limitations where feasible.
• The road reseal program has expended $5.9m of the $6.8m budget for 2022/2023 financial
year.
• Council has a current forecast of grant funding revenue of $20.2m while Council’s
contribution to projects with grant funding is at $17.3m and non-grant capital projects amount
to $19.1m.
• The Design Services team is currently undertaking design works and providing design
support to 56 projects scheduled within the 2022/2023 financial year, with a combined design
and construction value of $16.7m.
• The Planning team is currently supporting key master planning initiatives with multiple sub-
projects; estimated value $350,000 in 2022/2023 and an estimated future project investment
value of $15m+.
• There are currently 41 multi-year projects in various stages of completion
RECOMMENDATION
That Council note the report by the Infrastructure Planning, Design & Delivery Manager to the
Services & Organisation Committee Meeting dated 8 August 2023 providing an update on the
delivery of the 2022/2023 Capital Program as at 30 June 2023.
REPORT
This report is to inform Council of the overall status of the Capital Works Program at the end of
June 2023.
The report provides an opportunity to highlight and discuss projects within the program and
confirm the delivery status of projects delivered in the final quarter of the 2022/2023 financial
year.
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
The download may take up to a minute.
Full text of the other 8 pages
Page 2
SERVICES & ORGANISATION COMMITTEE MEETING 8 AUGUST 2023
It is important to note that the financial summary provided in this report is subject to timing and
reported accruals (i.e. a major project funded over multiple years may be significantly closer to
completion than the 2022/2023 financials may indicate).
The report does not address disaster recovery project, which will be subject to separate reporting
1. Current Projects
The major focus in the 3rd quarter of the 22/23 financial year has been:
Continuing various stages of • Tewantin, NDSC Stage 1 McKinnon Drive -
construction of major projects: Community Sports Complex
• Peregian Beach, Living Fire Tech Lab - Disaster
Rec Cat D
• Federal, Middle Creek Road - Reconstruction
• Noosa Heads, Dog Beach - SEMP
• Sunrise Beach, Sobraon Street - Slope
Stabilisation
• Black Mountain, Lawnville Road - Bridge
Renewal
• Tewantin, Sundial Park - BMX Pump Track
Upgrade
• Sunshine Beach, Adams Street - Land Slip
Design
Emergent works within • Sunrise Beach Shopping Centre - Shop Fit Out
2022/2023 financial year:
• Boreen Point Campground - Storage Shed
Replacement
• Sunshine Beach, Adams Street - Land Slip
Design
• Peregian Beach, Digital Hub - Office Fit-Out
• Noosa Northshore Campground - Wastewater
System Renewal
• Noosa River Holiday Park - Access Ramp
Renewal
• Noosa Leisure Centre - Replacement of
External Emergency Exit Doors
• Noosa North Shore - Wastewater System
• The J - Airconditioning Condenser Unit
Replacement
Review of tender submissions • Shire Wide, Pathway Program
for major projects budgeted for
construction delivery this • Noosaville, Foreshore Masterplan
financial year:
• Noosa Heads, Arkana Drive - Median Strip
Stabilisation
Page 3
SERVICES & ORGANISATION COMMITTEE MEETING 8 AUGUST 2023
Upcoming tenders, evaluations • Tewantin, Doonella Bridge - Renewal
and awards for projects
budgeted for construction in • Noosa Heads, Garth Prowd Bridge - Renewal
the 2022/2023 financial year:
• Noosa Heads, Noosa Woods - Pathway
• Sunshine Beach, Ed Webb Park - Upgrade
• Noosa Waters, Entry Statement – Renewal
• Tewantin, Doonella Bridge (Design) – Renewal
• Noosa Heads, Noosa Drive Halse Lane to
Sunshine Beach Rd – New
The Design Services team are currently undertaking design works and providing design support
to 56 projects scheduled within the 2022/2023 financial year, with a combined design and
construction value of $16.7m.
Design output this quarter has been impacted by the movement of key staff (currently 2 (two)
vacant full-time equivalent positions) and ongoing construction support.
The road reseal program has expended $5.9m of the $5.7m budget for 2022/2023 financial
year. Of the annual program, reseal of the following roads were undertaken during the final
quarter of 2023/2023 financial year:
• Noosa Springs, Noosa Springs Drive
• Noosa, David Low way
• Sunshine Beach, Dolphin Bay Drive
• Tewantin, Moorindil Street Roundabout.
• Peregian Beach, Heron Street, Peregian Beach.
• Noosaville, Shorehaven Drive.
Of the annual gravel resheeting program the following roads were undertaken during the final quarter
of the 2022/2023 financial year:
• Kin Kin, Neusa Vale Road
• Kin Kin, Bates Road
• Cootharaba, Kinmond creek Road.
The Shire Wide Pathway Program continues into the 2022/2023 financial year. The following
pathways received renewal and upgrade works during the final quarter of the final quarter of
2022/2023:
• Pomona, Stan Topper/ Memorial Avenue Missing Pathway Link
• Tewantin, Moorindil Street
• Cooroy, Maple Street Pathway/ Overlander Avenue to Bruce Highway Overpass - Ongoing
• Cooroy, Miva Street/ Tewantin Road - Ongoing,
The following pathways are in the planning and procurement stages, in preparation for undertaking
the works.
• Tewantin, Memorial Park/ Poinciana Avenue Pathway
Page 4
SERVICES & ORGANISATION COMMITTEE MEETING 8 AUGUST 2023 • Noosa Heads, Noosa Woods – Pathway • Tewantin, Cooroy Noosa Road Missing Pathway Link. As part of Council’s ongoing program of upgrading priority bus stops and shelters to comply with Commonwealth Disability Standards for Assessable Public Transport infrastructure, upgrade of 8 bus stops across Noosa Heads, Noosaville, Peregian Beach, Pinbarren and Tewantin will be carried out over the financial year. The final quarter of the 2022/2023 financial year saw the completion of the bus stop upgrade program, with the following stops successfully upgraded throughout the year: • Noosaville, Noosa Parade (Key Circuit, Eastbound & Westbound) • Noosaville, Noosa Parade (Witta Circle, Westbound) • Noosaville, Hilton Terrace (Noosa Convention Centre) • Noosaville, Eumundi Noosa Road (Rene Street) • Tewantin, Gympie Street (Werin Street) • Peregian, Beach David Low Way (Woodland Drive) • Pinbarren, Greenridge Pinbarren Road. 2. Project Updates Whole of Shire Mobile Library Service Solution Mobile library launched in June2023. Outreach programs continue and are increasing in popularity. Detailed Design Redevelopment Cooroy Sports Complex Concept level floor plans and renders completed for Cooroy Sports Complex. Currently awaiting development approvals. Replacement of External Emergency Exit Doors, Noosa Leisure Centre Stadium External emergency exit doors replaced in June 2023 to ensure the safety of all guests and employees.
Page 5
SERVICES & ORGANISATION COMMITTEE MEETING 8 AUGUST 2023 NDSC Stage 1 McKinnon Drive Community Sports Complex Construction is nearing completion on the McKinnon Drive Community Sports Complex with practical completion on target for July 2023. Cooroy Cemetery Equipment Shed Upgrade works to the Cooroy Cemetery Equipment Shed have progressed with awarding of works for water storage and supply, concrete slabs, car spaces and people with disabilities compliant pathways with line marking. Target completion quarter 4, 2023/2024 Shire Wide Pathway Program The annual pathway program continues into the 4th quarter of 22/23 with works taking place in Tewantin, Pomona and Cooroy. 3. Grant Funding The 2022/2023 financial year Capital Works program includes an unprecedented amount of grant funding. Figures 1 and 2 below demonstrate the non-grant funded capital projects vs projects with grant funding and Council’s contribution towards those with grant funding. Figure 1 detail Percentage of CWP Value of CWP Non-Grant Projects 34% $19.1m
Page 6
SERVICES & ORGANISATION COMMITTEE MEETING 8 AUGUST 2023
Projects with Grant Funding 66% Refer figure 2 for more
detail
Figure 1
Figure 2 detail Percentage Value
of CWP of CWP
Non grant projects 34% $21.1m
Grant funding revenue 36% $20.2m
Council's contribution to 31% $17.3m
projects with grant funding
Figure 2
4. Completed Projects
While the 4th quarter continues to experience a heated construction market with ongoing material
shortages, lengthy lead times, pricing increases and contractor availability issues; 79% of capital
expenditure has been completed to date this quarter. The Project Control Group and Capital
Works Executive have continued to enable staff and Council to make informed decisions that
relate to projects being delivered throughout the year.
This quarter has seen the successful completion of the following key projects:
Page 7
SERVICES & ORGANISATION COMMITTEE MEETING 8 AUGUST 2023
Shire Bus Shelter Disabled
Compliant Annual Program
Remaining two (2) DDA compliant
bus shelters within the annual
program have been delivered in the
final quarter of 22/23 financial year
Link to Corporate Plan
Theme No. 2. - Liveability
Liveability encompasses housing, facilities and services, transport, health and wellbeing to enable
an inclusive, connected and vibrant community.
Objective 2.7
Fund and deliver sustainable assets and facilities and associated services responding to the
changing needs of the community and the challenges and opportunities of the future.
Previous Council Consideration
Nil
Finance
The year-to-date capital delivery expenditure to 30th June is $42.5m or 79% of the capital
program total.
Figures 3 and 4 below demonstrate the year-to-date budget, actual expenditure and percentage
of program delivered including commitments, broken down for Capital and Other Capital. Other
Capital includes Asset Management, Information Communication and Technology, Fleet, and
the Planning Scheme expansion.
Other Capital
Capital Total Capital Works
(ICT, Fleet)
CWP Baseline BR1
$49,777,771 $4,364,152 $54,141,923
Budget 22/23
Budget Year to Date $49,777,771 $4,364,152 $54,141,923
Actuals Year To Date $39,712,853 $2,883,634 $42,596,487
*Remaining
Commitments/contract $10,064,918 $1,480,518 $11,545,436
values
Figure 3 – Capital Finance data as at 30th June 2023.
Page 8
SERVICES & ORGANISATION COMMITTEE MEETING 8 AUGUST 2023 Figure 4 – Budget Status of Capital Works as at 30th June 2023 Risk & Opportunities Risks that have presented challenges to delivery of the Capital Works Program include the increased costs associated with reduced availability of resources, equipment, and materials. This is compounded by a decreased availability of contractors and reluctance for contractors to price tenders. The construction industry is also proving challenging due to this inflated market and future uncertainty with a lack of confidence in the supply chain and availability of manpower, resulting in the private sector adopting a wait and see approach due to mentioned constraints. A heated construction market and vacant full-time equivalent positions have continued to provide ongoing project delivery challenges throughout the 3rd quarter of 2022/2023 financial year. The Infrastructure Services Department is continuing to address staffing shortages and high turnover with recruitment underway for a Design Coordinator, Designer, Project Managers, and Transport and Traffic Coordinator. During the 4th quarter of 2022/2023, a Graduate Engineer has been onboarded within the Design department. In addition management of the program includes the added complexity of large amounts of grant funding and support in the programming of disaster recovery projects. With the support of the Executive, a resourcing plan is currently being considered for the 2023/24 FY, as the value and number of projects is significant and delivery of the program requires more investment in project planning, workforce planning, and staging of design and delivery activities to be consistent with available resources Consultation External Consultation - Community & Stakeholder
Page 9
SERVICES & ORGANISATION COMMITTEE MEETING 8 AUGUST 2023
Nil
Internal Consultation
Departments consulted:
Office of the CEO, Mayor & Community Services Corporate Services
Councillors
Mayor & Councillors Director Director
Chief Executive Officer Community Development x Financial Services
Executive Officers Sport & Active Lifestyles Fleet
Community Engagement Arts & Culture Revenue Services
People & Culture Community Connection ICT
Governance Customer Experience x Commercial Property
Strategy & Environment & Development & Regulation Infrastructure Services
Sustainable Development
Director Director x Director
Strategic Land Use Planning Development Assessment x Infrastructure Planning,
Design and Delivery
Economic Development & Local Laws Civil and Asset operations
Destination Management
Environmental Services Environmental Health x Asset Management
Innovation & Digital Hub Building & Plumbing x Building & Facilities
x Property / Permits Disaster Management
Waste