Skip to the record
The definitive source for everything Noosa Council.

Original source · versioned page text

CAPITAL PROGRAM 2022/23 DELIVERY STATUS · Report

of 9

Page text shows just the words. Original shows the document exactly as it was published.

SERVICES & ORGANISATION COMMITTEE MEETING                                              8 AUGUST 2023


6.1       CAPITAL PROGRAM 2022/23 DELIVERY STATUS


Author              Acting Director Infrastructure Services, Shaun Walsh
                    Infrastructure Services Department
Index               ECM\Subject\2022-2023 Capital Works Program
Attachments         None


EXECUTIVE SUMMARY
This report provides a status update for the Capital Works Program as at 30 June 2023.
      •   The total proposed expenditure for capital works for 2022/2023 financial year is ($54.1m),
          inclusive of carry forwards ($11m), expenditure in direct control of Infrastructure Delivery
          ($49.8m), and other such as community projects, ICT and fleet ($4.3m).
      •   As at 30 June 2023, Council has expended a total of 79% of the 2022/2023 financial year
          budget with another $6.7m in commitments.
      •   The ongoing reduced availability of labour, equipment and materials and a ‘hot’ construction
          industry is proving challenging however works are currently being managed within overall
          budget limitations where feasible.
      •   The road reseal program has expended $5.9m of the $6.8m budget for 2022/2023 financial
          year.
      •   Council has a current forecast of grant funding revenue of $20.2m while Council’s
          contribution to projects with grant funding is at $17.3m and non-grant capital projects amount
          to $19.1m.
      •   The Design Services team is currently undertaking design works and providing design
          support to 56 projects scheduled within the 2022/2023 financial year, with a combined design
          and construction value of $16.7m.
      •   The Planning team is currently supporting key master planning initiatives with multiple sub-
          projects; estimated value $350,000 in 2022/2023 and an estimated future project investment
          value of $15m+.
      •   There are currently 41 multi-year projects in various stages of completion
RECOMMENDATION
That Council note the report by the Infrastructure Planning, Design & Delivery Manager to the
Services & Organisation Committee Meeting dated 8 August 2023 providing an update on the
delivery of the 2022/2023 Capital Program as at 30 June 2023.



REPORT
This report is to inform Council of the overall status of the Capital Works Program at the end of
June 2023.

The report provides an opportunity to highlight and discuss projects within the program and
confirm the delivery status of projects delivered in the final quarter of the 2022/2023 financial
year.
Log in to download the original file

Report.pdf · 3.9 MB (large file)

The download may take up to a minute.

Full text of the other 8 pages

Page 2

SERVICES & ORGANISATION COMMITTEE MEETING                                         8 AUGUST 2023


It is important to note that the financial summary provided in this report is subject to timing and
reported accruals (i.e. a major project funded over multiple years may be significantly closer to
completion than the 2022/2023 financials may indicate).

The report does not address disaster recovery project, which will be subject to separate reporting

1. Current Projects
The major focus in the 3rd quarter of the 22/23 financial year has been:
  Continuing    various     stages of       • Tewantin, NDSC Stage 1 McKinnon Drive -
  construction of major projects:              Community Sports Complex
                                            •   Peregian Beach, Living Fire Tech Lab - Disaster
                                                Rec Cat D
                                            •   Federal, Middle Creek Road - Reconstruction
                                            •   Noosa Heads, Dog Beach - SEMP
                                            •   Sunrise Beach,       Sobraon    Street   -   Slope
                                                Stabilisation
                                            •   Black Mountain, Lawnville Road - Bridge
                                                Renewal
                                            •   Tewantin, Sundial Park - BMX Pump Track
                                                Upgrade
                                            •   Sunshine Beach, Adams Street - Land Slip
                                                Design
  Emergent      works       within          •   Sunrise Beach Shopping Centre - Shop Fit Out
  2022/2023 financial year:
                                            •   Boreen Point Campground - Storage Shed
                                                Replacement
                                            •   Sunshine Beach, Adams Street - Land Slip
                                                Design
                                            •   Peregian Beach, Digital Hub - Office Fit-Out
                                            •   Noosa Northshore Campground - Wastewater
                                                System Renewal
                                            •   Noosa River Holiday Park - Access Ramp
                                                Renewal
                                            •   Noosa Leisure Centre - Replacement of
                                                External Emergency Exit Doors
                                            •   Noosa North Shore - Wastewater System
                                            •   The J - Airconditioning Condenser             Unit
                                                Replacement
  Review of tender submissions              •   Shire Wide, Pathway Program
  for major projects budgeted for
  construction delivery this                •   Noosaville, Foreshore Masterplan
  financial year:
                                            •   Noosa Heads, Arkana Drive - Median Strip
                                                Stabilisation

Page 3

SERVICES & ORGANISATION COMMITTEE MEETING                                         8 AUGUST 2023


  Upcoming tenders, evaluations             •   Tewantin, Doonella Bridge - Renewal
  and awards for projects
  budgeted for construction in              •   Noosa Heads, Garth Prowd Bridge - Renewal
  the 2022/2023 financial year:
                                            •   Noosa Heads, Noosa Woods - Pathway
                                            •   Sunshine Beach, Ed Webb Park - Upgrade
                                            •   Noosa Waters, Entry Statement – Renewal
                                            •   Tewantin, Doonella Bridge (Design) – Renewal
                                            •   Noosa Heads, Noosa Drive Halse Lane to
                                                Sunshine Beach Rd – New

The Design Services team are currently undertaking design works and providing design support
to 56 projects scheduled within the 2022/2023 financial year, with a combined design and
construction value of $16.7m.

Design output this quarter has been impacted by the movement of key staff (currently 2 (two)
vacant full-time equivalent positions) and ongoing construction support.

The road reseal program has expended $5.9m of the $5.7m budget for 2022/2023 financial
year. Of the annual program, reseal of the following roads were undertaken during the final
quarter of 2023/2023 financial year:
   • Noosa Springs, Noosa Springs Drive
   •   Noosa, David Low way
   •   Sunshine Beach, Dolphin Bay Drive
   •   Tewantin, Moorindil Street Roundabout.
   •   Peregian Beach, Heron Street, Peregian Beach.
   •   Noosaville, Shorehaven Drive.
Of the annual gravel resheeting program the following roads were undertaken during the final quarter
of the 2022/2023 financial year:
   •   Kin Kin, Neusa Vale Road
   •   Kin Kin, Bates Road
   •   Cootharaba, Kinmond creek Road.
The Shire Wide Pathway Program continues into the 2022/2023 financial year. The following
pathways received renewal and upgrade works during the final quarter of the final quarter of
2022/2023:
   •   Pomona, Stan Topper/ Memorial Avenue Missing Pathway Link
   •   Tewantin, Moorindil Street
   •   Cooroy, Maple Street Pathway/ Overlander Avenue to Bruce Highway Overpass - Ongoing
   •   Cooroy, Miva Street/ Tewantin Road - Ongoing,

The following pathways are in the planning and procurement stages, in preparation for undertaking
the works.
   •   Tewantin, Memorial Park/ Poinciana Avenue Pathway

Page 4

SERVICES & ORGANISATION COMMITTEE MEETING                                      8 AUGUST 2023


   •   Noosa Heads, Noosa Woods – Pathway
   •   Tewantin, Cooroy Noosa Road Missing Pathway Link.


As part of Council’s ongoing program of upgrading priority bus stops and shelters to comply with
Commonwealth Disability Standards for Assessable Public Transport infrastructure, upgrade of
8 bus stops across Noosa Heads, Noosaville, Peregian Beach, Pinbarren and Tewantin will be
carried out over the financial year.

The final quarter of the 2022/2023 financial year saw the completion of the bus stop upgrade
program, with the following stops successfully upgraded throughout the year:
   • Noosaville, Noosa Parade (Key Circuit, Eastbound & Westbound)
   •   Noosaville, Noosa Parade (Witta Circle, Westbound)
   •   Noosaville, Hilton Terrace (Noosa Convention Centre)
   •   Noosaville, Eumundi Noosa Road (Rene Street)
   •   Tewantin, Gympie Street (Werin Street)
   •   Peregian, Beach David Low Way (Woodland Drive)
   •   Pinbarren, Greenridge Pinbarren Road.

2. Project Updates
  Whole of Shire Mobile Library Service
  Solution
  Mobile     library launched in
  June2023. Outreach programs
  continue and are increasing in
  popularity.




  Detailed Design Redevelopment Cooroy
  Sports Complex
  Concept level floor plans and renders
  completed for Cooroy Sports
  Complex.       Currently     awaiting
  development approvals.

  Replacement       of   External
  Emergency Exit Doors, Noosa
  Leisure Centre Stadium
  External emergency exit doors
  replaced in June 2023 to ensure the
  safety of all guests and employees.

Page 5

SERVICES & ORGANISATION COMMITTEE MEETING                                8 AUGUST 2023




  NDSC  Stage    1   McKinnon           Drive
  Community Sports Complex
  Construction is nearing completion
  on the McKinnon Drive Community
  Sports Complex with practical
  completion on target for July 2023.



  Cooroy Cemetery Equipment Shed
  Upgrade works to the Cooroy Cemetery
  Equipment Shed have progressed with
  awarding of works for water storage and
  supply, concrete slabs, car spaces and
  people with disabilities compliant pathways
  with line marking. Target completion quarter
  4, 2023/2024




 Shire Wide Pathway Program
 The annual pathway program continues into
 the 4th quarter of 22/23 with works taking
 place in Tewantin, Pomona and Cooroy.




3. Grant Funding
The 2022/2023 financial year Capital Works program includes an unprecedented amount of
grant funding. Figures 1 and 2 below demonstrate the non-grant funded capital projects vs
projects with grant funding and Council’s contribution towards those with grant funding.

 Figure 1 detail                         Percentage of CWP    Value of CWP
 Non-Grant Projects                             34%           $19.1m

Page 6

SERVICES & ORGANISATION COMMITTEE MEETING                                        8 AUGUST 2023


 Projects with Grant Funding                         66%             Refer figure 2 for more
                                                                     detail




 Figure 1

 Figure 2 detail                Percentage     Value
                                 of CWP        of CWP
 Non grant projects                34%          $21.1m
 Grant funding revenue              36%         $20.2m
 Council's contribution to          31%         $17.3m
 projects with grant funding




Figure 2

4. Completed Projects
While the 4th quarter continues to experience a heated construction market with ongoing material
shortages, lengthy lead times, pricing increases and contractor availability issues; 79% of capital
expenditure has been completed to date this quarter. The Project Control Group and Capital
Works Executive have continued to enable staff and Council to make informed decisions that
relate to projects being delivered throughout the year.

This quarter has seen the successful completion of the following key projects:

Page 7

SERVICES & ORGANISATION COMMITTEE MEETING                                        8 AUGUST 2023


      Shire     Bus      Shelter    Disabled
      Compliant Annual Program
       Remaining two (2) DDA compliant
       bus shelters within the annual
       program have been delivered in the
       final quarter of 22/23 financial year




Link to Corporate Plan
Theme No. 2. - Liveability

Liveability encompasses housing, facilities and services, transport, health and wellbeing to enable
an inclusive, connected and vibrant community.

Objective 2.7
Fund and deliver sustainable assets and facilities and associated services responding to the
changing needs of the community and the challenges and opportunities of the future.




Previous Council Consideration
Nil
Finance
The year-to-date capital delivery expenditure to 30th June is $42.5m or 79% of the capital
program total.

Figures 3 and 4 below demonstrate the year-to-date budget, actual expenditure and percentage
of program delivered including commitments, broken down for Capital and Other Capital. Other
Capital includes Asset Management, Information Communication and Technology, Fleet, and
the Planning Scheme expansion.

                                                        Other Capital
                                   Capital                               Total Capital Works
                                                         (ICT, Fleet)
 CWP Baseline BR1
                                    $49,777,771             $4,364,152           $54,141,923
 Budget 22/23
 Budget Year to Date                $49,777,771             $4,364,152           $54,141,923

 Actuals Year To Date               $39,712,853             $2,883,634           $42,596,487

 *Remaining
 Commitments/contract               $10,064,918             $1,480,518           $11,545,436
 values
Figure 3 – Capital Finance data as at 30th June 2023.

Page 8

SERVICES & ORGANISATION COMMITTEE MEETING                                         8 AUGUST 2023




Figure 4 – Budget Status of Capital Works as at 30th June 2023



Risk & Opportunities
Risks that have presented challenges to delivery of the Capital Works Program include the
increased costs associated with reduced availability of resources, equipment, and materials.
This is compounded by a decreased availability of contractors and reluctance for contractors to
price tenders. The construction industry is also proving challenging due to this inflated market
and future uncertainty with a lack of confidence in the supply chain and availability of manpower,
resulting in the private sector adopting a wait and see approach due to mentioned constraints.

A heated construction market and vacant full-time equivalent positions have continued to
provide ongoing project delivery challenges throughout the 3rd quarter of 2022/2023 financial
year. The Infrastructure Services Department is continuing to address staffing shortages and
high turnover with recruitment underway for a Design Coordinator, Designer, Project Managers,
and Transport and Traffic Coordinator. During the 4th quarter of 2022/2023, a Graduate
Engineer has been onboarded within the Design department.

In addition management of the program includes the added complexity of large amounts of
grant funding and support in the programming of disaster recovery projects.

With the support of the Executive, a resourcing plan is currently being considered for the 2023/24
FY, as the value and number of projects is significant and delivery of the program requires more
investment in project planning, workforce planning, and staging of design and delivery activities to
be consistent with available resources

Consultation
External Consultation - Community & Stakeholder

Page 9

SERVICES & ORGANISATION COMMITTEE MEETING                                                 8 AUGUST 2023


Nil


Internal Consultation
Departments consulted:

      Office of the CEO, Mayor &             Community Services               Corporate Services
              Councillors
         Mayor & Councillors                 Director                         Director

         Chief Executive Officer             Community Development       x    Financial Services
         Executive Officers                  Sport & Active Lifestyles        Fleet
         Community Engagement                Arts & Culture                   Revenue Services
         People & Culture                    Community Connection             ICT
         Governance                          Customer Experience         x    Commercial Property
      Strategy & Environment &             Development & Regulation          Infrastructure Services
      Sustainable Development
         Director                            Director                    x    Director
         Strategic Land Use Planning         Development Assessment      x    Infrastructure      Planning,
                                                                              Design and Delivery
         Economic Development &              Local Laws                       Civil and Asset operations
         Destination Management
         Environmental Services              Environmental Health        x    Asset Management
         Innovation & Digital Hub            Building & Plumbing         x    Building & Facilities
                                       x     Property / Permits               Disaster Management
                                                                              Waste

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.