ECM_23038802_v2_Decision Notice - Approved by Delegation of Authority MCU24 0044 & OPW24 0045 · MCU24/0044

of 15

Text shows just the words. Original shows the document exactly as it was published.

Check the original when the exact wording matters.

 

2404-40124 SRA

Attachment 3—Reasons for referral agency response
(Given under section 56(7) of the Planning Act 2016)

 

The reasons for the SARA's decision are:
« The proposed development is for operational work for prescribed tidal works for a pontoon.
* The proposed development involves operational work in a developed tidal waterway, and as such
required assessment under the State Development Assessment Provisions (SDAP).
« SARA assessed the application against State code 7: Maritime safety, of the SDAP (v3.0) and found it
complies, subject to conditions to ensure:
© the development is carried out generally in accordance with the plans of development
submitted with the application
© that at all times, all lights on or above the development site do not interfere with safe
navigation in surrounding waterways
© the development does not encroach on the navigation corridor or high-risk maritime zone to
ensure the safe passage of vessels
© = that debris from the development does not create a hazard to navigation
© that there is no residual material that could create a hazard to navigation.
« SARA assessed the application against State code 8: Coastal development and tidal works, of the
SDAP (v3.0) and found it complies, subject to conditions to ensure:
© the development is carried out generally in accordance with the plan of development
submitted with the application.
© that at alll times, the works, to which this approval relates are for private purpose only.
© any operator and contractor involved in the works ensures impacts on coastal values
(water quality) are avoided or minimised.
© works only use materials which are free from contaminants as defined under section 11 of
the Environmental Protection Act 1994.
© damaged works as a result of erosion, flooding or storm tide inundation, the registered
landowner(s) of the subject land shail be responsible for the removal of all debris at their
own expense.

Material used in the assessment of the application:

the development application material and submitted plans
Planning Act 2016

Planning Regulation 2017

the SDAP (version 3.0), as published by SARA

the Development Assessment Rules

SARA DA Mapping system

section 58 of the Human Rights Act 2019

Attachment 4—Representations about a referral agency response
provisions

 

(page left intensonaby blank)

‘State Assessment and Referral Agency Page 6 of 7

 

 

 

Document Set ID: 23038802 Page 11 of 15

Version: 2, Version Date: 30/05/2024

Used in these records

About this file

File size
697 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

ECM_23038802_v2_Decision Notice - Approved by Delegation of Authority MCU24 0044 & OPW24 0045.pdf · 697 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.