Attachment 9 - Traffic Engineering Report
Traffic Engineering Report Proposed Relocatable Home Park At Lot 2 & 3 Myall Street, Cooroy On behalf of Ruby Developments Pty Ltd
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.
Full text of the other 48 pages
Page 2
About TTM
For 30 years, we’ve been at the centre of the
Australian development and infrastructure industry.
Our unique combination of acoustics, data, traffic
and waste services is fundamental to the success of
any architectural or development project.
We have over 50 staff, with an unrivalled depth of
experience. Our industry knowledge, technical
expertise and commercial insight allow us to deliver
an exceptional and reliable service.
T: (07) 3327 9500
F: (07) 3327 9501
E: [email protected]
Revision Record
No. Author Reviewed/Approved Description Date
1. N. Garvey DRAFT DA Report 05/09/19
2. N. Garvey D. Grummitt (RPEQ. 19356) DA Report 09/09/19
3.
4.
5.
© 2017 - TTM Consulting Pty Ltd ABN 65 010 868 621
Level 8, 369 Ann Street, Brisbane. PO Box 12015 George Street Brisbane 4003
Page 3
Contents
1 Introduction ..........................................................................................................................................5
1.1 Background .................................................................................................................................. 5
1.2 Scope ............................................................................................................................................ 5
1.3 Site Location ................................................................................................................................. 5
1.4 Development Profile .................................................................................................................... 7
1.5 Development Access .................................................................................................................... 7
1.6 Parking.......................................................................................................................................... 7
1.7 Service Vehicles ............................................................................................................................ 8
2 Existing Transport Infrastructure ............................................................................................................9
2.1 The Road Network ........................................................................................................................ 9
2.2 Road Planning............................................................................................................................... 9
2.3 Public Transport and Pedestrian Facilities .................................................................................... 9
3 Site Access Arrangements .................................................................................................................... 11
3.1 Myall Street Access ....................................................................................................................11
3.2 Emergency Vehicle Access .........................................................................................................11
4 Car Parking Arrangements ................................................................................................................... 13
4.1 Council Parking Supply Requirement .........................................................................................13
4.2 Car Park Layout ..........................................................................................................................14
5 Service Vehicle Arrangements .............................................................................................................. 15
5.1 Council Requirements ................................................................................................................15
5.2 Proposed Service Vehicle Arrangements and Their Adequacy ...................................................15
6 Traffic Impact Assessment ................................................................................................................... 17
6.1 Scope ..........................................................................................................................................17
6.2 Existing Traffic Volumes .............................................................................................................17
6.2.1 Peak Hour .......................................................................................................................17
6.3 Future Base Traffic Volumes.......................................................................................................18
6.4 Development Traffic ...................................................................................................................18
6.4.1 Estimated Development Traffic Generation ...................................................................18
6.4.2 Estimated Development Traffic Distribution ..................................................................19
6.5 Future Project Traffic Volumes ...................................................................................................21
Site: Lot 2 & 3 Myall Street, Cooroy 2
Reference: 19BRT0357
Page 4
6.5.1 Opening Year (2024) Base Traffic Scenario ....................................................................21
6.5.2 Opening Year (2024) Project Traffic Scenario.................................................................22
6.5.3 Future Year (2034) Base Traffic Scenario .......................................................................22
6.5.4 Future Year (2034) Project Traffic Scenario ...................................................................23
7 Road Network Performance ................................................................................................................. 24
7.1 Myall Street / Site Access Assessment .......................................................................................24
7.1.1 Turn Lane Warrant Analysis............................................................................................24
7.1.2 SIDRA Analysis ................................................................................................................24
7.1.3 Conclusion ......................................................................................................................25
7.2 Myall Street/ State Route 6/ Nandroya Road Roundabout Assessment ....................................25
7.2.1 SIDRA Analysis ................................................................................................................25
7.2.2 Conclusion ......................................................................................................................27
8 Active Transport .................................................................................................................................. 28
8.1 Public Transport .........................................................................................................................28
8.2 Pedestrian and Cyclist Provisions ...............................................................................................28
9 Summary and Conclusions ................................................................................................................... 29
9.1 Development Summary ..............................................................................................................29
9.2 Car Parking Arrangements..........................................................................................................29
9.3 Site Access Arrangements ..........................................................................................................29
9.4 Service Vehicle Arrangements....................................................................................................29
9.5 Active Transport Facilities ..........................................................................................................30
9.6 Impact on Surrounding Road Network .......................................................................................30
9.7 Conclusion ..................................................................................................................................30
Appendix A Proposed Site Plan................................................................................................................. 31
Appendix B Service Vehicle Swept Paths .................................................................................................. 32
Appendix C Sidra Intersection Analysis ..................................................................................................... 33
Site: Lot 2 & 3 Myall Street, Cooroy 3
Reference: 19BRT0357
Page 5
Table Index Table 1.1: Proposed Land Uses .......................................................................................................................... 7 Table 2.1: Local Road Hierarchy ......................................................................................................................... 9 Table 3.1: Driveway Requirements for Myall Street Access ............................................................................. 11 Table 4.1: Parking Supply Requirement ........................................................................................................... 13 Table 4.2: Parking Design Requirements ......................................................................................................... 14 Table 6.1: Development Traffic Generation – Summary .................................................................................. 19 Table 7.1: Turn Lane Warrant Assessment – Myall Street / Site Access Intersection ...................................... 24 Table 7.2: Summary of Sidra Outputs (Myall Street / Site Access Intersection) ............................................... 25 Table 7.3: Summary of Sidra Outputs (Myall Street / State Route 6 / Nandroya Road Intersection) ............... 26 Figure Index Figure 1.1: Site Location – Broader Context Source: Google Maps ........................................................... 6 Figure 1.2: Site Area – Local Context Source: Queensland Globe ........................................................ 6 Figure 2.1: Council’s Active Transport Network Source: The Noosa Plan ..................... 10 Figure 5.1: Internal Service Vehicle Circulation................................................................................................ 16 Figure 6.1: Surveyed Peak Hour Traffic Volumes ............................................................................................. 17 Figure 6.2: Relocatable Dwellings Development Traffic Distribution ............................................................... 20 Figure 6.3: Cooroy Golf Clubhouse Development Traffic Distribution ............................................................. 20 Figure 6.4: Total Development Traffic Generation .......................................................................................... 21 Figure 6.5: Estimated 2024 Peak Hour Traffic, Without Development (2.0%pa growth) ................................. 21 Figure 6.6: Estimated 2024 Peak Hour Traffic, With Development ................................................................. 22 Figure 6.7: Estimated 2034 Peak Hour Traffic, Without Development (2.0%pa growth)................................. 22 Figure 6.8: Estimated 2034 Peak Hour Ultimate Traffic, With Development ................................................... 23 Figure 7.1: Proposed Myall Street / Site Access Intersection Layout ............................................................... 24 Figure 7.2: Existing Myall Street / State Route 6 / Nandroya Road Intersection Layout .................................. 26 Site: Lot 2 & 3 Myall Street, Cooroy 4 Reference: 19BRT0357
Page 6
1 Introduction
1.1 Background
TTM Consulting has been engaged by Ruby Developments Pty Ltd to prepare a traffic engineering report
investigating a proposed relocatable home park and the construction of a gold club. It is understood that a
Development Application will be lodged with Noosa Shire Council (NSC) with referral to State Assessment
and Referral Agency (SARA).
1.2 Scope
This report investigates the transport aspects associated with the proposed development. The scope of the
transport aspects investigated includes:
• Parking supply required to cater for development demand
• Identification of likely traffic volumes and traffic distribution from the future development
• Identification of likely traffic impact of development on the public road network
• Access configuration to provide efficient and safe manoeuvring between the site and the private road
network
• Internal road layout to provide efficient and safe internal manoeuvring for service vehicles
• Suitability of access and internal facilities to provide for pedestrian and cyclist operation
• Access to suitable level of public transport
To assess the proposed transport arrangements, the development plans have been assessed against the
following guidelines and planning documents:
• The Noosa Plan 2006;
• Australian Standards for Parking Facilities (AS2890 series);
• Department of Transport and Main Roads ‘Road Planning and Design Manual 2nd Edition’ and associated
Austroads Guide to Road Design series; &
• Department of Transport and Main Roads ‘Guide to Traffic Impact Assessment 2017’.
1.3 Site Location
The site is located at Lots 1, 2 and 3 and 28 Myall Street, Cooroy as shown in Figure 1.1 and Figure 1.2. The
property description is Lots 1, 2 & 3 on SP115864 and Lot 33 on MCH2281. The site has a single road
frontage to Myall Street along the south-western boundary, with the north-eastern boundary bordered by
Site: Lot 2 & 3 Myall Street, Cooroy 5
Reference: 19BRT0357
Page 7
the North Coast Train Line. Lot 33 on MCH2281 is currently occupied by the existing Cooroy Golf Club with
the fairway located on Lot 33 and Lot 1 on SP115864. Lots 2 and 3 are currently unoccupied.
Development Site
Figure 1.1: Site Location – Broader Context Source: Google Maps
Development Site
Figure 1.2: Site Area – Local Context Source: Queensland Globe
Site: Lot 2 & 3 Myall Street, Cooroy 6
Reference: 19BRT0357
Page 8
1.4 Development Profile
The proposed development scheme involves a relocatable home park consisting of 232 lots (with the lots
measuring 14m x 21m) and the construction of a new Cooroy golf clubhouse. It is relevant to note that there
is an existing Cooroy Golf Club located on the site, which will be removed as part of the development. The
development also consists of a relocatable sale showroom, managers workshop and clubhouse (with indoor
& outdoor pools, residents workshop and lawn bowls facilities).
A copy of the development plan is included in Appendix A. A summary of the proposed land uses is
summarised in Table 1.1.
Table 1.1: Proposed Land Uses
Land Use Overall
Relocatable Dwelling Lots 232 lots
Recreation, Amusement and Fitness (Golf Clubhouse) 640m² GFA
1.5 Development Access
Vehicular access between the existing public road network and the development is proposed via an access
driveway at the south-western boundary of the site to Myall Street. The characteristics of this access include:
• Type B1 driveway access
• 11m wide at the property boundary
• Priority controlled
• All turns permitted
In addition to the above, an emergency vehicle access is provided to the Myall Street, State Route 6 and
Nandroya Road roundabout. Access by way of this crossover will be prohibited outside of emergencies and
secured by a locked security gate or bollard. The design of this access will be refined through detailed design
in accordance with NSC design requirements.
Further details regarding the proposed site access arrangements is included in Section 3.
1.6 Parking
The development proposal includes the following parking supply:
• 464 resident spaces (minimum) on each lot;
• 33 visitor spaces located around the site;
• 3 car wash bays located throughout the site; &
• 97 spaces at the Cooroy Golf Club clubhouse.
Site: Lot 2 & 3 Myall Street, Cooroy 7
Reference: 19BRT0357
Page 9
1.7 Service Vehicles Service vehicles up to a Heavy Rigid Vehicle (HRV) are able to enter and exit the site in a forward gear via Myall Street and circulate within the site. Further details regarding the proposed service vehicle arrangements is included in Section 5. Site: Lot 2 & 3 Myall Street, Cooroy 8 Reference: 19BRT0357
Page 10
2 Existing Transport Infrastructure 2.1 The Road Network The roads in the immediate vicinity of the site are administered by DTMR, with the exception of Ferrells Road, which is administered by NSC. The hierarchy and characteristics of roads in the immediate vicinity of the site are shown below in Table 2.1. Table 2.1: Local Road Hierarchy Road Speed Limit Lanes Classification Myall Street / Nandroya Road 60kph 2 (undivided) Main Road Bruce Highway 110kph 4 (divided) Motorway State Route 6 60kph 2 (divided) Main Road Ferrells Road 60kph 2 (undivided) Local Road Myall Street has a 7m wide carriageway at the site frontage. The intersection of Myall Street, State Route 6 and Nandroya Road is roundabout controlled. The intersection of Myall Street and Ferrells Road is priority- controlled. 2.2 Road Planning Review of the NSC Local Government Infrastructure Plan (LGIP) mapping indicates that Council has no transport infrastructure upgrades planned in the local area that would impact the subject site or be impacted by the proposed development. TTM have also reviewed the State Planning Policy Interactive Mapping System for the future road network in the vicinity of the subject site It is understood that DTMR has no transport infrastructure upgrades planned in the local area that would impact the subject site or be impacted by the proposed development. 2.3 Public Transport and Pedestrian Facilities Train Cooroy train station is located approximately 1.5km to the north of the site. Services to Brisbane City and Gympie North operate twice per day in each direction. Buses Translink has a bus route (631) that utilise Ferrells Road, with the nearest on-street bus stop being located approximately 300m to the north west of the site, at Ferrells Road near Myall Street (stop ID Stop ID: 301954). This route operates between Nambour and Noosa Junction Station and operates up to 60 minutes in peak periods and up to 120 minutes in the non peak periods. Site: Lot 2 & 3 Myall Street, Cooroy 9 Reference: 19BRT0357
Page 11
Pedestrians and Cyclists
Bicycle awareness zones are located on the northern section of Myall Street and surround local Council
roads.
Formal pedestrian footpaths are located on one side of Myall Street (on the western side from Ferrells Road
to the north of Myall Street). Formal kerb ramps are provided at all road intersections to Myall Street.
Council’s active transport network within the vicinity of the subject site, as shown in the NRCRC Planning
Scheme, is illustrated in Figure 2.1.
Development Site
Figure 2.1: Council’s Active Transport Network Source: The Noosa Plan
Site: Lot 2 & 3 Myall Street, Cooroy 10
Reference: 19BRT0357
Page 12
3 Site Access Arrangements
3.1 Myall Street Access
The development scheme proposes an 11m wide crossover to Myall Street, which will facilitate access to
both the relocatable dwellings and the golf club clubhouse. The proposed access driveway requirements for
the Myall Street crossover are specified in Table 3.1.
Table 3.1: Driveway Requirements for Myall Street Access
Design Aspect Council Requirement Proposed Provision Compliance
Distance from a minor intersection 10m (min) 180m Council Compliant
Distance from a major intersection 20m (min) 250m Council Compliant
Distance from another driveway 3m (min) 230m Council Compliant
Sight Distance- 60kph Ideally 83m, or 65m as East bound – 186m Council Compliant
an absolute minimum West bound – 150m
Design Type Commercial (2 way) Commercial (2 way) Council Compliant
Width/ Entry and Exit Widths 7m (2-way; HRV + car) 11m Council Compliant
Minimum Queuing Provisions 3 cars 3 cars Council Compliant
A turn lane warrant analysis has been undertaken in accordance with DTMR’s Supplement to Austroads
Guide to Road Design Part 4A: Unsignalised and Signalised Intersection (Aug 2014) to determine if turn
treatment upgrades are required as a result of the proposed development. The assessment indicates that in
the 10-year design horizon (2034) scenario, the proposed development requires a channelised right turn
lane treatment (CHR(s)) and a channelised or auxiliary left turn lane treatment (AUL / CHL). Further details
regarding the proposed turn treatments is included in Section 5.
Overall, the proposed access driveway complies with Council requirements.
3.2 Emergency Vehicle Access
The development proposes the construction of an emergency vehicle access crossover, which will form a
fourth leg to the Myall Street, State Route 6 and Nandroya Road roundabout. Whilst emergency service
vehicles are able to utilise the main access crossover to Myall Street, the proposed access will provide an
alternate access to the southern portion of the development. Use of this access will be strictly reserved for
use by emergency and service vehicles (up to the size of a small rigid) with access restricted by a security
gate or bollard at all other times. It is understood that the on-site manager will be responsible for ‘unlocking’
the access during an emergency. The design of this access will be refined through the detailed design phase
in accordance with NSC design requirements.
Whilst the proposed driveway width of 4.5m does not strictly satisfy the AS2890.2 requirements for a two-
way circulation aisle, the driveway will only be utilised in emergencies, with all emergency vehicle
movements expected to operate in a tidal fashion; inbound in response to the emergency, outbound
following resolution of the emergency. Based on the fact that the driveway will be only occasionally used by
Site: Lot 2 & 3 Myall Street, Cooroy 11
Reference: 19BRT0357
Page 13
emergency service vehicles and is provided as a secondary access point, it is considered that the width and location of the driveway is adequate in this instance. Overall, the proposed emergency access is considered to adequately cater for the practical demands proposed. Site: Lot 2 & 3 Myall Street, Cooroy 12 Reference: 19BRT0357
Page 14
4 Car Parking Arrangements
4.1 Council Parking Supply Requirement
Table 14-51 of the ‘Driveway and Car Parking Code’ within ‘The Noosa Plan’ specifies that car parking rates
for specific land uses. NSC parking requirements for the proposed development are identified in Table 4.1.
Table 4.1: Parking Supply Requirement
Land Use Council Requirement Extent Requirement Provision Compliance
Relocatable Dwellings
• Resident Parking 1 space per dwelling 232 dwellings 232 spaces 464 spaces* Compliant
• Residential Surplus/ 1 space per 2 dwellings 116 spaces 33 spaces Performance Solution
Visitor Parking
• Car Wash Bays 1 space per 100 dwellings 3 spaces 3 spaces Compliant
Recreation, Amusement 1 space per 20m² 640m² 32 spaces 97 spaces Compliant
and Fitness
(Golf Clubhouse)
*The provision of 464 spaces is based on each dwelling containing a double car garage.
Per Table 4.1 above, NSC parking requirements specify that a minimum of 1 parking space is to be provided
per dwelling. The equivalent 232 parking spaces will be catered for within each dwelling via enclosed garages
and driveways (minimum of 1 single garage per lot). Whilst only 35 formalised parking spaces have been
provided for use by visitors and surplus residential parking, the proposed provision is considered to be
acceptable based on the following:
• TTM have been informed by the applicant that the majority, if not all, of the proposed relocatable
dwellings will be provided with double car garages. As such, the proposed development would have an
equivalent residential parking supply of 464 parking spaces. It is important to note that the 116-parking
space requirement is to accommodate visitor and residential surplus parking. Subsequently, it is
anticipated that there will be minimal residential surplus parking demand outside of that which can be
accommodated within individual garages.
• The proposed circulation road width of 6m is sufficient to allow a B99 vehicle (representative of 99
percent of vehicles) to pass a parked car. For comparison, Planning Scheme Policy 5 of the ‘The Noosa
Plan’ states that an access road with a carriageway width of 6m is of sufficient width to accommodate
kerb-side parking. As such, it is proposed that visitor parking demand generated above the capacity of
the formal spaces provided can be accommodated by kerb-side parking along each of the internal
circulation roads.
The above parking supply is also to include PWD parking in communal parking areas (not including reserved
residential). The Council requirement for PWD parking is a minimum of 1 space per 100 standard spaces. As
such, 2 PWD parking spaces are required, with one located within the relocatable dwellings portion of the
site and one located within the Cooroy golf clubhouse carparking area.
Site: Lot 2 & 3 Myall Street, Cooroy 13
Reference: 19BRT0357
Page 15
Overall, TTM considers the proposed parking provision to be suitable to cater for the requirements of the
development.
4.2 Car Park Layout
Table 4.2 identifies the characteristics of the proposed parking area with respect to the Council
requirements. The last column identifies the compliance of each design aspect. Where compliance with
Council is not achieved, further information is provided below
Table 4.2: Parking Design Requirements
Design Aspect AS2890.1:2004 Requirements Proposed Provision Compliance
Parking space length:
− Standard bay 5.4m 5.4m Compliant
Parking space width:
− Residential 2.4m 2.6m Compliant
− Visitor 2.6m 2.6m Compliant
Aisle Width:
− Parking aisle 5.8m 6.0m Compliant
− Circulation aisle 5.8m 6.0m
Parking envelope clearance - 0.25m into bay within 0.3m & 0.2m None Compliant
Column intrusion into bay within 1.2m of front of bay
Parking envelope clearance – Space 0.3m clear of wall Space 0.3m clear of wall Compliant
space adjacent to wall
Maximum Gradient:
− PWD parking 1:40 (2.5%) Generally Flat Compliant
− Parking bay 1:20 (5.0%) Generally Flat Compliant
− Parking aisle 1:16 (6.25%) Generally Flat Compliant
− Ramp 1:5 (20%) Generally Flat Compliant
Maximum Change in Grade 1:8 (12.5%) summit Generally Flat Compliant
1:6.67 (15.0%) sag
Parking Aisle Extension 1m beyond last bay 2m beyond last bay Compliant
The proposed carpark layout complies with all AS2890.1 requirements and is therefore considered suitable.
Site: Lot 2 & 3 Myall Street, Cooroy 14
Reference: 19BRT0357
Page 16
5 Service Vehicle Arrangements
5.1 Council Requirements
Specific Outcome O7 of the NSC’s ‘Driveway and Parking Code’ states that a development must provide
sufficient carparking to accommodate the number and type of vehicles likely to be generated by the
development with reference to minimum service vehicle requirements for specific land uses as outlined in
Table 14-51. As the code provides no commentary regarding the number of service bays required for the
proposed land uses, the service vehicle requirements have been estimated by TTM based on practical
operational requirements of the site.
• Occasional access for a Heavy Rigid Vehicle (HRV). Provision is to ensure that:
- The vehicle can stand wholly contained within the site (clear of the verge);
- Occasional reverse manoeuvres are limited to one only, either to or from the site;
- The swept path is accommodated within the width of the access driveway.
• Regular access is required for a Refuse Collection Vehicle (RCV). Provision is to ensure that:
- The vehicle can enter and leave the site safely in a forward direction;
- The vehicle can traverse the site on circulation roads and aisles to access service areas;
- The vehicle can manoeuvre on-site to allow parking and loading or unloading in a designated service
area or bay.
5.2 Proposed Service Vehicle Arrangements and Their Adequacy
Service vehicles up to and including a HRV are able to enter/exit the site in a forward motion via Myall Street.
Given all internal roads have been designed to accommodate a HRV, the RCV/furniture truck is able to travel
through the site utilising the internal road as required. Given that these larger service vehicle movements are
expected to occur outside of peak hours, the internal traffic flows will be very low, this is not expected to
have an impact on the internal operation of the site.
It is relevant to note that servicing vehicle operations along the parking aisle separating Lots 71-74 and Lots
75-76 will be one-way, with larger vehicles restricted from attempting to exit the site via this aisle as
illustrated in Figure 5.1. TTM Drawing 19BRT0357-03 Rev A, included within Appendix B, illustrates HRV
access and egress manoeuvres at the internal roundabout.
The decision to limit vehicle movements as described above is due to the fact that the security gate located
at the access to the relocatable dwelling portion of the site would not be long enough to secure the site if
the island was truncated to accommodate the above-mentioned manoeuvre. It is relevant to note that a B99
vehicle (representative of 99 percent of vehicles) is able to exit the site from this aisle.
Site: Lot 2 & 3 Myall Street, Cooroy 15
Reference: 19BRT0357
Page 17
To accommodate the above service vehicle limitations, a bin pad has been proposed on the southern side of
the aisle to service Lots 71-74. The proposed bin pads are dimensioned to allow room for two bins from each
serviced lot. The pads allow for 0.9 x 0.9m of space per bin. As such, the bin pad servicing the four lots is
designed as 7.2 x 0.9m
Security Gate Inbound HRV/RCV
movements permitted
Bin Pad
Figure 5.1: Internal Service Vehicle Circulation
Regarding the servicing arrangements of the Cooroy golf clubhouse, a loading bay suitable for vehicles up to
the size of a HRV has been provided adjacent to the building.
Swept path analysis for the HRV design vehicle have been performed to demonstrate safe manoeuvring of
the vehicles, as shown in Appendix B.
Site: Lot 2 & 3 Myall Street, Cooroy 16
Reference: 19BRT0357
Page 18
6 Traffic Impact Assessment
6.1 Scope
In accordance with standard impact assessment guidelines traffic demands have been estimated for an
anticipated development opening year of 2024 and a 10-year design horizon of 2034.
Two key intersections have been assessed for morning and afternoon peak hour periods, including:
• Myall Street / State Route 6 / Nandroya Road Roundabout Intersection
• Myall Street / Site Access Assessment
These intersections have been assessed based on the surveyed existing (2019) traffic demands, and
estimated traffic demands at the assumed opening year of development (2024) and 10-year design horizon
(2034).
6.2 Existing Traffic Volumes
6.2.1 Peak Hour
TTM Data conducted an intersection movement survey at the Myall Street / State Route 6 / Nandroya Road
Roundabout Intersection, from 7:00am to 6:30pm on Thursday 22nd August 2019. The peak hours were
found to be 7:45 to 8:45am and 4:00 to 5:00pm. The results of the survey are shown below in Figure 6.1.
2019 Surveyed Data
AM Peak Site Access
PM Peak
0 0
0 0
0 0
Myall Street Nandroya Road
0 0 0 0 82 65
407 509 407 509 407 509 407 509 325 444 96 85
450 412 0 0 450 412 450 412 84 62 106 83
450 412 366 20 22 21
350 14
386 346
364 466
State Route 6
Figure 6.1: Surveyed Peak Hour Traffic Volumes
It is important to note that the existing Cooroy golf clubhouse, located on the northern portion of Lot 33 on
MCH2281, is accessed via a crossover to Myall Street. All parking for the golf course is accessed via this
crossover. As such, all vehicles travelling northward to the existing clubhouse along Myall Street were
Site: Lot 2 & 3 Myall Street, Cooroy 17
Reference: 19BRT0357
Page 19
accounted for in the above survey. Following the relocation of the clubhouse, these vehicles will be diverted into the subject site; as opposed to being ‘New Trips’. 6.3 Future Base Traffic Volumes To estimate future traffic demands in the absence of the proposed development, a conservative annual average compound traffic growth rate of 2.0% has been applied to the 2019 surveyed traffic volumes to obtain both opening year (2024) and 10-year design horizon (2034) demands. This growth rate is based on Council’s current population estimates of the expected growth within the Cooroy catchment, as well as historical traffic growth on Myall Street over the last 10-years (as indicated from DTMR’s AADT data for traffic count site 20049). TTM has identified three assessment periods for the road network as follows: Current Traffic Scenario This scenario includes the 2019 traffic volumes modelled over the existing road network. This analysis has been performed for both the AM and PM peaks. Opening Year (2024) Traffic Scenario This analysis incorporates a 2.0% per annum increase in the background traffic volume for a period of 5 years from the most recent survey. This analysis has been performed for both the AM and PM peaks at the Myall Street/ Site Access intersection and the Myall Street/State Route 6/Nandroya Road Roundabout Intersection. 2034 Traffic Scenario This analysis incorporates a 2.0% per annum increase in the background traffic volume for a period of (10 years past opening year). This analysis has been performed for both the AM and PM peaks at the Myall Street/ Site Access intersection. 6.4 Development Traffic 6.4.1 Estimated Development Traffic Generation 6.4.1.1 Relocatable Dwellings – New Trips In order to more accurately predict the levels of traffic generation associated with the relocatable dwelling aspects of the proposed development, TTM have integrated the results of previously undertaken traffic surveys at the access/egress points of an existing relocatable dwelling development. The existing development was of comparable scale and similarly situated in proximity to the nearby township. The surveys were undertaken on the 18th July 2019 and reflected an AM peak hour generation rate of 0.189vph/dwelling and PM peak hour generation rate of 0.124vph/dwelling. The surveys indicated that 50% of vehicles were inbound in the AM peak hour period, with the remaining 50% outbound. 60% of vehicles were surveyed to be travelling inbound in the PM peak hour period with the remaining 40% travelling outbound. Site: Lot 2 & 3 Myall Street, Cooroy 18 Reference: 19BRT0357
Page 20
6.4.1.2 Cooroy golf clubhouse – Diverted Trips Traffic generation for the proposed clubhouse has been conservatively estimated using information collated from traffic counts previously undertaken by TTM at similarly sized golf courses with accompanying clubhouses. This information has been used to supply a relative trip rate per hole, which in turn has been used to estimate the level of traffic generation for the proposed development during the weekday AM/PM peak-hour periods. The peak traffic generation for the surveyed 18-hole golf course (and relative trip rate per hole) obtained from the traffic counts are as follows: • AM peak-hour - 130vph (7.2vph/hole); & • PM peak-hour - 94vph (5.2vph/hole). Based on the application of these trip rates, it is estimated that the proposed clubhouse and golf course will generate the following additional trips: • AM peak-hour - 130vph; & • PM peak-hour - 94vph. The undertaken survey indicated that 52% of vehicles were inbound in the AM peak hour period, with the remaining 48% outbound. 25% of vehicles were surveyed to be travelling inbound in the PM peak hour period with the remaining 75% travelling outbound. 6.4.1.3 Summary Based on application of the peak hour and daily traffic generation rates outlined above, the overall traffic generation of the development will be as shown in Table 6.1. Table 6.1: Development Traffic Generation – Summary Land Use Extent Generation Rate AM Peak Hour PM Peak Hour Relocatable 232 dwellings 0.189vph/dwelling in the AM peak hour 44vph (23 in + 21 out) 29vph (16 in + 11 out) Dwelling Lots 0.124vph/dwelling in the PM peak hour Golf 18 holes 7.2vph/hole in the AM peak hour 130vph (68 in + 62 out) 94vph (23 in + 70 out) Clubhouse 5.2vph/hole in the PM peak hour Total 174vph (91 in + 83 out) 120vph (39 in + 81 out) 6.4.2 Estimated Development Traffic Distribution Directional distribution of development traffic is assumed to be consistent with existing traffic distribution as exhibited in the traffic survey data. It has been assumed that 80% of the peak hour traffic will be inbound towards the Cooroy township, with the remaining 20% outbound during both the AM and PM peak hours. Figure 6.2 details the expected trip distribution for the relocatable dwellings whilst Figure 6.3 details the expected distribution of the proposed clubhouse. Site: Lot 2 & 3 Myall Street, Cooroy 19 Reference: 19BRT0357
Page 21
Developement Volumes - Relocatable Dwellings
AM Peak Site Access
PM Peak
100% 100%
100% 100%
80% 20%
Myall Street Nandroya Road
80% 80% 80% 20% 0% 0%
80% 80% 0% 0% 20% 20% 20% 20% 20% 20% 0% 0%
80% 80% 20% 20% 20% 20% 20% 20% 0% 0% 0% 0%
0% 0% 20% 0% 0% 0%
20% 0%
20% 20%
20% 20%
State Route 6
Figure 6.2: Relocatable Dwellings Development Traffic Distribution
Developement Volumes - Golf Course Clubhouse
AM Peak Site Access
PM Peak
100% 100%
100% 100%
80% 20%
Myall Street Nandroya Road
80% 80% 80% 20% 0% 0%
60% 60% -20% -20% 0% 0% 20% 20% 20% 20% 0% 0%
60% 60% 20% 20% 0% 0% 20% 20% 0% 0% 0% 0%
-20% -20% 20% 0% 0% 0%
20% 0%
20% 20%
20% 20%
State Route 6
Figure 6.3: Cooroy Golf Clubhouse Development Traffic Distribution
Application of the above-mentioned traffic generation and distribution assumptions results in the
development traffic volumes shown in Figure 6.4.
Site: Lot 2 & 3 Myall Street, Cooroy 20
Reference: 19BRT0357
Page 22
Developement Volumes
AM Peak Site Access
PM Peak
90 81
39 84
65 16
Myall Street Nandroya Road
33 72 67 17 0 0
19 58 -14 -14 2 3 16 17 16 17 0 0
53 61 18 6 5 2 18 6 0 0 0 0
-13 -5 18 0 0 0
6 0
18 16
6 17
State Route 6
Figure 6.4: Total Development Traffic Generation
6.5 Future Project Traffic Volumes
6.5.1 Opening Year (2024) Base Traffic Scenario
Figure 6.5 shows the opening year (2024) base traffic demands, based on an application of an annual growth
rate of 2.0% for a period of 5 years (5 years past the date of the traffic surveys) to the 2019 traffic survey
volumes.
2024 Base Traffic Volumes
AM Peak Site Access
PM Peak
0 0
0 0
0 0
Myall Street Nandroya Road
0 0 0 0 91 72
449 562 449 562 449 562 449 562 359 490 106 94
497 455 0 0 497 455 497 455 93 68 117 92
497 455 404 22 24 23
386 15
426 382
402 515
State Route 6
Figure 6.5: Estimated 2024 Peak Hour Traffic, Without Development (2.0%pa growth)
Site: Lot 2 & 3 Myall Street, Cooroy 21
Reference: 19BRT0357
Page 23
6.5.2 Opening Year (2024) Project Traffic Scenario
The opening year project case scenario is obtained by the addition of development traffic generation shown
in Figure 6.4 to the base traffic volumes shown in Figure 6.5. These expected traffic movements are shown in
Figure 6.6.
2024 Project Volumes
AM Peak Site Access
PM Peak
90 81
39 84
65 16
Myall Street Nandroya Road
33 72 67 17 91 72
468 620 435 548 452 565 466 579 375 507 106 94
550 515 18 6 501 456 515 461 93 68 117 92
483 450 422 22 24 23
393 15
444 398
408 531
State Route 6
Figure 6.6: Estimated 2024 Peak Hour Traffic, With Development
6.5.3 Future Year (2034) Base Traffic Scenario
Figure 6.7 shows the future (2034) base traffic demands, based on an application of an annual growth rate of
2.0% for a period of 15 years (i.e. 10 years past an assumed 2024 completion date of the project) to the 2034
traffic volumes.
2034 Base Traffic Volumes
AM Peak Site Access
PM Peak
0 0
0 0
0 0
Myall Street Nandroya Road
0 0 0 0 110 87
548 685 548 685 548 685 548 685 437 598 129 114
606 554 0 0 606 554 606 554 113 83 143 112
606 554 493 27 30 28
471 19
520 466
490 627
State Route 6
Figure 6.7: Estimated 2034 Peak Hour Traffic, Without Development (2.0%pa growth)
Site: Lot 2 & 3 Myall Street, Cooroy 22
Reference: 19BRT0357
Page 24
6.5.4 Future Year (2034) Project Traffic Scenario
The opening year project case scenario is obtained by the addition of development traffic generation shown
in Figure 6.4 to the base traffic volumes shown in Figure 6.7. These expected traffic movements are shown in
Figure 6.8.
2034 Project Volumes
AM Peak Site Access
PM Peak
90 81
39 84
65 16
Myall Street Nandroya Road
33 72 67 17 110 87
566 743 534 671 550 688 564 702 454 614 129 114
659 615 18 6 610 556 624 561 113 83 143 112
592 550 511 27 30 28
477 19
537 482
496 644
State Route 6
Figure 6.8: Estimated 2034 Peak Hour Ultimate Traffic, With Development
Site: Lot 2 & 3 Myall Street, Cooroy 23
Reference: 19BRT0357
Page 25
7 Road Network Performance
7.1 Myall Street / Site Access Assessment
7.1.1 Turn Lane Warrant Analysis
A turn lane warrant analysis has been undertaken in accordance with DTMR’s Supplement to Austroads
Guide to Road Design Part 4A: Unsignalised and Signalised Intersection (Aug 2014) to determine if turn
treatment upgrades are required as a result of the proposed development.
Table 7.1 details the parameters and turn lane treatment types required at the proposed development site
access based on the estimated 2034 peak hour traffic volumes.
Table 7.1: Turn Lane Warrant Assessment – Myall Street / Site Access Intersection
Approach Scenario AM Peak Hour PM Peak Hour
Q R/L QM Treatment Q R/L QM Treatment
Right Turn-in 2034 Project 18 1335 CHR(s) 6 1116 CHR(s)
Left Turn-in 2034 Project 72 671 AUL / CHL 33 534 AUL (s)
The assessment indicates that the proposed development site access requires a channelised right turn lane
treatment (CHR(s)) and a channelised or auxiliary left turn lane treatment (AUL / CHL). A preliminary review
indicates that the required treatments can be accommodated within the existing road reserve.
7.1.2 SIDRA Analysis
The required access intersection configuration has been analysed for the 2024 and 2034 traffic volume
scenario. Figure 7.1 shows the modelled intersection configuration with the proposed turn treatments.
Figure 7.1: Proposed Myall Street / Site Access Intersection Layout
Site: Lot 2 & 3 Myall Street, Cooroy 24
Reference: 19BRT0357
Page 26
Table 7.2 summarises the analysis outputs. Detailed analysis output summaries are included in Appendix C.
Table 7.2: Summary of Sidra Outputs (Myall Street / Site Access Intersection)
Case Degree of Worst Average Worst Level 95th Percentile Critical Queue (m)
Saturation (%) Delay (sec) of Service
East South West
AM Project Case 2024 33.8 23.3 C 0.7 8.6 0
AM Project Case 2034 50.4 40.3 E 0.8 12.5 0
PM Project Case 2024 24.4 16.6 C 0.2 5.9 0
PM Project Case 2034 33.8 24.1 C 0.2 8.6 0
The analysis confirms that the driveway access intersection would have spare capacity at the opening-year
and 10-year design horizon of the proposed development (2024 and 2034) with the highest degree of
saturation being 50.4% (85% is the generally acceptable threshold) during the 2034 PM peak hour period
with a maximum average delay of 41 seconds.
As outlined in DTMR’s Guide to Traffic Impact Assessment, the average delay metric is the key performance
measure for priority-controlled intersections. It states that “where average peak hour delays for any turn
movement exceeds 42 seconds (the Level of Service C/D threshold) then the intersection should be
upgraded for safety reasons where it is practical to do so.”
The analysis demonstrates that the critical period in terms of average delay is the AM case. As indicated in
Table 7.2 above, the maximum delay for the 10-year design horizon scenario is calculated to be 40.3
seconds, which is within the nominated threshold of 42 seconds. This indicates that no mitigating
intersection upgrades are required to accommodate the development beyond the turn treatments
proposed.
7.1.3 Conclusion
Based on the above analysis, it is concluded that the proposed access configuration is adequate to
accommodate the traffic demands associated with the proposed development at the opening year and 10-
year design horizon. It is anticipated that the future works to include turn lane treatments will cater for the
base traffic demands and the proposed additional traffic associated with the development.
7.2 Myall Street/ State Route 6/ Nandroya Road Roundabout Assessment
7.2.1 SIDRA Analysis
The existing intersection configuration has been analysed for the 2024 traffic volume scenario. Figure 7.2
shows the modelled intersection configuration.
Site: Lot 2 & 3 Myall Street, Cooroy 25
Reference: 19BRT0357
Page 27
Figure 7.2: Existing Myall Street / State Route 6 / Nandroya Road Intersection Layout
Table 7.3 summarises the analysis outputs. Detailed analysis output summaries are included in Appendix C.
Table 7.3: Summary of Sidra Outputs (Myall Street / State Route 6 / Nandroya Road Intersection)
Case Degree of Worst Average Worst Level 95th Percentile Critical Queue (m)
Saturation (%) Delay (sec) of Service
East South West
AM Survey Case 2019 26.5 9.9 A 9.4 3.4 9.5
AM Base Case 2024 29.3 9.9 A 10.8 4.0 10.9
AM Project Case 2024 30.3 9.9 A 11.4 4.1 11.3
PM Survey Case 2019 19.7 9.8 A 8.5 2.3 6.3
PM Base Case 2024 21.8 9.8 A 9.7 2.6 7.1
PM Project Case 2024 22.2 9.8 A 10.0 2.7 7.5
The analysis confirms that the existing intersection would have spare capacity at the opening-year of the
proposed development (2024) with the highest degree of saturation being 30.3% (85% is the generally
acceptable threshold) during the 2024 AM peak hour period with a maximum average delay of 10 seconds.
As outlined in DTMR’s Guide to Traffic Impact Assessment, the average delay metric is the key performance
measure for priority-controlled intersections. It states that “where average peak hour delays for any
turnmovement exceeds 42 seconds (the Level of Service C/D threshold) then the intersection should be
upgraded for safety reasons where it is practical to do so.”
As indicated in Table 7.3 above, the maximum for the opening ‘without development’ scenario is calculated
to be 10 seconds, while the additional traffic demands associated with the proposed development would
result in a maximum average delay of 10 seconds. Both of these values are within the nominated threshold
of 42 seconds. This indicates that no mitigating intersection upgrades are required to accommodate the
development.
Site: Lot 2 & 3 Myall Street, Cooroy 26
Reference: 19BRT0357
Page 28
7.2.2 Conclusion Based on the above analysis, it is concluded that the existing intersection configuration is adequate to accommodate the traffic demands associated with the proposed development at the opening year. It is anticipated that no future works are required as a consequence of the additional traffic associated with the proposed development. Site: Lot 2 & 3 Myall Street, Cooroy 27 Reference: 19BRT0357
Page 29
8 Active Transport 8.1 Public Transport Access to public transport from the site is considered suitable, due to the presence of a bus stop on Ferrells Road located approximately 300m to the north west of the site, and its connectivity to and from Nambour and Noosa Junction Station. 8.2 Pedestrian and Cyclist Provisions The proposed road layout design is based on a shared road environment between vehicles and pedestrians. This is achieved by maintaining low traffic volumes and low traffic speeds throughout. It should be noted that the layout also proposes internal footpath connections from the site access to the sale showroom and community club house facilities. Given that the existing Cooroy Golf Club does not provide external pedestrian footpaths to the road network, pedestrian access to the site is not considered critical. However, the development does provide pedestrian access from the site access and an internal footpath network for the Golf Club. No formal cycling facilities have been proposed as part of this development application, however, the internal roadways are provided with adequate width to accommodate shared on road cyclist needs for a low speed, low volume environment. Site: Lot 2 & 3 Myall Street, Cooroy 28 Reference: 19BRT0357
Page 30
9 Summary and Conclusions 9.1 Development Summary The proposed development scheme involves a relocatable home park consisting of 232 lots (with the lots measuring 14m x 21m) and the construction of a new Cooroy Golf Club clubhouse. The development also consists of a relocatable sale showroom, managers workshop and clubhouse (with indoor & outdoor pools, residents workshop and lawn bowls facilities). 9.2 Car Parking Arrangements It is proposed that all residential parking required for the relocatable dwellings be accommodated within the enclosed garages provided within each lot. It is noted that a performance solution has been proposed for the visitor and residential surplus parking, detailed within Section 4.1. The proposed parking supply for the golf club clubhouse satisfies NSC accepted parking requirements. Overall, the proposed car parking arrangements for this development are adequate. The proposed design layout satisfies NSC’s design standards and is suitable for the development. 9.3 Site Access Arrangements The development scheme proposes an 11m wide crossover to Myall Street, which will facilitate access to both the relocatable dwellings and the Cooroy golf clubhouse. Additionally, the development proposes the construction of an emergency vehicle access crossover to Nandroya Road. The design of these crossovers is generally in accordance with NSC requirements with both crosssovers ideally positioned in terms of intersection/driveway separation and sight distance requirements. As detailed in Section 7, a turn lane warrant analysis has been undertaken which indicates that in the 10-year design horizon (2034) scenario, the proposed development site access requires a channelised right turn lane treatment (CHR(s)) and a channelised or auxiliary left turn lane treatment (AUL / CHL). Overall, TTM consider the access arrangements to adequately cater for the practical demands of the proposed development. 9.4 Service Vehicle Arrangements Servicing for this development will be facilitated within the circulation aisles, accessed off Myall Street. The largest design vehicle, a 12.5m HRV, can manouevre within the site ultimately entering and exiting in a forward gear. Regarding the servicing arrangements of the Cooroy golf clubhouse, a loading bay suitable for vehicles up to the size of a HRV has been provided adjacent to the building. Site: Lot 2 & 3 Myall Street, Cooroy 29 Reference: 19BRT0357
Page 31
Overall, the proposed service vehicle arrangements are considered adequate to meet the needs of the proposed development. 9.5 Active Transport Facilities The current public transport infrastructure and proposed site provisions for pedestrian/bicycle facilities is considered adequate for the development. 9.6 Impact on Surrounding Road Network Assessment of the proposed development indicates that the development will not have a significant impact on the future road network. As such, no mitigating road works are required beyond the warranted turn treatments 9.7 Conclusion Based on the assessment contained within this report, TTM see no traffic engineering reason why the relevant approvals should not be granted. Site: Lot 2 & 3 Myall Street, Cooroy 30 Reference: 19BRT0357
Page 32
Appendix A Proposed Site Plan Site: Lot 2 & 3 Myall Street, Cooroy Reference: 19BRT0357 [OCR of page images] itm Appendix A Proposed Site Plan Site: Lot 2 & 3 Myall Street, Cooroy Reference: 19BRTO357
Page 33
LEGEND YIELD
FOR APPROVAL STANDARD LOTS - 14m x 21m
TOTAL NUMBER OF LOTS 232
NOT FOR CONSTRUCTION
REAR ACCESSED LOTS (REFER ATTACHED PLAN)
OPTIONS GAIN/LOSS
RELOCATABLE SALES SHOWROOM 0
COMMUNITY LANDSCAPING RV COMPOUND 0
BOCCE COURT 0
G O L F C O U R S E DASHED LINE OF CUT EXISTING VEGETATION
18TH
12TH GREEN RESIDENTS WORKSHOP 100m2 FILL
CUT RETAINING WALL ZONE, REFER CIVILS
TEE
25m OUTDOOR POOL
PUTTING
GREEN
PROPOSED
CLUB HOUSE
GOLF CLUB
BOUNDARY LINE (LAWN BOWL ON 17 LOTS
20 LOTS 12 13 14 15 16 17 18 19 20 FIRST LEVEL)
21 22 23 24
25
111.0
09 10 11 PAD RL 118.0
06 07 08
05 190 191 26
04
192
03
114 124 134 144 27
02 96 105
01 77 81 88 193
1ST
TEE 97 106
115 125 135 145 199
10 LOTS 28
29
75
82 89 154 163 172 181
78
76
6 LOTS 98 107
116 126 136 146
30
83 90 155 164 173 182 194
79 198 197 196 195 206 31
117 127 137 147 205
99 108
MANAGERS UNIT 84 91 156 165 174 183 200 201 202 203 204 32
80
74
18 LOTS 109 20 LOTS 128 20 LOTS 148
11
15 LOTS 92 118 138
18 LOTS 166 18 LOTS 184
3.0
100
15 LOTS
11
157 175 33
4.0
73 85 207
11
5.0
11
121.0
119 129 139 149
6.0
11
12
101 110
7.
72 208 34
11
0.
0
0
8.
158 167 176 185 223
0
86 93
11
9.0
12
0. 209
71 120 130 140 150
0
214 213 212 211 210 222 35
102 111 11
87 94 159 9.0 168 177 186 221
70 220
PROPOSED 121 131 141 11
6.0 151
11
8.0
215 216 217 218 219 36
103 112
10
BRIDGE 69
11
160 169 178 187
6.
5.0
95
0
224
10
10
8.
0 122
11
1. 132 142
11
4.0 152
11
7.0
18 LOTS 225
37
7.
0 68 104 113
0
11
3.0
161 170 179 188
67 38
66
11
2.0 226
1ST 65 123 11 133 143 153 39
64
0.0
227
63 162 171 180 189 232 231 230 229 228
GREEN 40
RV 62
61 41**
COMPOUND 60 42**
59 58 57 56 55 54 53 52 51 50 49 48 47 46 45 44 43**
109
1800m2
.0
DRIVEWAY
SALES
37 LOTS
EASEMENT
MANAGERS WORKSHOP
SHOWROOM EXISTING VEGETATION
EMERGENCY
SITE ACCESS
BIN PICKUP PAD MY A L L S T R E E T
BOCCE COURT
MASTER PLAN 1:1500 @
1500 A3
@ A3
• THIS DRAWING HAS BEEN PRODUCED BASED
ISSUE DATE DESCRIPTION ON INFORMATION SUPPLIED BY OTHERS. WHILE PROJECT JAREDPOOLEDESIGN DRAWN CB DRAWING - MASTER PLAN
FA
G
01.08.19
27.02.19
21.03.19
YIELD
ISSUEDINCREASED
FOR APPROVAL
YIELD INCREASED
ALL ATTEMPTS HAVE BEEN MADE TO ENSURE THE
ACCURACY OF THE DRAWING JARED POOLE. PROPOSED NEW DEVELOPMENT DATE JAN. 2019 DRAWING No. ISSUE
BP1074/SK2.01 NA
DESIGN WILL NOT BE HELD RESPONSIBLE FOR
THE ACCURACY OF THE INFORMATION PROVIDED. AT NORTH LEVEL 1 33 ELKHORN AVENUE SCALE 1:1500 @ A3
H 22.03.19 RV COMPOUND AND WORKSHOP ADDED
• THE WORKS DESCRIBED ON THIS AND SURFERS PARADISE, Q. 4217 AUSTRALIA
I
J
25.03.19
29.03.19
YIELD INCREASED
GOLF CLUB ADDED
ACCOMPANYING DRAWINGS ASSOCIATED WITH
THIS PROJECT PRODUCED BY JARED POOLE.
LOT 2 & 3 MYALL STREET, COOROY, QLD PO BOX 42
K 11.04.19 LAYOUT AMENDED
DESIGN ARE COVERED BY COPYRIGHT. THE WORKS FOR ISLE OF CAPRI, Q. 4217 AUSTRALIA
DESCRIBED ARE APPLICABLE TO THE PROJECT TEL 07 5527 5300
M
L 10.05.19
04.06.19
LAYOUT UPDATED, LEVELS ADDED
LAYOUT UPDATED, CIVIL INFO ADDED
SITE ONLY AND MUST NOT BE USED FOR ANY
OTHER PURPOSE. WORKS CANNOT BE COPIED OR
GEMLIFE EMAIL [email protected]
N 06.09.19 INTERNAL DRIVEWAY NETWORK UPDATED.
REPRODUCED BY ANY MEANS WITHOUT WRITTEN WEB WWW.JPD.COM.AU
PERMISSION OF JARED POOLE. DESIGN.
Page 34
Appendix B Service Vehicle Swept Paths Site: Lot 2 & 3 Myall Street, Cooroy Reference: 19BRT0357
Page 35
e
d Vehicl
eavy Rigi
HRV - H
HRV - Heavy Rigid Vehicle
HRV - Heavy Rigid Vehicle
l:\synergy\projects\19brt\19brt0357 lot 2 & 3 myall street, cooroy\3 - plans\ttm\19 09 06 dg01\19brt0357 dg01-03_a.dwg
HRV ACCESS MANOEUVRE #1 HRV ACCESS MANOEUVRE #2 HRV EGRESS MANOEUVRE
12.5
HRV - Heavy Rigid Vehicle
Overall Length 12.500m
Overall Width 2.500m
Overall Body Height 4.300m
NOTES:
Min Body Ground Clearance
Track Width
0.417m
2.500m 1. SUBJECT TO DETAILED DESIGN PRELIMINARY
2. SITE EXTENTS BASED OFF NEAR MAP IMAGERY
Lock-to-lock time
Curb to Curb Turning Radius
6.00s
12.500m 3. SUBJECT TO DETAILED SURVEY ADVICE ONLY 19BRT0357-03
Clearance Envelope 0.500m 4. KERB TO BE MOUNTABLE 6 September 2019
2.4 5.9 1.4 Design Speed Forward 5.0km/h
LOCALITY PLAN
N.T.S.
SCALE PROJECT PROJECT NUMBER ORIGINAL SIZE
0 5 10 15 20 25m
T TM CONSULTING PTY LTD RELOCATABLE HOME PARK AND GOLF CLUB CLUBHOUSE 19BRT0357 A3
ABN 65 010 868 621 DRAWING TITLE DRAWING NUMBER REVISION
SCALE 1:500 AT ORIGINAL SIZE
LEVEL 8, 369 Ann Street, BRISBANE, QLD, 4000
PROJECT NORTH CLIENT P.O. BOX 12015, BRISBANE, QLD, 4003 HRV CIRCULATION ANALYSIS 19BRT0357-03 A
T: (07) 3327 9500 F: (07) 3327 9501 12.5m HRV DESIGN VEHICLE DATE SHEET
A 06-09-19 ORIGINAL ISSUE NG NG DG RUBY DEVELOPMENTS PTY LTD E: [email protected] W: www.ttmgroup.com.au 6 Sep 2019 1 OF 1
REV. DATE AMENDMENT DESCRIPTION DRAWN CHECKED APPROVED
Page 36
19BRT0357-04
le
Vehic LOCALITY PLAN
eavy Rigid
HRV - H N.T.S.
PRELIMINARY
ADVICE ONLY
6 September 2019
NOTES:
1. SUBJECT TO DETAILED DESIGN
2. SITE EXTENTS BASED OFF NEAR MAP IMAGERY
3. SUBJECT TO DETAILED SURVEY
4. KERB TO BE MOUNTABLE
l:\synergy\projects\19brt\19brt0357 lot 2 & 3 myall street, cooroy\3 - plans\ttm\19 09 06 dg01\19brt0357 dg01-03_a.dwg
12.5
HRV - Heavy Rigid Vehicle
2.4 5.9 1.4
HRV - Heavy Rigid Vehicle
Overall Length 12.500m
Overall Width 2.500m
Overall Body Height 4.300m
HRV ACCESS MANOEUVRE HRV EGRESS MANOEUVRE Min Body Ground Clearance 0.417m
Track Width 2.500m
Lock-to-lock time 6.00s
Curb to Curb Turning Radius 12.500m
Clearance Envelope 0.500m
Design Speed Forward 5.0km/h
SCALE PROJECT PROJECT NUMBER ORIGINAL SIZE
0 5 10 15 20 25m
T TM CONSULTING PTY LTD RELOCATABLE HOME PARK AND GOLF CLUB CLUBHOUSE 19BRT0357 A3
ABN 65 010 868 621 DRAWING TITLE DRAWING NUMBER REVISION
SCALE 1:500 AT ORIGINAL SIZE
LEVEL 8, 369 Ann Street, BRISBANE, QLD, 4000
PROJECT NORTH CLIENT P.O. BOX 12015, BRISBANE, QLD, 4003 HRV CIRCULATION ANALYSIS 19BRT0357-04 A
T: (07) 3327 9500 F: (07) 3327 9501 12.5m HRV DESIGN VEHICLE DATE SHEET
RUBY DEVELOPMENTS PTY LTD
A 06-09-19 ORIGINAL ISSUE NG NG DG E: [email protected] W: www.ttmgroup.com.au 6 Sep 2019 1 OF 1
REV. DATE AMENDMENT DESCRIPTION DRAWN CHECKED APPROVED
Page 37
Appendix C Sidra Intersection Analysis Site: Lot 2 & 3 Myall Street, Cooroy Reference: 19BRT0357
Page 38
SITE LAYOUT
Site: [2024 AM Project - Site Access]
Myall Street / Site Access
Site Category: (None)
Giveway / Yield (Two-Way)
SIDRA INTERSECTION 8.0 | Copyright © 2000-2018 Akcelik and Associates Pty Ltd | sidrasolutions.com
Organisation: TTM CONSULTING PTY LTD | Created: Thursday, 5 September 2019 2:46:29 PM
Project: \\TTMFPS01\Synergy\BR\Synergy\Projects\19BRT\19BRT0357 Lot 2 & 3 Myall Street, Cooroy\6 - Analysis\19BRT0357 SA_01_Site access
(turn treatments).sip8
Page 39
MOVEMENT SUMMARY
Site: [2024 AM Project - Site Access]
Myall Street / Site Access
Site Category: (None)
Giveway / Yield (Two-Way)
Movement Performance - Vehicles
Mov Turn Demand Flows Deg. Average Level of 95% Back of Queue Prop. Effective Aver. No. Average
ID Total HV Satn Delay Service Vehicles Distance Queued Stop Rate Cycles Speed
veh/h % v/c sec veh m km/h
East: Myall Street
5 T1 508 0.0 0.262 0.0 LOS A 0.0 0.0 0.00 0.00 0.00 59.9
6 R2 19 0.0 0.028 9.0 LOS A 0.1 0.7 0.55 0.73 0.55 47.0
Approach 527 0.0 0.262 0.3 NA 0.1 0.7 0.02 0.03 0.02 59.4
North: Site Access
7 L2 18 0.0 0.338 11.0 LOS B 1.2 8.6 0.82 0.97 1.00 38.9
9 R2 71 0.0 0.338 23.3 LOS C 1.2 8.6 0.82 0.97 1.00 43.6
Approach 88 0.0 0.338 20.8 LOS C 1.2 8.6 0.82 0.97 1.00 42.8
West: Myall Street
10 L2 76 0.0 0.041 5.5 LOS A 0.0 0.0 0.00 0.58 0.00 53.6
11 T1 577 0.0 0.296 0.0 LOS A 0.0 0.0 0.00 0.00 0.00 59.9
Approach 653 0.0 0.296 0.7 NA 0.0 0.0 0.00 0.07 0.00 58.8
All Vehicles 1268 0.0 0.338 1.9 NA 1.2 8.6 0.07 0.11 0.08 57.1
Site Level of Service (LOS) Method: Delay (SIDRA). Site LOS Method is specified in the Parameter Settings dialog (Site tab).
Vehicle movement LOS values are based on average delay per movement.
Minor Road Approach LOS values are based on average delay for all vehicle movements.
NA: Intersection LOS and Major Road Approach LOS values are Not Applicable for two-way sign control since the average delay
is not a good LOS measure due to zero delays associated with major road movements.
SIDRA Standard Delay Model is used. Control Delay includes Geometric Delay.
Gap-Acceptance Capacity: SIDRA Standard (Akçelik M3D).
HV (%) values are calculated for All Movement Classes of All Heavy Vehicle Model Designation.
SIDRA INTERSECTION 8.0 | Copyright © 2000-2018 Akcelik and Associates Pty Ltd | sidrasolutions.com
Organisation: TTM CONSULTING PTY LTD | Processed: Thursday, 5 September 2019 2:11:25 PM
Project: \\TTMFPS01\Synergy\BR\Synergy\Projects\19BRT\19BRT0357 Lot 2 & 3 Myall Street, Cooroy\6 - Analysis\19BRT0357 SA_01_Site
access (turn treatments).sip8
Page 40
MOVEMENT SUMMARY
Site: [2034 AM Project - Site Access]
Myall Street / Site Access
Site Category: (None)
Giveway / Yield (Two-Way)
Movement Performance - Vehicles
Mov Turn Demand Flows Deg. Average Level of 95% Back of Queue Prop. Effective Aver. No. Average
ID Total HV Satn Delay Service Vehicles Distance Queued Stop Rate Cycles Speed
veh/h % v/c sec veh m km/h
East: Myall Street
5 T1 623 0.0 0.321 0.0 LOS A 0.0 0.0 0.00 0.00 0.00 59.9
6 R2 19 0.0 0.034 10.5 LOS B 0.1 0.8 0.62 0.79 0.62 46.1
Approach 642 0.0 0.321 0.3 NA 0.1 0.8 0.02 0.02 0.02 59.4
North: Site Access
7 L2 18 0.0 0.032 10.0 LOS A 0.1 0.7 0.58 0.77 0.58 46.9
9 R2 71 0.0 0.504 40.3 LOS E 1.8 12.5 0.93 1.05 1.25 35.4
Approach 88 0.0 0.504 34.2 LOS D 1.8 12.5 0.86 0.99 1.12 36.7
West: Myall Street
10 L2 76 0.0 0.041 5.5 LOS A 0.0 0.0 0.00 0.58 0.00 53.6
11 T1 706 0.0 0.362 0.0 LOS A 0.0 0.0 0.00 0.00 0.00 59.9
Approach 782 0.0 0.362 0.6 NA 0.0 0.0 0.00 0.06 0.00 59.0
All Vehicles 1513 0.0 0.504 2.4 NA 1.8 12.5 0.06 0.10 0.07 56.5
Site Level of Service (LOS) Method: Delay (SIDRA). Site LOS Method is specified in the Parameter Settings dialog (Site tab).
Vehicle movement LOS values are based on average delay per movement.
Minor Road Approach LOS values are based on average delay for all vehicle movements.
NA: Intersection LOS and Major Road Approach LOS values are Not Applicable for two-way sign control since the average delay
is not a good LOS measure due to zero delays associated with major road movements.
SIDRA Standard Delay Model is used. Control Delay includes Geometric Delay.
Gap-Acceptance Capacity: SIDRA Standard (Akçelik M3D).
HV (%) values are calculated for All Movement Classes of All Heavy Vehicle Model Designation.
SIDRA INTERSECTION 8.0 | Copyright © 2000-2018 Akcelik and Associates Pty Ltd | sidrasolutions.com
Organisation: TTM CONSULTING PTY LTD | Processed: Thursday, 5 September 2019 2:11:25 PM
Project: \\TTMFPS01\Synergy\BR\Synergy\Projects\19BRT\19BRT0357 Lot 2 & 3 Myall Street, Cooroy\6 - Analysis\19BRT0357 SA_01_Site
access (turn treatments).sip8
Page 41
MOVEMENT SUMMARY
Site: [2024 PM Project - Site Access]
Myall Street / Site Access
Site Category: (None)
Giveway / Yield (Two-Way)
Movement Performance - Vehicles
Mov Turn Demand Flows Deg. Average Level of 95% Back of Queue Prop. Effective Aver. No. Average
ID Total HV Satn Delay Service Vehicles Distance Queued Stop Rate Cycles Speed
veh/h % v/c sec veh m km/h
East: Myall Street
5 T1 474 0.0 0.244 0.0 LOS A 0.0 0.0 0.00 0.00 0.00 59.9
6 R2 6 0.0 0.007 7.7 LOS A 0.0 0.2 0.48 0.63 0.48 48.2
Approach 480 0.0 0.244 0.1 NA 0.0 0.2 0.01 0.01 0.01 59.8
North: Site Access
7 L2 17 0.0 0.239 8.4 LOS A 0.8 5.9 0.72 0.89 0.79 42.8
9 R2 68 0.0 0.239 16.6 LOS C 0.8 5.9 0.72 0.89 0.79 46.9
Approach 85 0.0 0.239 15.0 LOS B 0.8 5.9 0.72 0.89 0.79 46.3
West: Myall Street
10 L2 35 0.0 0.019 5.5 LOS A 0.0 0.0 0.00 0.58 0.00 53.6
11 T1 458 0.0 0.235 0.0 LOS A 0.0 0.0 0.00 0.00 0.00 60.0
Approach 493 0.0 0.235 0.4 NA 0.0 0.0 0.00 0.04 0.00 59.2
All Vehicles 1058 0.0 0.244 1.4 NA 0.8 5.9 0.06 0.09 0.07 57.7
Site Level of Service (LOS) Method: Delay (SIDRA). Site LOS Method is specified in the Parameter Settings dialog (Site tab).
Vehicle movement LOS values are based on average delay per movement.
Minor Road Approach LOS values are based on average delay for all vehicle movements.
NA: Intersection LOS and Major Road Approach LOS values are Not Applicable for two-way sign control since the average delay
is not a good LOS measure due to zero delays associated with major road movements.
SIDRA Standard Delay Model is used. Control Delay includes Geometric Delay.
Gap-Acceptance Capacity: SIDRA Standard (Akçelik M3D).
HV (%) values are calculated for All Movement Classes of All Heavy Vehicle Model Designation.
SIDRA INTERSECTION 8.0 | Copyright © 2000-2018 Akcelik and Associates Pty Ltd | sidrasolutions.com
Organisation: TTM CONSULTING PTY LTD | Processed: Thursday, 5 September 2019 2:11:26 PM
Project: \\TTMFPS01\Synergy\BR\Synergy\Projects\19BRT\19BRT0357 Lot 2 & 3 Myall Street, Cooroy\6 - Analysis\19BRT0357 SA_01_Site
access (turn treatments).sip8
Page 42
MOVEMENT SUMMARY
Site: [2034 PM Project - Site Access]
Myall Street / Site Access
Site Category: (None)
Giveway / Yield (Two-Way)
Movement Performance - Vehicles
Mov Turn Demand Flows Deg. Average Level of 95% Back of Queue Prop. Effective Aver. No. Average
ID Total HV Satn Delay Service Vehicles Distance Queued Stop Rate Cycles Speed
veh/h % v/c sec veh m km/h
East: Myall Street
5 T1 579 0.0 0.299 0.0 LOS A 0.0 0.0 0.00 0.00 0.00 59.9
6 R2 6 0.0 0.009 8.5 LOS A 0.0 0.2 0.53 0.66 0.53 47.5
Approach 585 0.0 0.299 0.1 NA 0.0 0.2 0.01 0.01 0.01 59.8
North: Site Access
7 L2 17 0.0 0.338 10.9 LOS B 1.2 8.6 0.82 0.98 1.01 38.5
9 R2 68 0.0 0.338 24.1 LOS C 1.2 8.6 0.82 0.98 1.01 43.3
Approach 85 0.0 0.338 21.5 LOS C 1.2 8.6 0.82 0.98 1.01 42.5
West: Myall Street
10 L2 35 0.0 0.019 5.5 LOS A 0.0 0.0 0.00 0.58 0.00 53.6
11 T1 562 0.0 0.288 0.0 LOS A 0.0 0.0 0.00 0.00 0.00 59.9
Approach 597 0.0 0.288 0.4 NA 0.0 0.0 0.00 0.03 0.00 59.4
All Vehicles 1267 0.0 0.338 1.7 NA 1.2 8.6 0.06 0.08 0.07 57.5
Site Level of Service (LOS) Method: Delay (SIDRA). Site LOS Method is specified in the Parameter Settings dialog (Site tab).
Vehicle movement LOS values are based on average delay per movement.
Minor Road Approach LOS values are based on average delay for all vehicle movements.
NA: Intersection LOS and Major Road Approach LOS values are Not Applicable for two-way sign control since the average delay
is not a good LOS measure due to zero delays associated with major road movements.
SIDRA Standard Delay Model is used. Control Delay includes Geometric Delay.
Gap-Acceptance Capacity: SIDRA Standard (Akçelik M3D).
HV (%) values are calculated for All Movement Classes of All Heavy Vehicle Model Designation.
SIDRA INTERSECTION 8.0 | Copyright © 2000-2018 Akcelik and Associates Pty Ltd | sidrasolutions.com
Organisation: TTM CONSULTING PTY LTD | Processed: Thursday, 5 September 2019 2:11:26 PM
Project: \\TTMFPS01\Synergy\BR\Synergy\Projects\19BRT\19BRT0357 Lot 2 & 3 Myall Street, Cooroy\6 - Analysis\19BRT0357 SA_01_Site
access (turn treatments).sip8
Page 43
SITE LAYOUT
Site: 102 [2019 AM Survey - Roundabout]
New Site
Site Category: (None)
Roundabout
SIDRA INTERSECTION 8.0 | Copyright © 2000-2018 Akcelik and Associates Pty Ltd | sidrasolutions.com
Organisation: TTM CONSULTING PTY LTD | Created: Thursday, 5 September 2019 2:58:29 PM
Project: \\TTMFPS01\Synergy\BR\Synergy\Projects\19BRT\19BRT0357 Lot 2 & 3 Myall Street, Cooroy\6 - Analysis\19BRT0357
SA_01_Roundabout.sip8
Page 44
MOVEMENT SUMMARY
Site: 102 [2019 AM Survey - Roundabout]
New Site
Site Category: (None)
Roundabout
Movement Performance - Vehicles
Mov Turn Demand Flows Deg. Average Level of 95% Back of Queue Prop. Effective Aver. No. Average
ID Total HV Satn Delay Service Vehicles Distance Queued Stop Rate Cycles Speed
veh/h % v/c sec veh m km/h
South: RoadName
1 L2 385 0.0 0.209 3.1 LOS A 1.3 9.4 0.25 0.37 0.25 56.9
3 R2 21 0.0 0.015 9.9 LOS A 0.1 0.6 0.23 0.57 0.23 55.2
Approach 406 0.0 0.209 3.4 LOS A 1.3 9.4 0.24 0.38 0.24 56.8
East: RoadName
4 L2 23 0.0 0.106 4.5 LOS A 0.5 3.4 0.47 0.44 0.47 55.9
5 T1 88 0.0 0.106 3.9 LOS A 0.5 3.4 0.47 0.44 0.47 58.3
Approach 112 0.0 0.106 4.0 LOS A 0.5 3.4 0.47 0.44 0.47 57.8
West: RoadName
11 T1 68 0.0 0.059 2.2 LOS A 0.2 1.7 0.09 0.22 0.09 60.8
12 R2 467 0.0 0.265 9.6 LOS A 1.4 9.5 0.09 0.60 0.09 55.8
Approach 536 0.0 0.265 8.7 LOS A 1.4 9.5 0.09 0.55 0.09 56.4
All Vehicles 1054 0.0 0.265 6.1 LOS A 1.4 9.5 0.19 0.47 0.19 56.7
Site Level of Service (LOS) Method: Delay (SIDRA). Site LOS Method is specified in the Parameter Settings dialog (Site tab).
Roundabout LOS Method: SIDRA Roundabout LOS.
Vehicle movement LOS values are based on average delay per movement.
Intersection and Approach LOS values are based on average delay for all vehicle movements.
Roundabout Capacity Model: SIDRA Standard.
SIDRA Standard Delay Model is used. Control Delay includes Geometric Delay.
Gap-Acceptance Capacity: SIDRA Standard (Akçelik M3D).
HV (%) values are calculated for All Movement Classes of All Heavy Vehicle Model Designation.
SIDRA INTERSECTION 8.0 | Copyright © 2000-2018 Akcelik and Associates Pty Ltd | sidrasolutions.com
Organisation: TTM CONSULTING PTY LTD | Processed: Thursday, 5 September 2019 2:57:59 PM
Project: \\TTMFPS01\Synergy\BR\Synergy\Projects\19BRT\19BRT0357 Lot 2 & 3 Myall Street, Cooroy\6 - Analysis\19BRT0357
SA_01_Roundabout.sip8
Page 45
MOVEMENT SUMMARY
Site: 102 [2024 AM Base - Roundabout]
New Site
Site Category: (None)
Roundabout
Movement Performance - Vehicles
Mov Turn Demand Flows Deg. Average Level of 95% Back of Queue Prop. Effective Aver. No. Average
ID Total HV Satn Delay Service Vehicles Distance Queued Stop Rate Cycles Speed
veh/h % v/c sec veh m km/h
South: RoadName
1 L2 425 0.0 0.232 3.1 LOS A 1.5 10.8 0.27 0.38 0.27 56.8
3 R2 23 0.0 0.017 9.9 LOS A 0.1 0.6 0.25 0.57 0.25 55.1
Approach 448 0.0 0.232 3.5 LOS A 1.5 10.8 0.27 0.39 0.27 56.7
East: RoadName
4 L2 25 0.0 0.121 4.8 LOS A 0.6 4.0 0.50 0.47 0.50 55.7
5 T1 98 0.0 0.121 4.2 LOS A 0.6 4.0 0.50 0.47 0.50 58.1
Approach 123 0.0 0.121 4.3 LOS A 0.6 4.0 0.50 0.47 0.50 57.6
West: RoadName
11 T1 76 0.0 0.065 2.2 LOS A 0.3 1.8 0.10 0.22 0.10 60.7
12 R2 516 0.0 0.293 9.6 LOS A 1.6 10.9 0.10 0.60 0.10 55.8
Approach 592 0.0 0.293 8.7 LOS A 1.6 10.9 0.10 0.55 0.10 56.3
All Vehicles 1163 0.0 0.293 6.2 LOS A 1.6 10.9 0.21 0.48 0.21 56.6
Site Level of Service (LOS) Method: Delay (SIDRA). Site LOS Method is specified in the Parameter Settings dialog (Site tab).
Roundabout LOS Method: SIDRA Roundabout LOS.
Vehicle movement LOS values are based on average delay per movement.
Intersection and Approach LOS values are based on average delay for all vehicle movements.
Roundabout Capacity Model: SIDRA Standard.
SIDRA Standard Delay Model is used. Control Delay includes Geometric Delay.
Gap-Acceptance Capacity: SIDRA Standard (Akçelik M3D).
HV (%) values are calculated for All Movement Classes of All Heavy Vehicle Model Designation.
SIDRA INTERSECTION 8.0 | Copyright © 2000-2018 Akcelik and Associates Pty Ltd | sidrasolutions.com
Organisation: TTM CONSULTING PTY LTD | Processed: Thursday, 5 September 2019 2:57:59 PM
Project: \\TTMFPS01\Synergy\BR\Synergy\Projects\19BRT\19BRT0357 Lot 2 & 3 Myall Street, Cooroy\6 - Analysis\19BRT0357
SA_01_Roundabout.sip8
Page 46
MOVEMENT SUMMARY
Site: 102 [2024 AM Project - Roundabout]
New Site
Site Category: (None)
Roundabout
Movement Performance - Vehicles
Mov Turn Demand Flows Deg. Average Level of 95% Back of Queue Prop. Effective Aver. No. Average
ID Total HV Satn Delay Service Vehicles Distance Queued Stop Rate Cycles Speed
veh/h % v/c sec veh m km/h
South: RoadName
1 L2 444 0.0 0.243 3.1 LOS A 1.6 11.4 0.27 0.38 0.27 56.8
3 R2 23 0.0 0.017 9.9 LOS A 0.1 0.6 0.25 0.57 0.25 55.1
Approach 467 0.0 0.243 3.4 LOS A 1.6 11.4 0.27 0.39 0.27 56.7
East: RoadName
4 L2 25 0.0 0.122 4.9 LOS A 0.6 4.1 0.51 0.48 0.51 55.7
5 T1 98 0.0 0.122 4.3 LOS A 0.6 4.1 0.51 0.48 0.51 58.0
Approach 123 0.0 0.122 4.4 LOS A 0.6 4.1 0.51 0.48 0.51 57.5
West: RoadName
11 T1 76 0.0 0.065 2.2 LOS A 0.3 1.8 0.10 0.22 0.10 60.7
12 R2 534 0.0 0.303 9.6 LOS A 1.6 11.3 0.10 0.60 0.10 55.8
Approach 609 0.0 0.303 8.7 LOS A 1.6 11.3 0.10 0.55 0.10 56.3
All Vehicles 1200 0.0 0.303 6.2 LOS A 1.6 11.4 0.21 0.48 0.21 56.6
Site Level of Service (LOS) Method: Delay (SIDRA). Site LOS Method is specified in the Parameter Settings dialog (Site tab).
Roundabout LOS Method: SIDRA Roundabout LOS.
Vehicle movement LOS values are based on average delay per movement.
Intersection and Approach LOS values are based on average delay for all vehicle movements.
Roundabout Capacity Model: SIDRA Standard.
SIDRA Standard Delay Model is used. Control Delay includes Geometric Delay.
Gap-Acceptance Capacity: SIDRA Standard (Akçelik M3D).
HV (%) values are calculated for All Movement Classes of All Heavy Vehicle Model Designation.
SIDRA INTERSECTION 8.0 | Copyright © 2000-2018 Akcelik and Associates Pty Ltd | sidrasolutions.com
Organisation: TTM CONSULTING PTY LTD | Processed: Thursday, 5 September 2019 2:57:59 PM
Project: \\TTMFPS01\Synergy\BR\Synergy\Projects\19BRT\19BRT0357 Lot 2 & 3 Myall Street, Cooroy\6 - Analysis\19BRT0357
SA_01_Roundabout.sip8
Page 47
MOVEMENT SUMMARY
Site: 102 [2019 PM Survey - Roundabout]
New Site
Site Category: (None)
Roundabout
Movement Performance - Vehicles
Mov Turn Demand Flows Deg. Average Level of 95% Back of Queue Prop. Effective Aver. No. Average
ID Total HV Satn Delay Service Vehicles Distance Queued Stop Rate Cycles Speed
veh/h % v/c sec veh m km/h
South: RoadName
1 L2 368 0.0 0.197 3.0 LOS A 1.2 8.5 0.20 0.36 0.20 57.1
3 R2 15 0.0 0.011 9.8 LOS A 0.1 0.4 0.19 0.57 0.19 55.4
Approach 383 0.0 0.197 3.3 LOS A 1.2 8.5 0.20 0.36 0.20 57.0
East: RoadName
4 L2 22 0.0 0.077 3.9 LOS A 0.3 2.3 0.39 0.38 0.39 56.4
5 T1 65 0.0 0.077 3.3 LOS A 0.3 2.3 0.39 0.38 0.39 58.8
Approach 87 0.0 0.077 3.4 LOS A 0.3 2.3 0.39 0.38 0.39 58.2
West: RoadName
11 T1 86 0.0 0.072 2.1 LOS A 0.3 2.0 0.07 0.22 0.07 60.9
12 R2 342 0.0 0.193 9.6 LOS A 0.9 6.3 0.07 0.61 0.07 55.9
Approach 428 0.0 0.193 8.1 LOS A 0.9 6.3 0.07 0.53 0.07 56.8
All Vehicles 899 0.0 0.197 5.6 LOS A 1.2 8.5 0.16 0.44 0.16 57.0
Site Level of Service (LOS) Method: Delay (SIDRA). Site LOS Method is specified in the Parameter Settings dialog (Site tab).
Roundabout LOS Method: SIDRA Roundabout LOS.
Vehicle movement LOS values are based on average delay per movement.
Intersection and Approach LOS values are based on average delay for all vehicle movements.
Roundabout Capacity Model: SIDRA Standard.
SIDRA Standard Delay Model is used. Control Delay includes Geometric Delay.
Gap-Acceptance Capacity: SIDRA Standard (Akçelik M3D).
HV (%) values are calculated for All Movement Classes of All Heavy Vehicle Model Designation.
SIDRA INTERSECTION 8.0 | Copyright © 2000-2018 Akcelik and Associates Pty Ltd | sidrasolutions.com
Organisation: TTM CONSULTING PTY LTD | Processed: Thursday, 5 September 2019 2:58:00 PM
Project: \\TTMFPS01\Synergy\BR\Synergy\Projects\19BRT\19BRT0357 Lot 2 & 3 Myall Street, Cooroy\6 - Analysis\19BRT0357
SA_01_Roundabout.sip8
Page 48
MOVEMENT SUMMARY
Site: 102 [2024 PM Base - Roundabout ]
New Site
Site Category: (None)
Roundabout
Movement Performance - Vehicles
Mov Turn Demand Flows Deg. Average Level of 95% Back of Queue Prop. Effective Aver. No. Average
ID Total HV Satn Delay Service Vehicles Distance Queued Stop Rate Cycles Speed
veh/h % v/c sec veh m km/h
South: RoadName
1 L2 406 0.0 0.218 3.0 LOS A 1.4 9.7 0.22 0.36 0.22 57.0
3 R2 16 0.0 0.011 9.8 LOS A 0.1 0.4 0.20 0.57 0.20 55.3
Approach 422 0.0 0.218 3.3 LOS A 1.4 9.7 0.22 0.37 0.22 57.0
East: RoadName
4 L2 24 0.0 0.087 4.0 LOS A 0.4 2.6 0.41 0.40 0.41 56.3
5 T1 72 0.0 0.087 3.4 LOS A 0.4 2.6 0.41 0.40 0.41 58.7
Approach 96 0.0 0.087 3.6 LOS A 0.4 2.6 0.41 0.40 0.41 58.0
West: RoadName
11 T1 96 0.0 0.079 2.1 LOS A 0.3 2.3 0.08 0.22 0.08 60.9
12 R2 378 0.0 0.213 9.6 LOS A 1.0 7.1 0.07 0.61 0.07 55.9
Approach 474 0.0 0.213 8.1 LOS A 1.0 7.1 0.07 0.53 0.07 56.8
All Vehicles 992 0.0 0.218 5.6 LOS A 1.4 9.7 0.17 0.45 0.17 57.0
Site Level of Service (LOS) Method: Delay (SIDRA). Site LOS Method is specified in the Parameter Settings dialog (Site tab).
Roundabout LOS Method: SIDRA Roundabout LOS.
Vehicle movement LOS values are based on average delay per movement.
Intersection and Approach LOS values are based on average delay for all vehicle movements.
Roundabout Capacity Model: SIDRA Standard.
SIDRA Standard Delay Model is used. Control Delay includes Geometric Delay.
Gap-Acceptance Capacity: SIDRA Standard (Akçelik M3D).
HV (%) values are calculated for All Movement Classes of All Heavy Vehicle Model Designation.
SIDRA INTERSECTION 8.0 | Copyright © 2000-2018 Akcelik and Associates Pty Ltd | sidrasolutions.com
Organisation: TTM CONSULTING PTY LTD | Processed: Thursday, 5 September 2019 2:58:00 PM
Project: \\TTMFPS01\Synergy\BR\Synergy\Projects\19BRT\19BRT0357 Lot 2 & 3 Myall Street, Cooroy\6 - Analysis\19BRT0357
SA_01_Roundabout.sip8
Page 49
MOVEMENT SUMMARY
Site: 102 [2024 PM Project - Roundabout ]
New Site
Site Category: (None)
Roundabout
Movement Performance - Vehicles
Mov Turn Demand Flows Deg. Average Level of 95% Back of Queue Prop. Effective Aver. No. Average
ID Total HV Satn Delay Service Vehicles Distance Queued Stop Rate Cycles Speed
veh/h % v/c sec veh m km/h
South: RoadName
1 L2 414 0.0 0.222 3.0 LOS A 1.4 10.0 0.22 0.36 0.22 57.0
3 R2 16 0.0 0.011 9.8 LOS A 0.1 0.4 0.20 0.57 0.20 55.3
Approach 429 0.0 0.222 3.3 LOS A 1.4 10.0 0.22 0.37 0.22 57.0
East: RoadName
4 L2 24 0.0 0.087 4.1 LOS A 0.4 2.7 0.42 0.41 0.42 56.2
5 T1 72 0.0 0.087 3.5 LOS A 0.4 2.7 0.42 0.41 0.42 58.6
Approach 96 0.0 0.087 3.7 LOS A 0.4 2.7 0.42 0.41 0.42 58.0
West: RoadName
11 T1 96 0.0 0.080 2.1 LOS A 0.3 2.3 0.08 0.22 0.08 60.9
12 R2 395 0.0 0.222 9.6 LOS A 1.1 7.5 0.07 0.61 0.07 55.9
Approach 491 0.0 0.222 8.1 LOS A 1.1 7.5 0.07 0.53 0.07 56.8
All Vehicles 1016 0.0 0.222 5.7 LOS A 1.4 10.0 0.17 0.45 0.17 57.0
Site Level of Service (LOS) Method: Delay (SIDRA). Site LOS Method is specified in the Parameter Settings dialog (Site tab).
Roundabout LOS Method: SIDRA Roundabout LOS.
Vehicle movement LOS values are based on average delay per movement.
Intersection and Approach LOS values are based on average delay for all vehicle movements.
Roundabout Capacity Model: SIDRA Standard.
SIDRA Standard Delay Model is used. Control Delay includes Geometric Delay.
Gap-Acceptance Capacity: SIDRA Standard (Akçelik M3D).
HV (%) values are calculated for All Movement Classes of All Heavy Vehicle Model Designation.
SIDRA INTERSECTION 8.0 | Copyright © 2000-2018 Akcelik and Associates Pty Ltd | sidrasolutions.com
Organisation: TTM CONSULTING PTY LTD | Processed: Thursday, 5 September 2019 2:58:00 PM
Project: \\TTMFPS01\Synergy\BR\Synergy\Projects\19BRT\19BRT0357 Lot 2 & 3 Myall Street, Cooroy\6 - Analysis\19BRT0357
SA_01_Roundabout.sip8