               Preparation of a Preliminary Construction Management Plan
               4.     A preliminary Construction Management Plan must be submitted with any Operational Works
                      application and must address the following:
                      a.      traffic management during all aspects of the construction phase including:
                              i.       a Traffic Management Control Plan in accordance with the Manual of Uniform
                                       Traffic Control Devices (MUTCD) detailing all temporary signage and traffic
                                       control measures prior to construction.
                              ii.      maintenance of safe pedestrian access for the areas affected by the works during
                                       and after daily construction has ceased.
                                       iii. proposed fencing to the site during the construction phase of the
                                       development.
                              iv.      approval of the Traffic Management Control Plan by the Department of Transport
                                       and Main Roads (DTMR) for any works on State controlled roads.
                                       v.   provision for worker car parking.
                      b.      maintenance and protection of water quality and existing drainage lines through the
                              construction site, through the implementation of appropriate erosion and sediment
                              control measures
                      c.      works programme identifying key components of the works and their respective
                              durations
                      d.      establishment of a communication protocol with the general public, adjoining owners,
                              emergency services and local businesses to advise of agreed construction times,
                              impacts on traffic, services and other relevant issues
                      e.      identification of complaint management procedures including:
                              i.       contact details for the on-site manager
                              ii.      dispute resolution procedures
                      f.      details on the location of external fill sites/sources, the haulage route, type of vehicle
                              to be utilised during filling operations and frequency of usage. NB any damage to the
                              existing road system as a result of haulage operations shall be fully repaired at the
                              applicant’s expense
                      g.      it is acknowledged that the preliminary Construction Management Plan will be a draft
                              document requiring finalisation upon appointment of the Principal Contractor employed
                              to construct the works and a final document will be required to be submitted at the
                              PreStart Meeting for the project.
               Private Infrastructure
               5.     All private infrastructure for the development must be designed to meet the planning scheme
                      requirements unless otherwise agreed by the relevant authority.
               Qualified Person
               6.     For the purpose of preparing a Landscape Plan, a qualified person is considered to be a
                      landscape architect, landscape designer and/or horticulturist with a minimum of 3 years
                      current experience in the field of landscape design.
               7.     For the purpose of preparing an Arborist Report, a qualified person is considered to be a
                      person with either:
                      a.      ISA certification; or
                      b.      a Diploma of Arboriculture in addition to a minimum of 3 years current experience in
                              the field of arboriculture.




                                                                                                        Page 13 of 18
Document Set ID: 24498083
Version: 5, Version Date: 02/02/2026

Used in these records

About this file

File size
432 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Minor Change Existing Approval - RAL18_0023 02 (As Published).pdf · 432 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.