INFRASTRUCTURE & SERVICES COMMITTEE MEETING REPORT 10 NOVEMBER 2015
The J First Quarter 2015/16
Actual YTD Budget YTD Variance (YTD)
Total Revenue $143,499 $146,340 -$2,841
Total Expenditure $299,637 $300,448 $811
Net Operating Surplus/Deficit -$156,138 -$154,108 -$2,030
Depreciation* $68,628 $68,628 $0
Internal Charges* $51,901 $50,460 -$1,441
* Please note depreciation and internal charges are included in total expenditure.
The J First Quarter 2015/16
$400,000
$300,000
$200,000
Actual
$100,000
Budget
$0
Total Revenue Total Expenditure Net Operating
Surplus/Deficit
($100,000)
($200,000)
As a whole, The J’s financial performance is relatively on track for the first quarter of the year,
with the net cost to Council being $2,030 greater than budgeted.
Revenue performed solidly with employee cost recoveries the only account to show a negative
variance of any significance. This account ended the quarter $5,500 behind budget. Upon review
the budget showed to be heavily skewed to the first quarter (46% of annual revenue was
budgeted for in quarter 1) and will be adjusted to more realistic levels to ensure more accurate
YTD reporting from this point forward.
Employee benefits were $15,338 overspent for the quarter with a majority of the cost attributed to
casual employees. While revenue budgets for the quarter represented 31% of annual targets
(due to the large number of significant events in quarter 1), employee benefits budgets only
represented 24% of the annual cost. This mismatch explains the overspend which will fall back in
line over coming months.
A number of expenditure accounts saw minor savings during the quarter however it is expected
that a majority of these will even out throughout the year.
Page 50 of 88
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.