Negotiated Decision Notice MCU21 0002
Officer: Tara Norley Direct Telephone: 07 53296486 Our Reference: MCU21/0002 Your Reference: 2020-41 16 April 2021 Karloo Constructions C/- Building Suncoast Green 6 Lorraine Ave MARCOOLA QLD 4564 [email protected] Dear Sir Negotiated Decision Notice Planning Act 2016 I refer to your application and the representations you made in respect to the decision notice. On 16 April 2021, Council decided your representations. This negotiated decision notice replaces the decision notice approved on 6 April 2021. Details of the negotiated decision are as follows: APPLICATION details Application No: MCU21/0002 & OPW21/0015 Street address: 13 Vision Ct Noosaville Qld 4566 Real property description: Lot 5 SP 295958 Planning Scheme: Noosa Plan 2020 (25 September 2020) decision details Council on 6 April 2021, decided to issue the following type of approval: Development Permit for Material Change of Use of Premises (Low Impact Industry) In relation to representations, Council on 16 April 2021 decided to: Agree to amend annotation on Approved Plans Note the report is provided in accordance with Section 83(9) of the Planning Act 2016 currency period of approval The currency period for this development approval is stated in the conditions below. assessment manager conditions MATERIAL CHANGE OF USE PLANNING Unless otherwise stated, all conditions of this Decision Notice must be complied with prior to the use commencing, and then compliance maintained at all times while the use continues. Approved Plans Development undertaken in accordance with this approval must generally comply with the approved plans of development. The approved plans are listed in the following table unless otherwise amended by these conditions. Sheet No. Rev. Plan/Document Name Date 01 B Cover Sheet, prepared by Building Suncoast Green - 02 B Site/Floor Plan Level 1, prepared by Building Suncoast Green - 03 B Roof Plan Level 2, prepared by Building Suncoast Green - 04 B Sections, prepared by Building Suncoast Green - 05 B Elevations, prepared by Building Suncoast Green - 06 B Landscape Plan, prepared by Building Suncoast Green As annotated by Council - 07 B Landscape Schedule, prepared by Building Suncoast Green As annotated by Council - Currency Period This development approval lapses if the use has not happened by 16 April 2027, unless an application to extend the currency period is approved by Council. Performance Bond Security in the form of a cash bond or trading bank guarantee to the sum of $15,000 must be submitted to Council, to secure performance of all conditions of this approval, prior to pre-start meeting. The cash bond or trading bank guarantee will be returned on performance of the conditions of approval less any costs incurred by Council in respect of enforcing performance of this permit. Council reserves the right to call upon the bond or guaranteed sum to effect compliance with conditions. Nature and Extent of Approved Use Any retail sale of goods and/or administration uses must remain an ancillary component to, and have a direct relationship with the approved industrial use. The combined gross floor area (GFA) of any retail and administration components must not exceed 40% of the total GFA of the tenancy, with either individual component not exceeding 30% of the GFA of the tenancy. The approved tenancies must not be used as a self-storage facility. Industry activities are operated in a manner to avoid noise emissions that unreasonably diminish the amenity of the area or surrounding uses. Building Height The maximum height of the development must not exceed 10 metres above the finished ground level and the natural ground level. Building Appearance The development must be finished with subdued external building colours. All mechanical equipment and other service infrastructure located on the site must be: Located not less than 2 metres from a property boundary; and Fully enclosed or screened such that they are not visible from the street frontages nor adjoining properties. Where screened by landscaping, landscaping beds must be at least 1.5 metres wide. All waste storage areas must be screened from the street and adjoining property by buildings, landscaping or fencing. Emissions The development must contain any odour and/or dust air pollutants within the boundaries of the site. Landscaping The development site must be landscaped. The works must be undertaken in accordance with the Operational Works approval and Planning Scheme Policy PSP2 - Landscaping and must include in particular: the works shown on the Approved Plans; vegetated screening of any electrical transformers, bin storage areas and the like from the road frontage; provision of 4 street trees within the Vision Court road reserve, including 3 on the western side and one on the eastern side of the new driveway; and sreet trees must be a minimum pot size of 45L and planted in accordance with IPWEA drawing GS-010, with 100mm of forest mulch applied to the root collar and spade edged. Any fencing to the road frontage must be set back at least 1 metre from both street boundaries, and must have a minimum average setback of 2 metres to the street boundary. All land between the fence and the property boundary must be densely landscaped. All landscape works must be established and maintained in accordance with the approved design for the life of the development, and in a manner that ensures healthy, sustained and vigorous plant growth. All plant material must be allowed to grow to full form and be refurbished when its life expectancy is reached. Fencing and Walls The rear and side boundaries of the site are to be enclosed with security fencing no less than 1.8 metres in height. Mechanical plant, equipment and storage Mechanical plant and equipment are to be fully enclosed or screened and visually integrated into the line and plane of the building and roof design and must not project beyond the height or width of the building when viewed from the street and adjoining properties Water & Sewer Connections An underground connection to reticulated water and sewerage must be provided to the development site in accordance with the standards and requirements of Northern SEQ Distributor–Retailer Authority (Unitywater). A Certificate of Completion from the Northern SEQ Distributor–Retailer Authority (Unitywater) must be submitted to Council that certifies an underground connection to reticulated water and sewerage has been provided to the development site. ENGINEERING External Works Vision Ct must be upgraded for the length of its frontage to the subject site. The works must be undertaken in accordance with the subject approval and must include in particular, the construction of a pedestrian footpath in accordance with the conditions of this Decision Notice Site Access and Driveways A sealed access driveway must be provided from Vision Ct to all parking and manoeuvring areas of the development. The works must be undertaken generally in accordance with the approved plans. Car Parking A minimum of 17 car parking spaces must be provided and marked on the site and made available and accessible at all times while the use is open for business. The works must include in particular: 7 staff parking spaces within the total, which are clearly marked for that purpose Provision of vandal resistant public lighting with intensities to satisfy the requirements of Australian Standard AS1158: Public Lighting Code; 1 disabled parking space/s within the total dimensions, crossfalls and gradients in accordance with Australian Standard AS/NZS2890.1:2004 Parking Facilities All car parking areas and access driveways must be maintained exclusively for vehicle parking and manoeuvring and kept in a tidy and safe condition at all times. Directional signage must be provided to direct visitors and customers to the car parking spaces provided on site. Service Vehicles Service vehicle parking, manoeuvring and standing spaces must be provided on the site. The works must be undertaken in accordance with the conditions of this Decision Notice and must include in particular one 12 metres x 3.6 metres loading bay. Pedestrian and Bicycle Facilities Pedestrian and bicycle facilities must be provided for the development. The works must be undertaken in accordance with the conditions of this Decision Notice and must include in particular: 2 metre wide concrete footpath within the road verge, extending from the eastern edge of the proposed driveway to the prolongation of the subject property’s eastern boundary; A total of 7 bicycle parking spaces. Stormwater Drainage The site must be provided with a stormwater drainage system connecting to a lawful point of discharge. The works must be undertaken in accordance with the conditions of this Decision Notice and must include in particular, the works shown on the Approved Plans. Services Unless otherwise stipulated by telecommunications legislation at the time of construction, the development must be provided with all necessary conduits, pits and pipes to accommodate the future connection of optic fibre technology telecommunications. Certification must be submitted to Council from all relevant service providers (Energex, NBN and Unitywater) which certifies that the development has met the requirements of this Decision Notice and all applicable legislation at the time of construction. Easements Unless otherwise agreed in writing by the relevant service provider, any public or third party infrastructure located on the subject site must be placed within an easement registered against the title of the property. All easements must be designed in accordance with the planning scheme and granted at no cost to the Grantee. Where the Grantee is Council or a service authority, the easement documentation must be in accordance with the Grantee’s standard easement terms. Draft easement documentation must be submitted to Council for endorsement. All works must be kept clear of any existing or proposed easements on the subject land, unless agreed otherwise in writing by the Grantee. Earthworks and Retaining Walls All fill and associated batters must be contained entirely within the subject site unless written permission from the respective landowner(s) is provided to Council. All earthworks must be undertaken in accordance with the provisions of Australian Standard AS3798: Guidelines on Earthworks for Commercial and Residential Developments. Where the development involves excavation or filling over, or adjacent to, drainage, water supply or sewerage infrastructure, all access chamber surface levels must be adjusted to provide a freeboard of 100mm above the finished ground surface level. All retaining walls must be designed and constructed in accordance with the planning scheme and must be certified by an RPEQ where exceeding 1.0m in height. All retaining walls that are publicly accessible and exceed 1.0m in height must be fitted with a commercial grade safety fence. Damage to Services and Assets Any damage caused to existing services and assets as a result of the development works must be repaired at no cost to the asset owner at the following times: Where the damage would cause a hazard to pedestrian or vehicle safety, immediately; or where otherwise, upon completion of the works associated with the development. Any repair work which proposes to alter the alignment or level of existing services and assets must first be referred to the relevant service authority for approval OPERATIONAL WORKS APPROVED PLANS Development undertaken in accordance with this approval must generally comply with the approved plans of development. The approved plans are listed in the following table unless otherwise amended by these conditions. Plan No. Rev. Plan/Document Name Date C020 . Siteworks and Drainage Plan prepared by Empire Engineering As annotated by Council 09/02/2021 C040 A . Signs and Linemarking plan prepared by Empire Enigneering 08/12/2020 06 B Landscape Plan, prepared by Building Suncoast Green As annotated by Council - 07 B Landscape Schedule, prepared by Building Suncoast Green As annotated by Council - CURRENCY PERIOD The Currency Period for this development approval lapses if the development has not substantially started by 6 April 2027 unless an application to extend the currency period is approved by Council. SITE SPECIFIC CONDITIONS An amended plan, showing a 2m wide footpath within the road verge, extending from the eastern boundary, must be submitted to Council prior to the prestart meeting. The footpath must be constructed generally in accordance with Council’s standard drawing RS-065. PRIOR TO COMMENCEMENT OF WORKS Engineering All necessary approvals from external service providers (eg Unitywater) and external parties on which the development works are proposed have been obtained and a copy supplied to Council. A condition report including photographs of the frontage of the site must be completed and submitted to council prior to the prestart meeting. Certificates demonstrating currency of public liability insurance and works insurance covering the works must be submitted to Council prior to the prestart meeting. Council must be contacted at least 5 working days prior to any works commencing to organise a prestart. The contact number to arrange a pre-start meeting is 5329 6500. The pre-start meeting must include the relevant parties for the following aspects of the works: Civil engineering works; Landscape works; Erosion and sediment control works; Other relevant parties A Construction Management Plan must be submitted to Council prior to the pre-start meeting and must specifically address the following: Appropriate traffic signage in accordance with the Manual of Uniform Traffic Control Devices (MUTCD); Provision for safe pedestrian access across the frontage of the site both during daily construction and after daily construction has ceased. Any changes to the details associated with the supervising RPEQ or Principal Contractor during construction, must be notified to council in writing within five business days of the change occurring. Any conflict between the development and an existing or proposed service must be referred to the relevant service authority for determination prior to commencement of works. DURING CONSTRUCTION Engineering The developer must meet any costs to repair damage to any Council asset during construction, where damage is a result of the development works. Damage to assets must be repaired immediately where it creates a hazard to the community. In circumstances where the damage does not create a hazard to the community, it must be repaired immediately on completion of the works associated with the development. All works must be supervised by a Registered Professional Engineer of Queensland (RPEQ) who is independent of the Developer and Principal Contractor, and they must certify that all works conform to the Operational Works permit. Where municipal works are involved, such confirmation must be submitted for the respective hold points prior to any site inspection by Council Officers. All works must be constructed and work procedure undertaken in accordance with: The approved plans/documents and conditions detailed in this Decision Notice; The relevant conditions of the higher order Material Change of Use approval to which this approval relates; All relevant Noosa Council Planning Scheme Policies, standard drawings, standard specifications and guidelines; and The latest version of the Healthy Waterways document “Water Sensitive Urban Design Technical Design Guidelines for South East Queensland” for all water quality devices to be constructed on site Pavement Design and Construction Pavement design for privately owned works must be undertaken in accordance with the relevant standards. Structural integrity of the driveway and car park areas will remain the responsibility of the property owner/developer and must be certified by an RPEQ. Works within Road Reserve/Reinstatement Safe pedestrian access on all streets in the vicinity of the development must be maintained at all times. Should footpath/road closures be necessary to carry out construction works, Council’s Engineering Officer must be notified prior to the proposed closure and all requirements complied with. All frontage works must match neatly with existing road and verge/footpath features. Additional works beyond the frontage may be required to provide an acceptable transition to existing road and verge/footpath profiles. Electrical conduits or other services proposed to be installed within existing and proposed road reserves under existing sealed carriageways, concrete pathways, concrete/sealed driveways or significant vegetation must be installed by boring. Trenching is not permitted, unless specifically approved by Council. Pathways All pathways must be constructed in accordance with the following requirements: All footpath/cycleway must comply with Council’s Standard Drawing SEQ R-065; Provision must be made for disabled access at all kerb crossings associated with pathways, in accordance with Council's current standards; All paths must have a slip resistant surface; Expansion and contraction joints must provide a flush finish. Installation of joints by saw cutting is preferred to ensure a smooth ride for cyclists; The required work includes any modifications to ensure the footpath finishes flush with all existing service covers and the like, or alternatively these services are raised or altered, so as not to create a pedestrian safety hazard. Pathways must: Terminate in a manner that ensures smooth transition to existing surfaces for public safety; Be designed and constructed to comply with the Disability Discrimination Act (DDA), Access to Premises Standard, Austroads and relevant sections of AS1428 Design for access and mobility. Site Access and Driveways Driveway crossovers must be constructed in accordance with Council’s Standard Drawing RS-051 and any associated addendum. Any existing unnecessary or redundant property accesses must be removed, and the kerb, footpath and verge area reinstated to match the existing footpath and/or verge treatments. Grassed verge areas to be reinstated must be provided with 100 mm topsoil and grass seed or turf, and must be maintained by the developer until established. The following must be complied with during the construction of the required crossover/driveway: The driveway surfacing must consist of either an approved hot mixed asphaltic concrete or patterned/plain concrete. The driveway must be constructed so as not to concentrate stormwater runoff onto neighbouring properties Underground service conduits for water supply, electricity and any other services must be provided as part of the access driveway Where there is an existing pedestrian path, a matching crossfall must be provided for the driveway on the alignment of the path, for the full width of the path The property access must be located a minimum of 1m clear of existing power poles, streetlights or other signage. The developer is responsible for any necessary relocation of existing services to provide this clearance and must contact the relevant service authorities and comply with their requirements in relation to these works. Earthworks and Retaining Walls All earthworks shall be undertaken in accordance with the provisions of AS 3798 Guidelines on Earthworks for Commercial and Residential Development, with geotechnical testing undertaken in accordance with Section 8 of the Standard. Test results as required by AS 3798, and a certificate of quality and uniformity of fill shall be provided by a RPEQ and submitted to Council prior to the commencement of the use. Fall protection must be provided to retaining walls that are over 1m high. Slope and batters are a maximum grade of: 1 in 6 where in proximity to waterbodies; 1 in 4 for grassed areas; 1 in 3 for planted areas; 1 in 2 for combined structural engineering and planting solutions. Stormwater Drainage Appropriate scour protection must be provided at the outlet of all stormwater pipes including temporary outlets. Works associated with this permit must not adversely impact on the existing drainage conditions on other properties (eg by blocking or interfering with natural overland flows). Construction of all internal stormwater drainage works must comply with the relevant section/s of Australian Standard AS/NZS 3500.3. Erosion and Sediment Control Prescribed Water Contaminants (as defined in Schedule 9 of Environmental Protection Regulation 2008) must not be released from the site or to waters within the site, or be likely to be released should rainfall occur, unless all reasonable and practicable measures are taken to prevent or minimise the release and concentration of contamination. Sediment and erosion control measures must be in place prior to works commencing. If such measures are not in place or are not satisfactory, “on the spot” fines may be issued. Such fines can be issued if sediments from the site are found to enter or have the potential to enter Council’s stormwater system, natural waterways, any downstream stormwater filtration system or adversely impacting on other properties. The sediment and erosion control design and measures have NOT been approved, it is the site's Supervising Engineer who is responsible for ensuring that the sediment and erosion control measures have: Been duly designed by an RPEQ or CPESC and constructed in accordance with "best practise" methods; Been revised by an RPEQ or CPESC to address the issues raised by changes in the projected construction schedule and/or methods; Been revised to address predicted rainfall events, and Achieve the desired environmental outcomes. Council may request further controls to be installed should the implemented measures be found inefficient. The erosion and sediment control measures must be designed, installed and maintained in accordance with the supervising engineer instructions and the current best practice standards * (Refer to Advisory Note). The developer must ensure non-essential exposure of soil is prevented by restricting the extent of disturbance and minimising the duration of soil exposure to adverse weather conditions and effectively turf, cover or stabilise any disturbed area without delay and prior to rainfall occurring. The developer must ensure sediment does not leave the site or enter onto adjoining properties or Council’s drainage system due to surface runoff or on tyres of vehicles and/or machinery. It is essential to implement appropriate approved erosion and sediment control measures throughout the site during all phases of construction including vehicle shakedown pad/grid (or similar) at the access to the construction site. Where sediments or other contaminants are deposited on a road, they must be removed so as not to enter Council’s drainage system or waterways. Prior to the completion of the development and commencement of the use, all site surfaces must be effectively stabilised using methods which have achieved effective short-term stabilisation and which will continue to achieve effective stabilisation in the medium to long-term. For the purpose of this condition, an effectively stabilised surface is defined as one that does not, or is not likely to result in visible evidence of soil loss caused by sheet, rill or gully erosion or lead to sedimentation, or lead to water contamination. Landscaping The finished level of all mulch in garden beds and landscaped medians is to be a minimum of 50mm below the level of the adjacent top of kerb. All landscaping is to be constructed in accordance with Council’s Planning Scheme Policy PSP2 Landscaping. Suitable root barriers must be installed where proposed trees are adjacent to paths, pavement etc in accordance with Council’s Planning Scheme Policy PSP2 Landscaping. An inspection is to be carried out with the relevant Council officers, the Contractor and Supervising Engineer after road centrelines have been established, and prior to clearing being carried out. This inspection is to deal with the limits of clearing to be carried out for this development. This meeting is to take place prior to the “Pre-start” meeting. Damage to Services and Assets Any damage caused to existing services and assets as a result of the development works must be repaired at no cost to the asset owner at the following times: where the damage would cause a hazard to pedestrian or vehicle safety, immediately; or where otherwise, upon completion of the works associated with the development. Any repair work which proposes to alter the alignment or level of existing services and assets must first be referred to the relevant service authority for approval. FOLLOWING CONSTRUCTION / PRIOR TO COMMENCEMENT OF THE USE Certification Upon completion of the work a certificate must be issued by an RPEQ certifying that the works have been constructed in accordance with the Operational Works permit. A final inspection and approval of the new works and completed reinstatement works by Council’s Inspector is required. Please contact Council on 5329 6500 to arrange for the inspection. ON MAINTENANCE All municipal works must be accepted ‘On Maintenance’ by Council in accordance with Council’s relevant Planning Scheme Policy prior to plan sealing. To achieve ‘On Maintenance’, the supervising RPEQ must submit to Council: certification that all works have been undertaken and completed in accordance with the requirements of this Permit; a plan showing the constructed footpath; maintenance and operational manuals for all proprietary or site specific devices. OFF MAINTENANCE Prior to requesting an Off Maintenance inspection the developer must provide a written request for the Off Maintenance inspection. A re-inspection fee in accordance with Council’s Fees and Charge Register will be charged where: A Council inspection reveals works do not comply with approval requirements; Submitted certification falsely states works comply with approval requirements. referral agencies Not applicable. Advisory notes The following notes are included for guidance and information purposes only and do not form part of the assessment manager conditions: ADVERTISING DEVICES All Advertising Devices must comply with Schedule 10 of Subordinate Local Law No.1 (Administration) 2015 including both temporary and permanent signage. All freestanding, pylon or pole signs or signage that is illuminated requires approval from Council prior to being installed. All signage identified in s6 of Schedule 10 of Subordinate Local Law No. 1 is prohibited from being erected in the Shire. INFRASTRUCTURE CHARGES All developments and/or changes to existing developments may require payment of “Infrastructure Charges” (as applicable) in accordance with Council’s “Charges Resolution” made pursuant to the planning legislation and regulations current at the time of issue. For further information, please refer to https://www.noosa.qld.gov.au/planning-development/development-tools-guidelines/infrastructure-charges BUILDING AND CONSTRUCTION INDUSTRY (PORTABLE LONG SERVICE LEAVE) LEVY The QLeave levy must be paid prior to the issue of a development permit where it is required. Council will not be able to issue a Decision Notice without receipt of details that the Levy has been paid. The following notes are included for guidance and information purposes only and do not form part of the assessment manager conditions: GENERAL ADVISORY NOTES Council has undertaken an audit check of the Operational Works drawings in relations to the proposed works. A detailed check of the calculations and drawings has not been undertaken, as they have been certified by a RPEQ. The RPEQ bears full responsibility for all aspects of the engineering design. Council reserves the right to require further amendments and/or additions at a later date should design errors become apparent. Council reserves the right to call up any performance bond held or levy charges against the property, should emergency works be required to be undertaken by Council to make the site safe due to inactivity on the development site for extended periods of time. Should any changes or modifications to the approved plans be required as a result of construction constraints, a “Request to change an existing approval” under the Planning Act 2016 must be made. Amended plans clearly indicating the changes must be lodged with this application along with the appropriate fees. PRESTART, ON AND OFF MAINTENANCE INSPECTIONS REQUEST Contact Council on 5329 6500 to arrange a prestart or an inspection giving a minimum of 5 business days’ notice of preferred inspection time. If Council officers are required to undertake additional inspections of the same works, a reinspection fee will be applicable in accordance with Council’s Fees and Charges register applicable at the time. A minimum maintenance period of 12 months will apply to all municipal works and thereafter until such time as the works are performing in accordance with the approved design unless noted otherwise ENVIRONMENTAL ADVISORY NOTES The Environmental Protection Act 1994 states that a person must not carry out any activity that causes, or is likely to cause, environmental harm unless the person takes all reasonable and practicable measures to prevent or minimise the harm. Environmental harm includes environmental nuisance. In this regard persons and entities, involved in the civil, earthworks, construction and landscaping phases of this development are to adhere to their ‘general environmental duty’ to minimise the risk of causing environmental harm. EROSION AND SEDIMENT CONTROL Accepted best practice standards include International Erosion Control Association Australasia Best Practice Erosion and Sediment Control Qualified Person, for the purpose of erosion and sediment control is a Certified Professional in Erosion and Sediment Control (CPESC) or suitably experienced Registered Professional Engineer of Queensland (RPEQ). As a general rule, a site is determined to have achieved effective short-term stabilisation if at the time of the plan sealing inspection: a) Methods of stabilisation are: • appropriate for slopes and slope lengths; and • are consistent with best practice environmental management practices such as in the Manual for Erosion and Sediment Control or the IECA Manual; and b) Stormwater runoff from the site is not currently, and is not likely to result in visible evidence of sedimentation or erosion, or lead to water contamination. If at the time of request for plan sealing, the method of short-term stabilisation has not achieved a level of stability that Council's Officers believe will have a high probability of achieving long term stability (i.e. until house construction has occurred on all lots), Council Officers may take the following matters into consideration in determining whether the site is capable of achieving medium to long-term stability: • evidence that the site has been effectively stabilised in the short term; • evidence that soil has been adequately ameliorated; • evidence that seed of annual and perennial grass species has been applied at an adequate rate; and • that grass seed has germinated at a density that is likely to achieve an effective grass cover. property notes Not applicable. VARIATION approval details Not applicable. further development permits required Type of Development Permit Required Subject of the required Development Permit Development Permit for Building Works All building work. submissions Not applicable. RIGHTS OF APPEAL You are entitled to appeal against this decision. A copy of the relevant appeal provisions from the Planning Act 2016 is attached. During the appeal period, you as the applicant may suspend your appeal period and make written representations to Council about the conditions contained within the development approval. If Council agrees or agrees in part with the representations, a negotiated decision notice will be issued. Only one negotiated decision notice may be given. OTHER DETAILS If you wish to obtain more information about the decision, electronic copies are available on line at www.noosa.qld.gov.au or at Council Offices. Yours faithfully, Tara Norley Development Planner Enc: Appeal Rights Infrastructure Charge Notice Approved Plans/Documents DECISION NOTICE HISTORY Original Decision Notice – 6 April 2021. Negotiated Decision Notice – 16 April 2021, amend annotation on plans Appeal Rights PLANNING ACT 2016 & PLANNING REGULATION 2017 Chapter 6 Dispute resolution Part 1 Appeal rights 229 Appeals to tribunal or P&E Court (1) Schedule 1 of the Planning Act 2016 states – (a) Matters that may be appealed to – (i) either a tribunal or the P&E Court; or (ii) only a tribunal; or (iii) only the P&E Court; and (b) The person- (i) who may appeal a matter (the appellant); and (ii) who is a respondent in an appeal of the matter; and (iii) who is a co-respondent in an appeal of the matter; and (iv) who may elect to be a co-respondent in an appeal of the matter. (2) An appellant may start an appeal within the appeal period. (3) The appeal period is – (a) for an appeal by a building advisory agency – 10 business days after a decision notice for the decision is given to the agency; or (b) for an appeal against a deemed refusal – at any time after the deemed refusal happens; or (c) for an appeal against a decision of the Minister, under chapter 7, part 4, to register premises or to renew the registration of premises – 20 business days after a notice us published under section 269(3)(a) or (4); or (d) for an appeal against an infrastructure charges notice – 20 business days after the infrastructure charges notice is given to the person; or (e) for an appeal about a deemed approval of a development application for which a decision notice has not been given – 30 business days after the applicant gives the deemed approval notice to the assessment manager; or (f) for any other appeal – 20 business days after a notice of the decision for the matter, including an enforcement notice, is given to the person. Note – See the P&E Court Act for the court’s power to extend the appeal period. (4) Each respondent and co-respondent for an appeal may be heard in the appeal. (5) If an appeal is only about a referral agency’s response, the assessment manager may apply to the tribunal or P&E Court to withdraw from the appeal. (6) To remove any doubt. It is declared that an appeal against an infrastructure charges notice must not be about- (a) the adopted charge itself; or (b) for a decision about an offset or refund- (i) the establishment cost of trunk infrastructure identified in a LGIP; or (ii) the cost of infrastructure decided using the method included in the local government’s charges resolution. 230 Notice of appeal (1) An appellant starts an appeal by lodging, with the registrar of the tribunal or P&E Court, a notice of appeal that- (a) is in the approved form; and (b) succinctly states the grounds of the appeal. (2) The notice of appeal must be accompanied by the required fee. (3) The appellant or, for an appeal to a tribunal, the registrar must, within the service period, give a copy of the notice of appeal to – (a) the respondent for the appeal; and (b) each co-respondent for the appeal; and (c) for an appeal about a development application under schedule 1, table 1, item 1 – each principal submitter for the development application; and (d) for and appeal about a change application under schedule 1, table 1, item 2 – each principal submitter for the change application; and (e) each person who may elect to become a co-respondent for the appeal, other than an eligible submitter who is not a principal submitter in an appeal under paragraph (c) or (d); and (f) for an appeal to the P&E Court – the chief executive; and (g) for an appeal to a tribunal under another Act – any other person who the registrar considers appropriate. (4) The service period is – (a) if a submitter or advice agency started the appeal in the P&E Court – 2 business days after the appeal has started; or (b) otherwise – 10 business days after the appeal is started. (5) A notice of appeal given to a person who may elect to be a co-respondent must state the effect of subsection (6). (6) A person elects to be a co-respondent by filing a notice of election, in the approved form, within 10 business days after the notice of appeal is given to the person. 231 Other appeals (1) Subject to this chapter, schedule 1 and the P&E Court Act, unless the Supreme Court decides a decision or other matter under this Act is affected by jurisdictional error, the decision or matter is non-appealable. (2) The Judicial Review Act 1991, part 5 applies to the decision or matter to the extent it is affected by jurisdictional error. (3) A person who, but for subsection (1) could have made an application under the Judicial Review Act 1991 in relation to the decision or matter, may apply under part 4 of that Act for a statement of reasons in relation to the decision or matter. (4) In this section – decision includes- (a) conduct engaged in for the purpose of making a decision; and (b) other conduct that relates to the making of a decision; and (c) the making of a decision or failure to make a decision; and (d) a purported decision; and (e) a deemed refusal. non-appealable, for a decision or matter, means the decision or matter- (a) is final and conclusive; and (b) may not be challenged, appealed against, reviewed, quashed, set aside or called into question in any other way under the Judicial Review Act 1991 or otherwise, whether by the Supreme Court, another court, a tribunal or another entity; and (c) is not subject to any declaratory, injunctive or other order of the Supreme Court, another court, a tribunal or another entity on any ground. 232 Rules of the P&E Court (1) A person who is appealing to the P&E Court must comply with the rules of the court that apply to the appeal. (2) However, the P&E Court may hear and decide an appeal even if the person has not complied with the rules of the P&E Court [word/footer1.xml] Page 13 of 14 [word/footer2.xml] PO Box 141 P. (07) 5329 6500 [email protected] TEWANTIN QLD 4565 F. (07) 5329 6501 www.noosa.qld.gov.au Page 1 of 14 [word/footer3.xml] Page 14 of 14 [word/footer4.xml] PO Box 141 P. (07) 5329 6500 [email protected] TEWANTIN QLD 4565 F. (07) 5329 6501 www.noosa.qld.gov.au Page 1 of 14 [Attachment: image2.png (image text)] ee) NOOSA COUNCIL
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalSearchable page text hides email addresses. Original files are unchanged and may show email addresses.