Original PDF page 6, section 1. The text section number identifies this passage in the reader.

     2.3. Proposed Development Drainage Pattern

          2.3.1 Stormwater Concept
The internal stormwater drainage network will consist of a number of pits to provide collection points for upstream
run-off and enclosed courtyard areas, and a trench drain at the threshold of the basement car park to prevent water
intrusion and ensure that the basement parking area will be free draining under gravity.

Roof run-off from the new building will be drained via downpipes into a stormwater attenuation tank. The tank is
sized to reduce the overall developed site flows to pre-development levels, ensuring discharge from the site
minimises any impact to the downstream environment.

The internal drainage will be conveyed and discharged into an existing kerb inlet pit on Wyandra Street as the lawful
point of discharge from the site.

The roof and allotment drainage system for the proposed site shall be designed to comply with:

     1. Noosa Shire Council Planning Scheme Policy (PSP) - Engineering Design Standards – Roads, drainage and
        earthworks;

     2. The Queensland Urban Drainage Manual (QUDM); and

     3. AS/NZS 3500.3:2015 - Plumbing and Drainage Part 3: Stormwater Drainage.

Refer to Appendix A Proposed Development Concept Plan for the proposed stormwater drainage layout plan
illustrating the concept described above.



     2.4. Flood Considerations
Review of the Noosa Shire Council Intramaps flood layers including the Flood Hazards Overlay has identified that
the site is located outside of any flood or inundation areas within the locality indicating it is not expected that that
the proposed development will be subject to flooding.




Project number 20220078
File RECOR Preliminary Stormwater Management Report - 20220078.docx, 2022-03-29                                Page 6 of 15
Revision 0


P +61 7 5211 1003                          A 37 Mary St, Noosaville Qld 4566      E [email protected]    recorconsulting.com

Used in these records

About this file

File size
3.1 MB (large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Stormwater Management Plan.pdf · 3.1 MB (large file)

The download may take up to a minute.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.