APPROVED PLANS
MCU21/0133 & OPW21/0220 OP WORKS
NOOSA COUNCIL
ISSUE
0.25D - JOINT DEPTH
5 NOVEMBER 2021
25mm SEALANT
REINFORCING FABRIC
MESH. -
SAW CUT, INSERT OR TOOLED JOINT. NO ABUTTING STRUCTURE OR OTHER
SEALANT REQUIRED AT TOP OF JOINT PAVEMENT.
30
50
30
50
REINFORCING 40
FABRIC MESH.
VARIES
SEALANT TO PREVENT INGRESS
VARIES
OF DETRITUS.
OPTIONAL DOWEL FOR LOAD TRANSFER MAY BE 10MM THICK
ADDED ACROSS THE JOINT. REFER DOWEL BAR COMPRESSIBLE
SCHEDULE FOR DETAILS. FILLER MATERIAL
INDUCED FULL DEPTH OF
CRACK. 200μm MOISTURE
PAVEMENT.
BARRIER IF
ORDERED BY
SUPERINTENDENT.
200μm MOISTURE BARRIER IF ORDERED
BY SUPERINTENDENT
DETAIL A - CONTROL JOINT (CJ) DETAIL B- ISOLATION JOINT (IJ)
SCALE: 1:16 SCALE: 1:16
PLAIN DOWEL BARS, SAWCUT, FREE
FROM BURR.
JOINTING NOTES
SEALANT AND FILER TYPES TO BE 1. ALL JOINTING AND CONCRETE TO BE IN ACCORDANCE WITH THE REQUIREMENTS OF
APPROVED BY SUPERINTENDENT. AS3727.1:2016.
REINFORCING FABRIC MESH. 2. SAW CUT JOINTS MUST BE:
2.1. BETWEEN 41 AND 31 OF CONCRETE PAVEMENT DEPTHS.
2.2. CLEARED OF ANY DEBRIS FROM THE CUTTING METHOD.
10
2.3. PERFORMED WITHIN 6 TO 12 HOURS OF FINISHING CONCRETE POURS.
40 40
25
30
3. DOWELL BARS MUST BE INSTALLED EXACTLY 90° TO THE FACE OF JOINT TO ALLOW
D PVC TUBE (TIGHT FIT TO
200μm MOISTURE BARRIER IF EXPANSION AND CONTRACTION MOVEMENTS.
ORDERED BY SUPERINTENDENT. DOWEL) WITH WATERTIGHT 4. JOINTING LAYOUT TO BE CONFIRMED BY SUPERINTENDANT PRIOR TO CONSTRUCTION
ENDCAP. COMMENCING. LAYOUT SHOULD AVOID ACUTE ANGLES IN THE CONCRETE SLAB AND AVOID
MISMATCHED JOINTS.
5. JOINT SEALANTS WHERE USED MUST ADHERE TO SIDE OF JOINT FACES ONLY AND SHALL NOT
25
EXTEND ABOVE SIDES OF JOINTS ONTO THE SLAB SURFACE.
L/2 + 30mm 50
6. DOWEL BARS ARE TO BE
BOND BREAKING COMPOUND 1 6.1. FOR 100MM THICK SLAB, 12MM Ø OF LENGTH 300MM AND SPACED AT 400MM CENTRES
6.2. FOR 125MM THICK SLAB, 16MM Ø OF LENGTH 350MM AND SPACED AT 300MM CENTRES
L/2 L/2 C20.1 6.3. FOR 150MM THICK SLAB, 20MM Ø OF LENGTH 400MM AND SPACED AT 300MM CENTRES
SECTION 1 6.4. FOR 200MM THICK SLAB, 24MM Ø OF LENGTH 40MM AND SPACED AT 300MM CENTRES
SCALE: 1.10 C20.1
BOND BREAKING
COMPOUND MAY BE
REPLACED WITH A
PURPOSE MADE DOWEL
SLEEVE.
DETAIL C - EXPANSION JOINT (EJ)
SCALE: 1:16
CHANNEL 600MM
3500MM TRAFFIC LANE (NOM) 07/09/21 UPDATED FOR RFI - BRP
08/07/21 ISSUED FOR OPW - BRP
PARKING BAY 2100MM
DATE REVISION MARK CHK
PROJECT ENGINEER
PROVIDE 30MM AC10 SURFACE AND MAKE SMOOTH
SEMI-MOUNTABLE JOIN TO EXISTING
Upstream Catchment KERB TYPE 3
Area = 750m² EXISTING ROAD
tc = 5 mins 150MM N32 CONCRETE WITH 300mm WIDE STRESS ABSORBING PAVEMENT AND SEAL
fi = 0.75 (Conservatively Assumed) SL92 REINFORCEMENT STRIP LOCATED OVER JOINT.
MAKE SMOOTH
TRANSITION TO
TO REMAIN. E [email protected]
Qmax (1% AEP) = 0.07m³/s EXISTING SURFA
CE A 37 MARY ST NOOSAVILLE, QLD
200mm 300MM
1V:2H 1V:2H Sf = 3% NOMINAL 3% CROSSF
ALL
P +61 7 5211 1003
Hydraulic Radius = 0.15m
CLIENT
300mm Mannings n (QUDM - grass channel) = 0.035
V = 1.42m/s NOVATO GROUP
NOM 50MM SAND PROJECT
Area Catch Drain = 0.1m²
BLINDING LAYER
Area required (Qmax/V) = 0.05m² SAWCUT EXISTING PAVEMENT 300mm INSIDE
EXISTING EDGE.
UNIT DEVELOPMENT
CHANNEL REFER TO RS-080. 9 BOTTLEBRUSH AVENUE
DETAIL D - TURFED CATCH DRAIN
SCALE: NTS
PROVIDE PAVEMENT BASE TO
MATCH TO EXISTING
NOOSA HEADS
PROVIDE 150MM THICK
THICKNESS. TITLE
SUBGRADE LAYER OF MIN 15
CBR.
ROADS AND DRAINAGE
DETAILS
DETAIL E - ON STREET PARKING SECTION
SCALE: NTS
PROJECT NO. DRAWING NO. STATUS
20210008 C21 OPW
DRAWN DESIGNED SCALE ISSUE
BRP BRP NTS A
Document Set ID: 21694501
21635898
Version: 1, Version Date: 09/11/2021
01/10/2021
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.