Minor Change Existing Approval - MCU18 0008 01 & OPW18 0013 01 (As Published) · MCU18/0008.01
Officer: Tiani Bird
Direct Telephone: 07 5329 6245
Our Reference: MCU18/0008.01
OPW18/0013.01
Your Reference: 20251020
8 August 2025
Avapro02 P/L Tte
C/- Adapt Development Management P/L
Level 1/103 Sippy Downs Dr
SIPPY DOWNS QLD 4556
[email protected]
Dear Sir/Madam,
Decision Notice – Minor Change
Planning Act 2016
I refer to your application received on 22 July 2025, requesting a minor change to an existing
development approval. Council decided your requested changes.
Details of the decision are as follows:
1. APPLICATION DETAILS
Application No: MCU18/0008.01 & OPW18/0013.01
Street address: 1/4 Vision Ct, Noosaville Qld 4566
Real property description: Lot 1 SP 307689
Planning Scheme: Noosa Plan 2020 (25 September 2020)
2. DECISION DETAILS
The following type of approval was issued on 18 My 2018.
• Development Permit for Material Change of Use - Industrial Type 2 Production, Alteration &
Repackaging; and
• Development Permit for Operational Work (Stormwater, Earthworks, Carparking & Access,
Landscaping)
In relation to the request to make a minor change to the existing approval, Council on 7 August
2025, decided to approve the requested changes. The changes are detailed below.
A. Approve the change, and
B. Amend condition 2.
3. CURRENCY PERIOD OF APPROVAL
The currency period for this development approval is stated in the conditions below.
ABN 97.969.214.121 PO Box 141
noosa.qld.gov.au Tewantin QLD 4565
[email protected] 07 5329 6500
Page 1 of 13
Document Set ID: 24010585
Version: 4, Version Date: 08/08/2025
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalFull text of the other 12 pages
Page 2
4. ASSESSMENT MANAGER CONDITIONS
MATERIAL CHANGE OF USE – MCU18/0008
PLANNING
When Conditions must be Complied With
1. Unless otherwise stated, all conditions of this Decision Notice must be complied with prior to
the use commencing, and then compliance maintained at all times while the use continues.
2. Development undertaken in accordance with this approval must generally comply with the
approved plans of development. The approved plans are listed in the following table unless
otherwise amended by these conditions.
Plan No. Rev. Plan/Document Name Date
02 of 07 G Elevations, prepared by Building Suncoast 05.04.18
Green
03 of 07 G Sections, prepared by Building Suncoast 05.04.18
Green
04 of 07 G Rendered 3D View, prepared by Building 05.04.18
Suncoast Green
01 of 02 A Site/Ground Plan, prepared by Building 21.07.25
Suncoast Green
02 of 02 A Mezzanine Floor Plan, prepared by Building 21.07.25
Suncoast Green
3. Development authorised by this approval must be undertaken generally in accordance with
the Approved Plans listed within this Decision Notice.
Nature and Extent of Approved Use
4. Any display and retail sale of goods must remain an ancillary component to the approved
use and must not exceed 20%.
Building Appearance
5. All air conditioning units and other mechanical and service equipment must be fully enclosed
or screened such that they are not visible from the street frontages.
Building Height
6. The maximum height of the development must not exceed 10 metres above the finished
ground level and the natural ground level.
Performance Bond
7. Security in the form of a cash bond or trading bank guarantee to the sum of $15,000 must
be submitted to Council to secure performance of all conditions of this approval, prior to pre-
start meeting. The cash bond or trading bank guarantee will be returned on performance of
the conditions of approval less any costs incurred by Council in respect of enforcing
performance of this permit. Council reserves the right to call upon the bond or guaranteed
sum to effect compliance with conditions.
Street Identification
8. The street address of the development must be clearly visible and discernible from the
primary frontage of the site by the provision of a street number and, where appropriate, the
building name.
Page 2 of 13
Document Set ID: 24010585
Version: 4, Version Date: 08/08/2025
Page 3
Water & Sewer Connections
9. An underground connection to reticulated water and sewerage must be provided to the
development site in accordance with the standards and requirements of Northern SEQ
Distributor–Retailer Authority (Unitywater).
10. A Certificate of Completion from the Northern SEQ Distributor–Retailer Authority (Unitywater)
must be submitted to Council that certifies an underground connection to reticulated water
and sewerage has been provided to the development site.
ENVIRONMENTAL HEALTH
Outdoor Lighting Devices
11. Lighting associated with the use must be designed, sited, installed and tested to comply with
Table 2.1 & 2.2 of Australian Standard AS4282-1997 “Control of the obtrusive effects of
outdoor lighting” using a control level of 1.
Waste Disposal
12. The developer must provide waste storage and disposal facilities in accordance with
Planning Scheme Policy No. 9 “Waste Management Multi-Dwellings and Commercial and
Industrial Premises”. The facilities must include an external impervious area correctly sized
for all refuse and recycling containers and suitably screened from public places and
neighbouring properties. A bin wash area is required with a cold-water tap, hose and drain
outlet connected to sewer, via a bucket trap. The drain outlet must be designed to prevent
storm water entry to the sewerage system. This can be achieved with a nib wall 50mm high
and up to 700mm x 700mm wide (max 0.5m²), or alternatively the waste area can be roofed,
or any other design approved by Council.
13. Refuse containers must be provided in accordance with the requirements of the
Environmental Protection (Interim Waste) Regulation 1996 and (Waste Management)
Regulation 2000, for the storage and collection of refuse.
ENGINEERING
14. A minimum of 14 car parking spaces and 4 motor cycle spaces must be provided on the site
which includes 1 disabled space. One loading bay in addition to the 14 car spaces as
indicated on the approved plans.
15. The development is approved for deliveries by a Small Ridged Vehicle (SRV – L: 6.40m, W:
2.33m).
16. Six (6) bicycle parking spaces must be provided on-site and a minimum of 1 end of trip locker
facility must be provided to each industrial tenancy.
17. All car parking areas and access driveways must be maintained exclusively for vehicle
parking and manoeuvring and kept in a tidy and safe condition at all times.
18. To ensure pedestrian safety between vehicles exiting the site and pedestrians on the
footpath, the driveway and any associated fencing or vegetation near the driveway must
comply with the minimum sight line requirements as defined in AS 2890.1, section 3.2.4.
Stormwater Drainage
19. Stormwater runoff from the development must be disposed of on-site generally in accordance
with the approved engineering plans and must not cause scour or damage to the subject site
or any adjoining property.
Electricity and Telecommunication Services
20. Unless otherwise stipulated by telecommunications legislation at the time of construction, the
development must be provided with all necessary conduits, pits and pipes to accommodate
the future connection of optic fibre technology telecommunications.
Page 3 of 13
Document Set ID: 24010585
Version: 4, Version Date: 08/08/2025
Page 4
Landscaping Works
21. The development site must be landscaped. The works must be undertaken in accordance
with the approved plans and Planning Scheme Policy PSP 3 Landscaping Plants and
Guidelines.
22. The 2 existing garden beds with 3 street trees in each located between the footpath and the
road to be removed for the new driveways must be replaced with 6 x melaleuca salicina
(melaleuca salignus) planted between the footpath and the front boundary of the site. The
trees must have a minimum pot size of 45 litres.
23. All landscape works must be established and maintained in accordance with the approved
design for the life of the development, and in a manner that ensures healthy, sustained and
vigorous plant growth. All plant material must be allowed to grow to full form and be
refurbished when its life expectancy is reached.
OPERATIONAL WORKS – OPW18/0013
Approved Plans
1. Development undertaken in accordance with this approval must generally comply with the
approved plans of development. The approved plans are listed in the following table unless
otherwise amended by these conditions.
Plan No. Rev. Plan/Document Name Date
27284-OW3.1 - Operational Works: Bulk Earthworks, Oct 2017
prepared by SCG Consulting Engineers
27284-OW6.1 - Operational Works: Driveway & Access, Oct 17
prepared by SCG Consulting Engineers
27284-OW6.2 - Operational Works: Driveway Levels & Oct 17
Sections, prepared by SCG Consulting
Engineers
27284-SW1.1 - Operational Works: Water Supply, Oct 17
prepared by SCG Consulting Engineers
05 of 07 G Landscape Part 1, prepared by Building 05.04.18
Suncoast Green
06 of 07 G Landscape Part 2, prepared by Building 05.04.18
Suncoast Green
07 of 07 G Landscape Details, prepared by Building 05.04.18
Suncoast Green
Landscaping Works
2. Six melaleuca salicina (melaleuca salignus) street trees (as replacement for the garden trees
removed for the driveway) must be planted within the road reserve between the existing
footpath and the front boundary of the development site. The street trees must have a pot
size of 45 litres.
3. The redundant garden areas removed for the new driveways between the footpath and the
kerb and channel must be removed and the gardens replaced with turf.
4. All landscape works must be constructed and undertaken generally in accordance with the
approved plans and conditions detailed in this Decision Notice.
Page 4 of 13
Document Set ID: 24010585
Version: 4, Version Date: 08/08/2025
Page 5
5. Turfed areas within the Vision Court road reserve must:
a. join smoothly and level with adjoining surfaces; and
b. be free of disease, pest, weeds, rock and debris.
6. Landscape works must:
a. be in accordance with Planning Scheme Policy PSP 3 Landscaping Plants and
Guidelines;
b. take all measures to prevent Fire Ants (or any stages of the fire ant life cycle) entering
the work site;
c. take all measures to prevent Myrtle Rust infection;
d. not obstruct overland flow paths and must include adequate drainage to minimise
ponding. Mulch or any floatable material must not be located in swales, overland flow
paths or around grated drains;
e. not encroach onto kerb and channel, footpaths, pedestrian or vehicular/ circulation
areas;
f. not restrict access to service meters;
g. delineate all garden to grassed area interfaces with a hard edge;
h. ensure sales signage and ancillary infrastructure is not installed within the road
reserve;
i. ensure permanent irrigation is not installed within the road reserve;
j. ensure all weeds and debris are removed from planting areas prior to planting; and
k. ensure mulch is aged, comprised of leaf and limb material of varying sizes, free of
foreign matter including anthropogenic waste, rock, soil / sediment contamination and
is applied to ensure a minimum 100mm depth once settled.
7. Soil provided for landscaping must provide for the site specific vegetation performance
objectives.
8. All landscape works must be completed prior to the commencement of use.
PRIOR TO THE COMMENCEMENT OF WORKS
Engineering
9. A condition report including photographs of the frontage of the site must be completed and
submitted to council prior to the prestart meeting and any works commencing.
10. A condition report including photographs of all fences and retaining walls bordering the site
and any buildings, structures, pathways, landscaping features etc on adjoining properties
that could potentially be impacted on by the proposed earthworks and construction works
must be completed and submitted to Council prior to the prestart meeting.
11. The principal contractor must have all the appropriate insurance and public liability
documentation to carry out the works. The principal contractor is also responsible to ensure
that any subcontractors also have the appropriate insurance and public liability
documentation. Certificates demonstrating currency of public liability insurance and works
insurance covering the works must be submitted to Council prior to the prestart meeting.
Page 5 of 13
Document Set ID: 24010585
Version: 4, Version Date: 08/08/2025
Page 6
12. Council must be contacted at least 5 working days prior to any works commencing to
organise a prestart. The contact number to arrange a pre-start meeting is 5329 6245. The
pre-start meeting must include the relevant parties for the following aspects of the works:
a. civil engineering works;
b. landscape works;
c. erosion and sediment control works; and
d. other relevant parties
13. A Construction Management Plan must be submitted to Council prior to the pre-start meeting
and must specifically address the following:
a. Traffic Management during all aspects of the construct phase including:
i. A Traffic Management Control Plan in accordance with Manual of Uniform Traffic
Control Devices (MUTCD) detailing all temporary signage and traffic control
measures prior to construction
ii. Maintenance of safe pedestrian access across the frontage of the site both during
daily construction and after daily construction has ceased
iii. Proposed fencing to the site during the construction phase of the development
iv. Adequate parking arrangements for construction workers and appliances.
b. Maintenance and protection of water quality and existing drainage lines through the
construction site through the implementation of appropriate erosion and sediment
control measures
c. Works programme identifying key components of the works and their respective
durations
d. Establishment of a communication protocol with the general public, adjoining owners,
emergency services and local businesses to advise of agreed construction times,
impacts on traffic and services and other relevant issues
e. Identification of complaint management procedures including:
i. contact details for the on-site manager
ii. dispute resolution procedures
14. Any changes to the details associated with the supervising RPEQ or Principal Contractor
during construction, must be notified to council in writing within five business days of the
change occurring.
15. Any conflict between the development and an existing or proposed service must be referred
to the relevant service authority for determination prior to commencement of works.
DURING CONSTRUCTION
Engineering
16. The developer must meet any costs to repair damage to any Council asset during
construction, where damage is a result of the development works. Damage to assets must
be repaired immediately where it creates a hazard to the community. In circumstances where
the damage does not create a hazard to the community, it must be repaired immediately on
completion of the works associated with the development.
17. To ensure pedestrian safety between vehicles exiting the site and pedestrians on the
footpath, the driveway and any associated fencing or vegetation near the driveway shall
comply with the minimum sight line requirements as defined in AS 2890.1, section 3.2.4.
Page 6 of 13
Document Set ID: 24010585
Version: 4, Version Date: 08/08/2025
Page 7
18. All works must be supervised by a Registered Professional Engineer of Queensland (RPEQ)
who is independent of the Developer and Principal Contractor, and they must certify that all
works conform to the Operational Works permit. Where municipal works are involved, such
confirmation must be submitted for the respective hold points prior to any site inspection by
Council Officers.
19. All works must be constructed and work procedure undertaken in accordance with:
a. The approved plans/documents and conditions detailed in this Decision Notice
b. All relevant Noosa Council Planning Scheme Policies, standard drawings, standard
specifications and guidelines
c. The latest version of the Healthy Waterways document “Water Sensitive Urban Design
Technical Design Guidelines for South East Queensland” for all water quality devices
to be constructed on site
20. Pavement design for privately owned works must be undertaken in accordance with the
relevant standards. Structural integrity of the driveway and car park areas will remain the
responsibility of the property owner/developer and must be certified by an RPEQ.
Works within Road Reserve/Reinstatement
21. Safe pedestrian access on all streets in the vicinity of the development must be maintained
at all times. Should footpath/road closures be necessary to carry out construction works,
Council’s Engineering Officer must be notified prior to the proposed closure and all
requirements complied with.
22. All frontage works must match neatly with existing road and verge/footpath features.
Additional works beyond the frontage may be required to provide an acceptable transition to
existing road and verge/footpath profiles.
23. Any electrical conduits or other services proposed to be installed within existing and
proposed road reserves under existing sealed carriageways, concrete pathways,
concrete/sealed driveways or significant vegetation must be installed by boring. Trenching is
not permitted, unless specifically approved by Council.
Site Access and Driveways
24. Driveway crossovers must be constructed in accordance with the approved plans and in in
compliance with IPWEA standard drawing RS- 051 and must have levels and grades match
the levels and the grades of any existing or proposed concrete pathway without posing trip
hazard.
25. The following must be complied with during the construction of the required
crossover/driveway:
a. The driveway width must not exceed 7.23m at the front boundary line.
b. The driveway surfacing must consist of either an approved hot mixed asphaltic
concrete or patterned/plain concrete.
c. Underground service conduits for water supply, electricity and any other services must
be provided as part of the access driveway
d. Where there is an existing pedestrian path, a matching crossfall must be provided for
the driveway on the alignment of the path, for the full width of the path
e. Have a minimum clearance of 0.5m from any Unitywater/Telstra and be located a
minimum of 1m clear of existing power poles, streetlights or other signage. The
developer is responsible for any necessary relocation of existing services to provide
this clearance and must contact the relevant service authorities and comply with their
requirements in relation to these works.
26. Any existing kerb & channel and concrete footpath sections requiring removal due to the new
works must be saw-cut and removed to allow for a smooth and neat finish with the new
works.
Page 7 of 13
Document Set ID: 24010585
Version: 4, Version Date: 08/08/2025
Page 8
Earthworks
27. All earthworks shall be undertaken in accordance with the provisions of AS 3798 Guidelines
on Earthworks for Commercial and Residential Development, with geotechnical testing
undertaken in accordance with Section 8 of the Standard, and to a minimum of ‘Level 2’ as
defined in Appendix B. Test results as required by AS 3798, and a certificate of quality and
uniformity of fill and compaction shall be provided by a RPEQ and submitted to Council prior
to final inspection.
28. All Earthworks and construction works must be carried out taking into consideration the
protection of any existing above and below surface services, and the stability and protection
of fences and any buildings and structures on the adjoining properties.
Stormwater Drainage
29. Appropriate scour protection must be provided at the outlet of all stormwater pipes including
temporary outlets.
30. Works associated with this permit must not adversely impact on the existing drainage
conditions on other properties (eg by blocking or interfering with natural overland flows).
31. Construction of all internal stormwater drainage works must comply with the relevant
section/s of Australian Standard AS/NZS 3500.3.
32. Prior to the completion of the development, all site surfaces must be effectively stabilised
using methods which have achieved effective short-term stabilisation and which will continue
to achieve effective stabilisation in the medium- to long-term (refer to E&SC Advisory Notes).
For the purpose of this condition, an effectively stabilised surface is defined as one that does
not, or is not likely to result in visible evidence of soil loss caused by sheet, rill or gully erosion
or lead to sedimentation, or lead to water contamination.
Environment - Erosion and Sediment Control
33. Prescribed Water Contaminants (as defined in the Environmental Protection Act 1994) must
not be released from the site or to waters within the site, or be likely to be released should
rainfall occur, unless all reasonable and practicable measures are taken to prevent or
minimise the release and concentration of contamination.
34. Erosion and sediment control measures must be installed and maintained to minimise
erosion on the site and to minimise the export of sediment and associated pollutants from
the site. The erosion and sediment control measures must be designed, installed and
maintained in accordance with current best practice standards (refer to advisory notes).
35. Prior to the final inspection for the development, all site surfaces must be effectively stabilised
using methods which have achieved effective short-term stabilisation and which will continue
to achieve effective stabilisation in the medium to long-term (refer to advisory notes). For the
purpose of this condition, an effectively stabilised surface is defined as one that does not, or
is not likely to result in visible evidence of soil loss caused by sheet, rill or gully erosion or
lead to sedimentation, or lead to water contamination.
36. Limit soil exposure on the site to a distance of no more than 2m beyond the extent of
earthworks shown on the approved plans except where the exposed soil is effectively
stabilised without delay and prior to rainfall occurring.
Damage to Services and Assets
37. Any damage caused to existing services and assets as a result of the development works
must be repaired at no cost to the asset owner at the following times:
a. where the damage would cause a hazard to pedestrian or vehicle safety, immediately;
or
b. where otherwise, upon completion of the works associated with the development.
Any repair work which proposes to alter the alignment or level of existing services and assets
must first be referred to the relevant service authority for approval.
Page 8 of 13
Document Set ID: 24010585
Version: 4, Version Date: 08/08/2025
Page 9
FOLLOWING CONSTRUCTION
Certification
38. Upon completion of the work and prior to final inspection by Council a certificate must be
issued by an RPEQ certifying that the works have been constructed in accordance with the
Operational Works permit and the applicable standards.
39. A final inspection and approval of the completed works by Council’s Inspector is required.
Please contact Council on 5329 6245 to arrange for the inspection.
5. REFERRAL AGENCIES
Not applicable.
6. ADVISORY NOTES
PLANNING
Aboriginal Cultural Heritage Act 2003
1. There may be a requirement to establish a Cultural Heritage Management Plan and/or obtain
approvals pursuant to the Aboriginal Cultural Heritage Act 2003 (ACH Act).
The ACH Act establishes a cultural heritage duty of care which provides that: “A person who
carries out an activity must take all reasonable and practicable measures to ensure the
activity does not harm Aboriginal cultural heritage”. It is an offence to fail to comply with the
duty of care. Substantial monetary penalties may apply to individuals or corporations
breaching this duty of care. Injunctions may also be issued by the Land and Resources
Tribunal, and the Minister administering the ACH Act can also issue stop orders for an activity
that is harming or is likely to harm Aboriginal cultural heritage or the cultural heritage value
of Aboriginal cultural heritage.
You should contact the Cultural Heritage Unit on 07 3247 6212 to discuss any obligations
under the ACH Act.
Equitable Access and Facilities
2. The plans for the proposed building work have NOT been assessed for compliance with the
requirements of the National Construction Code - Building Code of Australia (Volume 1) as
they relate to people with disabilities. Your attention is also directed to the fact that in addition
to the requirements of the National Construction Code as they relate to people with
disabilities, one or more of the following may impact on the proposed building work:
a. the Disability Discrimination Act 1992 (Commonwealth);
b. the Anti-Discrimination Act 1991 (Queensland); and
c. the Disability (Access to Premises – Buildings) Standards.
Development Compliance Inspection
3. Prior to the commencement of the use, please contact Council's DA Planning Section to
arrange a Development Compliance Inspection.
INFRASTRUCTURE CHARGES
4. This Development Permit will trigger an “Infrastructure Charge Notice” to be issued in
accordance with Council’s “Charges Resolution” made pursuant to the planning legislation
and regulations current at the time of issue.
Page 9 of 13
Document Set ID: 24010585
Version: 4, Version Date: 08/08/2025
Page 10
ENGINEERING
General Advisory Notes
5. Council has undertaken an audit check of the Operational Works drawings in relations to the
proposed works. A detailed check of the calculations and drawings has not been undertaken,
as they have been certified by a RPEQ. The RPEQ bears full responsibility for all aspects
of the engineering design. Council reserves the right to require further amendments and/or
additions at a later date should design errors become apparent.
6. Council reserves the right to call up any performance bond held or levy charges against the
property, should emergency works be required to be undertaken by Council to make the site
safe due to inactivity on the development site for extended periods of time.
7. Should any changes or modifications to the approved plans be required as a result of
construction constraints, a “Request to change an existing approval” under the Sustainable
Planning Act 2009 must be made. Amended plans clearly indicating the changes must be
lodged with this application along with the appropriate fees.
Prestart
8. Contact Council on 5329 6245 to arrange a prestart or an inspection giving a minimum of 5
business day’s notice of preferred inspection time.
9. It should be noted prior to arranging a pre-start meeting the Right of Appeal Period of 20
business days should have been passed or the applicant has have confirmed by a letter or
an email that he/she has accepted the conditions of Decision Notice and waived his/her
appeal right.
10. If Council officers are required to undertake additional inspections of the same works, a
reinspection fee will be applicable in accordance with Council’s Fees and Charges register
applicable at the time.
Environmental Advisory Notes
11. The Environmental Protection Act 1994 states that a person must not carry out any activity
that causes, or is likely to cause, environmental harm unless the person takes all reasonable
and practicable measures to prevent or minimise the harm. Environmental harm includes
environmental nuisance. In this regard persons and entities, involved in the civil, earthworks,
construction and landscaping phases of this development are to adhere to their ‘general
environmental duty’ to minimise the risk of causing environmental harm.
Erosion and Sediment Control
12. Accepted best practice standards include:
a. Best Practice Erosion and Sediment Control, International Erosion Control Association
(2008).
Page 10 of 13
Document Set ID: 24010585
Version: 4, Version Date: 08/08/2025
Page 11
13. As a general rule, a site is determined to have achieved effective short-term stabilisation if
at the time of the plan sealing inspection:
a. Methods of stabilisation are:
• appropriate for slopes and slope lengths; and
• are consistent with best practice environmental management practices such as
in the Manual for Erosion and Sediment Control or the IECA Manual; and
b. Stormwater runoff from the site is not currently, and is not likely to result in visible
evidence of sedimentation or erosion, or lead to water contamination.
If at the time of request for plan sealing, the method of short-term stabilisation has not
achieved a level of stability that Council's Officers believe will have a high probability
of achieving long term stability (i.e. until house construction has occurred on all lots),
Council Officers may take the following matters into consideration in determining
whether the site is capable of achieving medium to long-term stability:
• evidence that the site has been effectively stabilised in the short term;
• evidence that soil has been adequately ameliorated;
• evidence that seed of annual and perennial grass species has been applied at
an adequate rate; and
• that grass seed has germinated at a density that is likely to achieve an effective
grass cover.
For example, while hydromulch can provide an immediate and effective stabilising
cover to soils, the protective cover can be relatively short-lived if vegetation fails to
establish before the thin layer of mulch decomposes. So if hydromulch is selected as
the method of temporary short term stabilisation, Council Officers will seek to confirm
that perennial as well as annual grasses are well established at the time of plan sealing
to reduce the risk of instability of the site in the medium to long term. As a general rule,
hydromulch will only be accepted as a “patch” fix and should comprise no more than
20% of the exposed site area due to the high risk of failure. Due to the requirement to
progressively stabilise exposed areas, it is not envisioned that this will present any
difficulties for an appropriately managed and compliant site.
Building and Construction Industry (Portable Long Service Leave) Levy
14. Where it is required, the QLeave levy should be paid prior to arranging the prestart meeting.
The details that the Levy has been paid must be submitted to Council prior to the prestart.
QLeave contact: 1800 803 481 (free call) or (07) 3212 6855.
7. PROPERTY NOTES
Not applicable.
8. VARIATION APPROVAL DETAILS
Not applicable.
9. FURTHER DEVELOPMENT PERMITS REQUIRED
Type of Development Permit Required Subject of the required Development Permit
Development Permit for Building Works All Building Works
10. SUBMISSIONS
Not appliable.
Page 11 of 13
Document Set ID: 24010585
Version: 4, Version Date: 08/08/2025
Page 12
11. RIGHTS OF APPEAL
You are entitled to appeal against this decision. A copy of the relevant appeal provisions from the
Planning Act 2016 is attached.
12. OTHER DETAILS
If you wish to obtain more information about the decision, electronic copies are available on line at
www.noosa.qld.gov.au or at Council Offices.
Yours faithfully,
Tiani Bird
Development Planner
Enc: Appeal Rights
Infrastructure Charge Notice
Approved Plans/Documents
DECISION NOTICE HISTORY
• Original Decision Notice – 18 May 2018.
• Decision Notice – Minor – MCU18/0008.01 & OPW18/0013.01 –
07 August 2025, with an amendment to condition 2.
Page 12 of 13
Document Set ID: 24010585
Version: 4, Version Date: 08/08/2025
Page 13
Appeal Rights
PLANNING ACT 2016 & PLANNING REGULATION 2017
Chapter 6 Dispute resolution (3) The appellant or, for an appeal to a tribunal, the registrar must,
within the service period, give a copy of the notice of appeal to –
Part 1 Appeal rights
(a) the respondent for the appeal; and
229 Appeals to tribunal or P&E Court
(b) each co-respondent for the appeal; and
(1) Schedule 1 of the Planning Act 2016 states –
(c) for an appeal about a development application under schedule
(a) Matters that may be appealed to –
1, table 1, item 1 – each principal submitter for the
(i) either a tribunal or the P&E Court; or development application; and
(ii) only a tribunal; or (d) for and appeal about a change application under schedule 1,
table 1, item 2 – each principal submitter for the change
(iii) only the P&E Court; and
application; and
(b) The person-
(e) each person who may elect to become a co-respondent for the
(i) who may appeal a matter (the appellant); and appeal, other than an eligible submitter who is not a principal
submitter in an appeal under paragraph (c) or (d); and
(ii) who is a respondent in an appeal of the matter; and
(f) for an appeal to the P&E Court – the chief executive; and
(iii) who is a co-respondent in an appeal of the matter; and
(g) for an appeal to a tribunal under another Act – any other
(iv) who may elect to be a co-respondent in an appeal of the
person who the registrar considers appropriate.
matter.
(4) The service period is –
(2) An appellant may start an appeal within the appeal period.
(a) if a submitter or advice agency started the appeal in the P&E
(3) The appeal period is –
Court – 2 business days after the appeal has started; or
(a) for an appeal by a building advisory agency – 10 business
(b) otherwise – 10 business days after the appeal is started.
days after a decision notice for the decision is given to the
agency; or (5) A notice of appeal given to a person who may elect to be a co-
respondent must state the effect of subsection (6).
(b) for an appeal against a deemed refusal – at any time after the
deemed refusal happens; or (6) A person elects to be a co-respondent by filing a notice of election,
in the approved form, within 10 business days after the notice of
(c) for an appeal against a decision of the Minister, under chapter
appeal is given to the person.
7, part 4, to register premises or to renew the registration of
premises – 20 business days after a notice us published under 231 Other appeals
section 269(3)(a) or (4); or
(1) Subject to this chapter, schedule 1 and the P&E Court Act, unless
(d) for an appeal against an infrastructure charges notice – 20 the Supreme Court decides a decision or other matter under this
business days after the infrastructure charges notice is given Act is affected by jurisdictional error, the decision or matter is non-
to the person; or appealable.
(e) for an appeal about a deemed approval of a development (2) The Judicial Review Act 1991, part 5 applies to the decision or
application for which a decision notice has not been given – matter to the extent it is affected by jurisdictional error.
30 business days after the applicant gives the deemed
(3) A person who, but for subsection (1) could have made an
approval notice to the assessment manager; or
application under the Judicial Review Act 1991 in relation to the
(f) for any other appeal – 20 business days after a notice of the decision or matter, may apply under part 4 of that Act for a
decision for the matter, including an enforcement notice, is statement of reasons in relation to the decision or matter.
given to the person.
(4) In this section –
Note – decision includes-
See the P&E Court Act for the court’s power to extend the appeal
(a) conduct engaged in for the purpose of making a decision; and
period.
(b) other conduct that relates to the making of a decision; and
(4) Each respondent and co-respondent for an appeal may be heard
in the appeal. (c) the making of a decision or failure to make a decision; and
(5) If an appeal is only about a referral agency’s response, the (d) a purported decision; and
assessment manager may apply to the tribunal or P&E Court to
(e) a deemed refusal.
withdraw from the appeal.
non-appealable, for a decision or matter, means the decision or
(6) To remove any doubt. It is declared that an appeal against an
matter-
infrastructure charges notice must not be about-
(a) is final and conclusive; and
(a) the adopted charge itself; or
(b) may not be challenged, appealed against, reviewed, quashed,
(b) for a decision about an offset or refund-
set aside or called into question in any other way under the
(i) the establishment cost of trunk infrastructure identified in Judicial Review Act 1991 or otherwise, whether by the
a LGIP; or Supreme Court, another court, a tribunal or another entity; and
(ii) the cost of infrastructure decided using the method (c) is not subject to any declaratory, injunctive or other order of
included in the local government’s charges resolution. the Supreme Court, another court, a tribunal or another entity
on any ground.
230 Notice of appeal
232 Rules of the P&E Court
(1) An appellant starts an appeal by lodging, with the registrar of the
tribunal or P&E Court, a notice of appeal that- (1) A person who is appealing to the P&E Court must comply with the
rules of the court that apply to the appeal.
(a) is in the approved form; and
(b) succinctly states the grounds of the appeal. (2) However, the P&E Court may hear and decide an appeal even if
the person has not complied with the rules of the P&E Court
(2) The notice of appeal must be accompanied by the required fee.
Page 13 of 13
Document Set ID: 24010585
Version: 4, Version Date: 08/08/2025
Used in these records
Minor Change Existing Approval - MCU18 0008 01 & OPW18 0013 01 (As Published).pdfRelated documentApplication case desk ↗
About this file
- File size
- 181 KB (small file)
- File type
No other editions are linked here.