                        Note *If a demolition contractor is undertaking works, then the Waste Management table
                        is to be completed by the demolition contractor.
                 WASTE
                 40.    The developer must provide waste storage and disposal facilities in accordance with
                        Planning Scheme Policy No. 9 "Waste Management Multi-Dwellings and Commercial
                        and Industrial Premises". The facilities must include an external impervious area
                        correctly sized for all refuse and recycling containers and suitably screened from public
                        places and neighbouring properties. A bin wash area is required with a cold-water tap,
                        hose and drain outlet connected to sewer, via a bucket trap. The drain outlet must be
                        designed to prevent storm water entry to the sewerage system. This can be achieved
                        with a nib wall 50mm high and up to 700mm x 700mm wide (max 0.5m2) , or alternatively
                        the waste area can be roofed, or any other design approved by Council.
                 41.    Refuse containers must be provided in accordance with the requirements of the
                        Environmental Protection (Interim Waste) Regulation 1996 and (Waste Management)
                        Regulation 2000, for the storage and collection of refuse.
                 42.    Bins must be provided throughout the site to reduce littering. All bins provided must be
                        for refuse and recycling and be decanted into the bulk bins by the site operators.
                 ENGINEERING
                 Site Specific Conditions
                 43.    The proposed flood barrier must be of a design that is activated by the rising flood levels
                        and the associated hydraulic differential to raise and lower the barrier. The barrier must
                        not require a power supply or human intervention. The barrier must be maintained by
                        the property owner in accordance with the manufacturer’s specifications. The works
                        must be undertaken in accordance with an Operational Works approval and must
                        include in particular:
                        a.      Certification from a Registered Professional Engineer of Queensland (RPEQ) that
                                states that the design of the barrier is suitable for its intended use.
                 44.    The development must include an internal stairwell connecting the basement level to the
                        upper floor. The stairwell must be located and constructed to provide an escape route
                        for people to evacuate the basement in the event the barrier and/or pump system fails.
                        Plans submitted as part of any subsequent operational works and building permit must
                        clearly indicate the stairwell.
                        External Works
                 45.    Mary Street must be upgraded for the length of its frontage to the subject site. The works
                        must be generally in accordance with drawing number 17699-SK100 Revision A
                        prepared by TOD Engineers and Project Managers dated 17 August 2018. The works
                        must be undertaken in accordance with an Operational Works approval and must
                        include in particular:
                        a.      construction of new kerb and channelling offset 7.5m (3.5m lane and 4m of cycle
                                lane/parallel parking) from the northern side of the existing landscaped median;
                        b.      suitable transitions from the new kerb line to join with the existing kerb at the
                                western and eastern end;
                        c.      landscaping of the verge area;
                        d.      construction of a pedestrian footpath in accordance with the conditions of this
                                Decision Notice;




                                                                                                         Page 8 of 15
Document Set ID: 22778276
Version: 6, Version Date: 24/01/2024

Used in these records

About this file

File size
210 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

SUPERSEDED - Council Meeting Decision - Other Change - MCU18 0102 02 [As Published].pdf · 210 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.