Attachment C - 6.3.2 Medium Density Residential Zone Code · MCU20/0071
Earthworks and drainage Table 6.3.1.3 Criteria for assessment (part)
Performance Outcomes Acceptable Outcomes Compliance
Earthworks and drainage
PO23 AO23 As detailed in the accompanying
Filling and excavation for Filling and excavation for operational works is civil engineering drawings, the
operational works do not directly, designed and constructed to ensure overland flow proposed development
demonstrates compliance with the
indirectly or cumulatively cause and/or flooding is not worsened, impeded, or
requirements of AO23. This will be
adverse impacts external to the otherwise diverted to adversely affect other subject to detailed review at the
development site by: properties or downstream environments. OPW stage.
(a) causing ponding of water on the
site or nearby land;
(b) increasing flooding, which
adversely affects the safety
or use of any land upstream
or downstream; or
(c) adversely affecting the flow of
water in any overland flow
path.
NOOSA PLAN 2020 Page 12 of
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Attachment C - 6.3.2 Medium Density Residential Zone Code.pdfRelated documentApplication case desk ↗
About this file
- File size
- 825 KB (small file)
- File type
No other editions are linked here.