 “Adamson Town Planning, specialising in providing higher order town planning
 advice”



d) power supply; and
e) telecommunications;

The proposed development will be required to supply all infrastructure necessary to service the
development. The applicant is currently having discussions with Unitywater about the water supply
and sewerage infrastructure being required to service the development.

It is proposed to provide full detail design of the stormwater drainage, power and telecommunications
infrastructure with the subsequent applications for operational works.

Electricity supply infrastructure
O18 Uses and works maintain a safe distance from electrical infrastructure including substations,
overhead power lines, power poles and transformers.

The subject land is constrained by an existing overland power supply line running along the eastern
boundary of Lot 3 within Easement D (refer Attachment 1). It is not expected that this infrastructure
will have any bearing on the development of proposed Lot 2, given the easement is already in place
and the application is to be referred to Energex.

O19 Stormwater run-off is managed so as not to cause any adverse impacts on the built or natural
environment including changes in quality, quantity or location of stormwater discharges.

Details of the how the stormwater run-off for the development is to be provided at the operational
works stage. Having regard to the nature of the development, the fall of the land towards Eenie Creek,
all stormwater drainage will be treated and managed before being discharged offsite.

O21 Land development responds to the distinctive landscape character of the site by utilising the natural
features of the site, which include –
a) watercourses and drainage lines;
b) significant trees;
c) understorey vegetation;
d) rock outcrops; and
e) views.

O22 Native vegetation, including individual mature trees are retained, protected, maintained and
supplemented, with particular consideration given to—
a) roadsides;
b) the amenity of adjoining land uses; and
c) the protection of environmentally sensitive areas.

O28 The natural environmental and cultural values of land in the Open Space Conservation Zone are
not adversely affected by subdivision, and land in freehold tenure in this zone is not subdivided.

O29 Lands with high biodiversity values which warrant conservation status are formally protected for
the long term.




18028 – Stockwell Development Group Pty Ltd                                       Page 18
Log in to download the original file

Town Planning Report - 22 November 2018 - Final.pdf · 1.7 MB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.