8. CONCLUSIONS AND RECOMMENDATIONS

The  following is a summary of the conclusions and recommendations in regard                         to the     geotechnical
investigation for the proposed development Noosa on Weyba.

However, the preceding sections of this report should be read for a full description of the conclusions and
recommendations.


 1.   The subsurface conditions at the site generally consisted of a layer of either loose sands or soft to firm

      clay underlain by stiff or better clays. Weathered rock was encountered in some of the boreholes.

 2.   The site preparation work should generally be carried out in accordance with AS3798-2007 ’Guidelines
      on Earthworks for Commercial and Residential            Developments’. A indicative stripping depth of 0.1 m was
      obtained from the fieldwork results.


 3.   Based    on   the   existing   natural soil   profile, the site may   be classified Class ’P’ in accordance with
      AS2870-2011 ’Residential Slabs and Footings’ due to soft/loose soils across the site.


 4.   It is recommended that either high or deep level footings may be appropriate depending on the type of
      structure.     Recommended          bearing capacity parameters         to   allow the   proportioning    of   footings,
      depending on the applied load, are included in Section 5.2.

 5.   Effluent disposal characteristics are provided in Section 5.3.



 6.   The relevant action criteria level has been exceeded and therefore indicates that a detailed acid sulfate

      management plan will be required.                Once the nature and         area   of disturbance is finalised, the

      requirement for further sampling and testing can be determined and an acid sulphate management
      plan completed including liming rates needed to neutralise the disturbed material.


Yours faithfully




~
Robert Harrington
                                                                7~David Stirling
Geotechnical Engineer                                             Senior Geotechnical Engineer
For Cardno Bowler




Prepared for Cardno (Old)                                                                                             Page 23

Used in these records

About this file

File size
49.3 MB (very large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Part 6 of 37 Appendix 3 - Geotechnical Assessment MCU12_0208.pdf · 49.3 MB (very large file)

The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.