Council archive · source document
Delegated Report - Code - Planning - RAL26 0023 (As Published) · RAL26/0023
2. DECISION DETAILS
Council decided to issue the following type of approval:
• Development Permit for a Reconfiguring a Lot - Boundary Realignment (2 lots into 2 lots).
3. CURRENCY PERIOD OF APPROVAL
The currency period for this development approval is stated in the conditions below.
4. ASSESSMENT MANAGER CONDITIONS
PLANNING
When Conditions Must Be Complied With
1. Unless otherwise stated, all works required by the conditions of this Decision Notice must be
completed prior to submission of the subdivision plan to Council for compliance assessment.
Currency Period
2. This development approval lapses if the requirements of the conditions have not been
completed and an application for plan seal is not lodged with Council by 25 September 2030,
unless an application to extend the currency period is approved by Council.
Approved Plans
3. Development authorised by this approval must be undertaken generally in accordance with
the Approved Plans listed in the table below.
Plan No. Rev. Plan/Document Name Date
261149_001_PROP A Proposed Boundary Realignment – Lot 2 on 20/08/2026
SP269273 & Lot 1 RP184583
4. The development must be undertaken and operated in a manner that causes no detrimental
effect upon the amenity of the neighbourhood by reason of the creation of excessive noise,
lighting nuisance or other emissions.
Boundary Encroachments
5. Certification must be submitted to Council from a Registered Cadastral Surveyor (Qld) which
certifies that:
a. all utility services and connections (e.g., electricity, telecommunications, water,
sewerage) are wholly located within the lot they serve or alternatively included within
an easement;
b. all existing crossovers and driveways, front and are wholly located within the lot they
serve or alternatively included within an easement;
c. all existing effluent disposal areas are wholly located within the lot they serve and
comply with the boundary setback requirements of the Plumbing and Drainage Act
2002 and associated codes and requirements;
d. all dams (including ponded water, dam walls and associated spillway structures) are
wholly located within the boundaries of a single lot; and
e. all retaining walls and structures are fully contained within the lot they retain.
Services
6. Reticulated electricity and telecommunication services must be provided to each lot in
accordance with the standards and requirements of the relevant service provider.
Page 6 of 8
Document Set ID: 25121836
Version: 4, Version Date: 25/09/2026
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Delegated Report - Code - Planning - RAL26 0023 (As Published).pdfRelated documentApplication case desk ↗
About this file
- File size
- 2.3 MB (large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take up to a minute.