Activities generally excluded from the defined TPZ include the following but not limited
to:

      a)   re-positioning or removal of the tree protection materials at any time during the
           construction work unless approval has been obtained by the Supervising Arborist.
           The tree protection materials will only be removed once these works have been
           fully completed;

      b)   any construction activities within the fenced TPZ which may have any harmful
           effect on the protected tree;

      c)   compaction occurring within the TPZ;

      d)   harmful activities outside of the TPZ’s e.g. soil erosion, radiant heat from
           machinery exhausts and polluting agents draining into the protected area;

      e)   machine excavation including trenching;

      f)   excavation for silt fencing;

      g)   cultivation;

      h)   storage;

      i)   preparation of chemicals, including preparation of cement products, including
           outside of the TPZ where polluting agents may drain into the protected area;

      j)   parking of vehicles and plant;

      k)   refuelling;

      l)   dumping of waste, including outside of the TPZ where polluting agents may drain
           into the protected area;

      m) wash down and cleaning of equipment, including outside of the TPZ where polluting
           agents may drain into the protected area;

      n)   placement of fill;

      o)   lighting of fires;

      p)   soil level changes;

      q)   soil compaction activities

      r)   temporary or permanent installation of utilities and signs;

      s)   physical damage to the tree



Note: The tree protection materials will not be re-positioned at any time during the construction work unless approval
has been obtained by the Treescience Supervising Project Arborist. Furthermore, the tree protection materials will only
be removed once these works have been fully completed. Entry into the fenced TPZ areas by persons, vehicles or
machinery is not permitted without consent from Treescience and in consultation with the relevant representatives.
                                                                                                                          Page30




PAR: V2
©Treescience Pty Ltd –uncontrolled when printed
Log in to download the original file

K - Preliminary Arborist Report (29.08.2019).pdf · 4.4 MB (large file)

The download may take up to a minute.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.