3. Noosa Project Restoration Plan V12
Attached to the e-mail Noosa Oyster Project _ Construction and Environmental Management Plan (CEMP).
Attached to the e-mail DA Application - Noosa Oyster Project (1 of 3).
This document appears to be plans or drawings. Its page text below holds only the words printed on the drawings, without the drawings themselves, so it may be jumbled or hard to follow. To see the plans as drawn, choose Original above or download the file (both need you to log in).
Log in to see the plans as drawn o Deploy substrate down current of the seagrass bed (e.g. on a falling tide for seagrasses located
upstream of the works), or within an hour of high or low tide (slack water).
o Ensuring silt curtains do not interact with marine plants and are deployed for the absolute
minimum possible soak time required to achieve the rock deployment at the site.
o Constant monitoring of the silt curtains to ensure they to not move and interact with marine
plants, impede fish passage or impose unreasonable imposition on other waterway users.
o Review substrate handling protocols and enhance the substrate cleaning/preparation efforts
until plumes are minimised.
o Review construction operations procedures and amend as required to minimise potential for
impacts.
o Consider implementing additional operational measures.
o Inspect the seagrass beds to determine if there is evidence of sediment smothering compared
to pre-works inspection.
o Report any impacts on seagrass to authorities as per permit conditions.
6.5 Load out site management
The proposed load out site is at the western end of Hilton Esplanade, Noosaville (figure 6.5). The load
out site is configured in two sections leaving sufficient space for recreational boaters and commercial
companies to access the shoreline (Figure 6.5b). The 15.4m long exclusion line between the two
sections is to separate the movement of rock between the two sections from boaters using the
shoreline. This section will be managed by the contractor using traffic cones, NOT fencing. The cones
will be removed when there is no movement of material between the two sections.
57
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLarge file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.