3. Noosa Project Restoration Plan V12
Attached to the e-mail Noosa Oyster Project _ Construction and Environmental Management Plan (CEMP).
Attached to the e-mail DA Application - Noosa Oyster Project (1 of 3).
This document appears to be plans or drawings. Its page text below holds only the words printed on the drawings, without the drawings themselves, so it may be jumbled or hard to follow. To see the plans as drawn, choose Original above or download the file (both need you to log in).
Log in to see the plans as drawnEngineering design by coastal specialist – Final oyster reef patch layout is to be confirmed by the
certifying coastal engineer post construction. For Phase 1 sites, this is undertaken by International
Coastal Management. For Phase 2 sites, this is a requirement prior to construction (refer Drawing
NROR-2021-02 note 1.6).
Erosion monitoring and mitigation
The restoration sites, as well as shoreline 100m upstream and downstream of the sites, will be
monitored visually every 6 months to check for signs of exacerbated shoreline erosion. Every 12
months, photographs will be used to compare changes in the shoreline shape. Where significant
erosion is detected and is directly attributable to the presence of the restoration works, remedial
actions will be undertaken in consultation with authorities, such as the modification of the height or
form of related oyster reef patches to reduce the erosion hazard (see Section 8.6 Contingency plan).
8.5 Complaints management
TNC has developed a self-explanatory project brochure and answers to Frequently Asked Questions
about the project. TNC has also published and distributed site maps and will disseminate information
about the construction and most construction management phase via mailouts. These are also made
widely available via the TNC website - see https://www.natureaustralia.org.au/what-we-do/our-
priorities/oceans/ocean-stories/noosa-river/noosa-faqs/ and will be promoted through project
partners and authorities to help spread information about the project and thus help to manage
inquiries.
TNC, as the project lead, will manage the response to all complaints in liaison with relevant authorities
as well as the contracted construction company. The rating and intended responses to complaints is
given in Table 8.5. The complaints record keeping system is as per Table 8.5a.
Complaints and responses will be included, in general terms, in annual reports. Relevant agencies may
access the detail of complaints, as per tables.
Table 8.5: Complaint rating and response
Complaint Nature Response Timeframe
severity
Low General concerns and Phone call and/or email Within 48 hours
questions about project response giving
activities, timeframes or response or source of
details. information.
General inquires not directly Refer to appropriate
related to the project agency
Medium Concerns related to specific Phone call and/or Within 24 hours
project actions and impact on formal written response
visual amenity or environment, depending on nature.
as they occur
Consultation with
Specific complaints about the relevant agencies
project in general regarding the response,
if required.
72
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLarge file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.