                                                                   Attachment 1 to Item 2
                                                                   General Committee Meeting Agenda
The Nature Conservancy                                             14 January 2019




                                              PROPOSAL

                             Noosa Council and The Nature Conservancy

                                       Noosa River Partnership

                                                    &

                                        Bring Back the Fish
                                Oyster Reef Restoration (Phase II and III)

                                              2019 - 2021


                                      The Nature Conservancy




   Noosa River Partnership                                                                Page | 1
Log in to download the original file

2019-01-14 General Committee Agenda - Attachment 1 to Item 2 - Noosa River Partnership Proposal(PDF, 1MB).pdf · 1.1 MB (small file)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

Full text of the other 18 sections

Section 2

The Nature Conservancy




TABLE OF CONTENTS

1.0. EXECUTIVE SUMMARY ........................................................................................................................... 3
2.0. NOOSA RIVER PARTNERSHIP (initial scope) ......................................................................................... 5
3.0. OYSTER RESTORATION PROJECT SCOPE .......................................................................................... 8
4.0. PROJECT STAGES AND DELIVERABLES ............................................................................................11
5.0. RESTORATION APPROACH ..................................................................................................................13
6.0. FUNDING STRATEGY ............................................................................................................................17
7.0. LOCAL CONTENT AND PROCUREMENT .............................................................................................17
8.0. TRADITIONAL OWNER ENGAGMENT ..................................................................................................18
10.0 PROJECT LEAD, PARTNERS AND STAKEHOLDER ROLES ...............................................................18
11.0 SUPPORTING DOCUMENTS ..................................................................................................................19




     Noosa River Partnership                                                                                                             Page | 2

Section 3

The Nature Conservancy


1.0.   EXECUTIVE SUMMARY
Noosa River Partnership
This project proposes to establish an innovative and regionally significant Noosa River
Partnership, between the Noosa Council and the global conservation organization The
Nature Conservancy, which seeks to improve the health and resilience of the Noosa River
and the industries and local communities that rely on its long-term wellbeing.
The focus of the Public-Private Partnership is to:
   •   Capitalize on the expertise of The Nature Conservancy’s global networks and
       experience (through knowledge brokering, mentoring, study tours and access to
       subject matter experts) to improve River management and strengthen the long-term
       social, environmental and economic health and resilience of the River;

   •   Demonstrate a leading example of a replicable, environmentally focused, Public-
       Private Partnership that achieves superior outcomes for the environment and local
       communities compared to existing river management models; and,

   •   Increase government (State and Federal), private, industry and community support
       for restoration and conservation-focused activities that improve the long-term social,
       economic and environmental health and resilience of the River.
The Partnership will initially prioritize the restoration of oyster reefs in the lower estuary (as
described below) as the first activity, with other potential activities including:
   •   General strategic support/advice for planning, management and evaluation
       associated with the new Noosa River Plan and other initiatives and projects
       associated with the river system;
   •   Coordination of research required to inform the delivery of the implementation of the
       Noosa River Plan; and
   •   Critical evaluation and potential reform of current and future management activities
       (e.g. commercial and recreational fishing, recreation, tourism, wetland restoration,
       sediment and nutrient inflows, community engagement).
The partnership will commence from July 2019 and will run for at least three years with the
outcomes of the first three years of the partnership to be reviewed in July 2022. The total
operating budget is $2.4M, inclusive of $1.2M from The Nature Conservancy and $1.2M
from Noosa Council with the expectation that further funding will be raised from a variety of
other sources to support on ground management activities. $1.36M of the available $2.4M
will be quarantined to support the next phase of oyster reef restoration as described in
Section 3 in this proposal.
The terms of reference for the partnership will be finalized between January - June 2019,
culminating in a Memorandum of Understanding and grant agreement between The Nature
Conservancy and Noosa Council executed by July 2019.
Oyster reef restoration
Oyster reefs were once common throughout the lower sections of the Noosa River estuary,
particularly around Tewantin but have been lost over the last century, primarily as a result
of historical overfishing and physical and ecological changes to the estuary. The project will
help deliver community aspirations identified in the Noosa River Plan (Noosa Council, 2019)
particularly objectives relating to upholding and improving the ecological resilience and fish
life within the lower estuary by restoring oyster reefs created by the native rock oyster,
Saccostrea glomera.

   Noosa River Partnership                                                                 Page | 3

Section 4

The Nature Conservancy


The restoration project will be delivered through a public-private partnership led by The
Nature Conservancy and Noosa Council, and include Kabi Kabi (Gubbi Gubbi), Noosa Parks
Association and Noosa Biosphere Reserve Foundation. Key stakeholders include:
Queensland Government, Healthy Land and Water, The Thomas Foundation, local
universities, fishing and aquaculture industries, restaurants and community groups.
including State Government and private businesses, individuals, trusts and foundations. The
Project will commence in July 2019 and operate until at least 2021 when the need for further
restoration will be assessed.
Oyster reef restoration methodology will follow standards aligned with best practice oyster
restoration and the Society for Ecological Restoration global guidelines. Deliverables
associated with the project include: 1. Planning and governance, 2. Reef restoration, 3.
Monitoring, evaluation and reporting and 4. Community engagement and volunteering. The
project will follow a staged approach to restoration: Phase I – feasibility which has been
completed by University of Sunshine Coast, Phase II- optimal design (2019-2020) which
seeks to determine the optimal design, locations and most cost effective method of reef
restoration and Phase III- full restoration (2020-2021) which seeks to construct reefs at all
feasible locations identified during Phase I and II. This phased, timebound approach will
reduce ecological and financial risks through the application of an adaptive management
framework.
Project outcomes include: The restoration of a threatened ecosystem (shellfish reefs) and
associated increases in local marine biodiversity and recreationally important fish species
and increased community engagement, volunteering and environmental stewardship within
the Noosa community.




   Noosa River Partnership                                                            Page | 4

Section 5

The Nature Conservancy


2.0.   NOOSA RIVER PARTNERSHIP (initial scope)


   2.1. Recognition of prior collaboration and rationale for Noosa River partnership

Over the last four years, Noosa Council and The Nature Conservancy have worked
together to build a deeper understanding of the environmental significance and long-term
sustainable management options for the Noosa River. This has included:

    1. Noosa River Expert Workshop, Powerhouse Museum, 2014
A two day workshop, hosted by The Nature Conservancy on behalf of The Thomas
Foundation and Noosa Parks Association, comprising 12 academic and NGO estuary
scientists. The workshop identified 14 conservation activites that could lead to a healthier
Noosa River, with oyster reef restoration listed as a priority action in addition to prawn
restocking and Kin Kin sediment management. These activites (including further scoping
studies) were later jointly funded by Noosa Council.

   2. TNC Oyster Restoration Scoping Study, 2015
The Nature Conservancy and Ecological Service Professionals Pty on behalf of Noosa
Council and others undertook a short, five month ecological assessment to quantify oyster
densities across 11 intertidal and subtidal sites within the estuary. The study confirmed
high densities of oyster recruitment particularly around Weyba Creek, the main channel
around Tewantin, and in the narrow channel between Goat Island and Noosa North Shore.
The project recommended installing a number of pilot reefs for further assessment.

   3. University of Queensland Historical Ecology of the Noosa Estuary fisheries, 2015
Ruth Thurston from the University of Queensland undertook a historical ecology study on
behalf of The Nature Conservancy and Noosa Council in the Noosa River estuary to
develop an understanding of historical fisheries productivity, including oysters. The study
confirmed oyster reefs used to exist in the estuary and were commercial harvested in the
early 1900s. Fish populations were also significantly larger in the past than they are today.

    4. University of Sunshine Coast, Bring Back the Fish, 2017-2019
A three year study which has installed a series of reef units consisting of coir bags filled
with oyster shell (pilot reefs) at 15 sites across the estuary. The project will assess the
structural integrity, oyster recruitment, fish and invertebrate community assemblages and
human interactions with the reefs. This project will collect important ecological information
that will support the final design and implementation of reef restoration in Phases II and III
of this Project (see 6.1. below for more information on project phases). The initial concept
was developed by The Nature Conservancy and University of Sunshine Coast and is
partially funded by Noosa Council.

   5. Review of Bring Back the Fish Project, 2018

In February 2018, The Nature Conservancy and several independent academics provided
a review of the Bring Back the Fish project (including a review of the Prawn Study, Oyster
Restoration and Keep it in Kin Kin) and provided a number of strategic recommendations
to Noosa Council, Noosa Biosphere Reserve Foundation and Noosa Parks Association
associated with their continuation.




   Noosa River Partnership                                                              Page | 5

Section 6

The Nature Conservancy


   6. Noosa River Plan, 2019
The completion of the Noosa River Plan by Noosa Council in early 2019 will identify
current and future threats and management interventions to abate identified threats within
the Noosa River estuary. The Plan will identify the strategic alignment of oyster reef
restoration to the long-term health and resilience of the Noosa River estuary. TNC
provided comments on the initial draft of the plan.

Noosa Council and The Nature Conservancy in addition to other organizations with an
interest in the River’s sustainability (including Noosa Parks Association, The Thomas
Foundation and Noosa Biosphere Reserve Foundation), through a series of dialogue and
presentations to Council Executive Committee, have recognized the strategic priorities of
both organizations and of others would be more effectively served through a formal public-
private partnership, rather than on an individual project basis. This agreement has led to
the development of this proposal and rationale for establishing the partnership.


2.2. Partnership scope
The Partnership will initially prioritize the restoration of oyster reefs in the lower estuary (as
described in the section below) and will also include support for other potential activities
including:
   •   Strategic support for planning, management and evaluation associated with the new
       Noosa River Plan;
   •   Coordination of research required to inform the delivery of the Noosa River Plan and
       other initiatives and projects associated with the Noosa River systems; and
   •   Critical evaluation and potential reform of current and future management activities
       (e.g. commercial and recreational fishing, recreation, tourism, wetland restoration,
       sediment and nutrient inflows, community engagement).

Engagement could occur through:

       •   Access to TNC subject matter experts (particularly in conservation planning,
           fisheries, aquaculture, restoration, community engagement) to provide guidance
           and advice to Council environment and river management staff
       •   Assistance with strategic planning, co-creation of management plans and
           activities and evidence-based decision analysis, particularly through the
           development of reports, workshops and mentoring
       •   Site visits and study tours to TNC projects and TNC expertise visiting

The specific terms of reference for the partnership (including deliverables and outcomes)
will be developed between Noosa Council and The Nature Conservancy between January
- June 2019. The terms of reference will form the basis for of a Memorandum of
Understanding and/or Grant Agreement between the two organizations.

To finalize the scope of the partnership, it is proposed to match the needs of Noosa
Council and the management objectives of the Noosa River Plan to The Nature
Conservancy’s global marine and coastal expertise, which includes:

   •   Marine ecosystem restoration
   •   Community conservation planning and engagement
   •   Marine protected area and marine spatial planning design and management
   •   Fisheries management
   Noosa River Partnership                                                                 Page | 6

Section 7

The Nature Conservancy


    •    Aquaculture
    •    Coastal resilience planning and adaptation
    •    Nature based adaptation and natural solutions to coastal risks

This needs and expertise analysis will occur through a joint workshop scheduled within the
first quarter of 2019.


2.3. Draft budget
Indicative resources required to deliver the Noosa River Partnership including support for
oyster reef restoration (detailed in next section) are outlined in the table below.
Resource include support for:
    •    TNC conservation staff to provide support and capacity building to Noosa Council
         Environment and River Management staff
    •    Travel costs and management associated with site visits and knowledge exchanges
    •    Management of the oyster reef restoration project for Phase II and Phase II, including
         planning, permitting and management of associated sub-contractors with
         researchers and maritime companies
    •    Construction costs associated with of Phase II oyster reef restoration
    •    Communication and media
    •    Community engagement including workshops and public presentations
A final budget will be provided with the partnership terms of reference.



                        DRAFT PROJECT COSTS                           Year 1    Year 2      Year 3     Total



 Activity #1 - Strategic planning, project planning, governance and
 support                                                              132,904     136,069   139,329    408,303
 Activity #2 – Site visits, exchanges, workshops                       52,246      52,799    53,368    158,412
 Activity #3 - Oyster restoration                                     404,438     646,999   310,860   1,362,297
 Activity #4 – Communication, community engagement and media           62,472      57,920    58,877    179,269
 Activity #5 - Project and contract management                        106,413      92,136    94,366    292,916

 Subtotal                                                             758,473     985,924   656,800   240,1197
 Noosa Council contribution                                           379,237     492,962   328,400   1,200,599
 Total Expense (GST exclusive)                                        758,473     985,924   656,800   2,401,197




    Noosa River Partnership                                                                              Page | 7

Section 8

The Nature Conservancy


3.0.     OYSTER RESTORATION PROJECT SCOPE

    3.1. Historical significance

The underwater environment of the Noosa River lower estuary was once dominated with
extensive reef ecosystems created primarily by the Australian rock oyster (Saccostrea
glomerata). These reefs provided food and habitat for many other species including
desirable fish species such as whiting, bream and snapper whilst also filtering and
removing nutrients from the water column (a single oyster can filter up to 100 L of water a
day). The reefs were largely lost in the late 1800s to early 1900s primarily as a result of
dredging (which broke up the reef complex) and overharvesting (which removed oyster
biomass) by commercial wild oyster fishers. At the peak of the wild oyster harvest industry
(1906-1907) it is estimated that 2-3 million oysters were harvest in the lower estuary each
year1.

The loss of oyster biomass likely resulted in the ecosystem collapsing, with reefs now
replaced primarily by soft (sandy and muddy) sediments. Changes to the estuary’s
physical-chemical condition, canal development and shoreline armoring have also likely
contributed to the decline of the ecosystem or inhibited its natural recovery. Today, no
oyster reefs exist in the Noosa River estuary despite the presence of individual and small
populations of rock oysters. The closest known intact reef ecosystems occur near North
Stradbroke Island in Morton Bay. Notably, a recent study has identified that the Australian
rock oyster ecosystem is the most threatened marine ecosystem in Australia, with up to
94% of the ecosystem lost throughout Australia since European settlement2.



       3.1.   Project Purpose
       The purpose of this project is to improve the ecological productivity and resilience of the
       Noosa River lower estuary, and the industries and local community that rely on its long-
       term health, by restoring oyster reef ecosystems and thereby increasing biodiversity,
       fish habitat, natural water filtration and amenity value.


       The project will support the implementation of the Noosa River Plan3 particularly
       objectives relating to upholding and improving the ecological resilience and fish life
       within the lower estuary.


       The ecological purpose, or ecosystem goal, is to re-establish a reef ecosystem
       developed by the indigenous rock oyster (Saccostrea glomerata) in the lower estuary.
       Higher levels of biodiversity and biomass, including desirable recreational and
       commercial fish species, are associated with oyster reef ecosystems (in some instances
       up to 500% greater than adjacent soft sediments). The restoration goal is to meet
       ecological community and biomass targets defined during the planning stages of the
       project and adapted from nearby reference sites.


1
  Thurston R. 2015. Historical ecology of the Noosa Estuary fisheries. Report to: Noosa Council, The Nature
Conservancy and The Thomas Foundation (available on request from TNC).
2
  Gillies et al. 2018. Australian Shellfish Ecosystems: past distribution, current status and future management. PLoS
ONE 13(2):e0190914. https://doi.org/10.1371/journal.pone.0190914
3
  Noosa River Plan, Noosa Council, 2019. Http://noosa.qld.gov.au

    Noosa River Partnership                                                                                      Page | 8

Section 9

The Nature Conservancy


    3.2.    Funding Sources
    This project is funded through a public-private partnership including:
       $1.2M from the Nature Conservancy
       $1.2M from Noosa Council
       $1.2M from various other sources yet to be secured (likely State Government,
       corporate businesses and private individuals, trusts and foundations).


The Nature Conservancy and project partners will endeavor to secure the $1.2M during the
first 18 months of the project, with resource acquisition to be led by The Nature
Conservancy’s Business Development Team (see 7.0 below). The unsecured $1.2M
component of the project will be used to support Phase III construction (see Project
Construction Phases below).

    3.3.    Project Description and workflow

This project seeks to restore an oyster reef system comprised of several individual but
connected reef patches (collective known as a reef ecosystem) throughout the lower
sections of the Noosa River estuary. The project builds on the ecological studies and trials
led by University of Sunshine Coast (2016-2018) identified as the feasibility component of
this project (i.e. Phase I, see 6.1. below).

The project workflow encompasses four work streams:


    1. Planning, governance and communication
    The first 12 months of the project will deliver activites required to effect successful
    ecosystem restoration and community engagement. These include: Development of a
    project implementation plan, project risk assessment, communications framework,
    habitat suitably modelling, community volunteering projects, reef design and
    construction briefs, permits, project governance and monitoring and evaluation reporting
    framework.


    2. Reef restoration and long-term management
    This phase of the project focuses on the procurement of materials and in water
    construction of oyster reefs. Activites associated with this phase will be outlined in the
    project implementation plan and include: preparation of tender documents and legal
    contracts for procurement of materials and reef construction by third parties, final
    preparation of reef design, locations and site management, execution of permit
    requirements and reef construction. The long-term management and tenure of
    restoration sites including the harvest of oysters and associated marine life is an
    important component of the project which should be negotiated amongst stakeholders
    prior to reef construction. This component is best led by the responsible governing
    agency and guided by TNC and stakeholders.


    3. Community engagement and volunteering


   Noosa River Partnership                                                             Page | 9

Section 10

The Nature Conservancy


    The project will establish a number of community engagement and volunteering
    opportunities, to be determined collaboratively by project stakeholders during the
    detailed planning phase of the project. These could include:
         •   Oyster shell recycling with local restaurants, oyster growers and seafood
             suppliers
         •   Oyster gardening
         •   Fish surveys
         •   Reef construction
         •   Reef monitoring including oyster settlement surveys
The concurrent delivery of community volunteering and engagement activities is an
important component of reef restoration, helping to foster a high level of support and long
term stewardship amongst the local community and estuary-dependent businesses.
Volunteering also helps to reduce costs associated with reef construction and monitoring
and strengthens community support for the Project and other related estuary management
activites. Community volunteering and engagement activites will include regular public
information nights, seminars and consultation.

    4. Monitoring, evaluation and reporting
    During the planning phase of the project a comprehensive Monitoring, Evaluation and
    Reporting framework will be developed to support the project. This includes:
       Clear articulation of the project’s goals, targets, objectives, monitoring and reporting
       methodology. Stakeholder roles and responsibilities will be defined separately in the
       Project Implementation Plan.
       Project targets are defined under five ecological and social categories, each with a
       number of associated measures:
        •    Shellfish- assessment of density, growth and survival of the ecosystem engineer,
             S. glomerata
        •    Biodiversity - assessment of increase in marine life and biomass
        •    Fish- assessment of increase in desired fish species and biomass
        •    Reef Integrity- assessment of structural features of the reef including height,
             shape and stability
        •    Social-economic- assessment of social outcomes including volunteering, job
             creation, community support.
       The project’s annual progress will be reported in digestible, community friendly
       project report cards. A more detailed technical monitoring report and annual project
       report will also be developed.




  Noosa River Partnership                                                              Page | 10

Section 11

The Nature Conservancy




4.0.        PROJECT STAGES AND DELIVERABLES


       Deliverable                     Lead          Details                                       Indicative
                                       Origination                                                 Timeline

       1.        Planning, governance and communication

       Project staffing                TNC           Hiring of       project manager and           2 months
                                                     identification of project staff responsible
                                                     for project delivery.

       Project Advisory Group          TNC           Informal advisory group chaired by TNC        6 months
       established consisting of                     and containing representatives from
       key stakeholders                              funding partners, responsible agencies
                                                     and technical advisors. Group to meet
                                                     quarterly or as determined in the TOR.

       Communication strategy          TNC           Outlines      key media opportunities,        3 months
                                                     notification protocols, key messages and
                                                     responsible persons.

       Project       Implementation    TNC           Contains detailed information relating to     9 months
       Plan                                          delivery of the project.

       Project Risk Assessment         TNC           Contains information on environmental,        9 months
                                                     social and economic project threats, risk
                                                     ratings and mitigating actions

       Habitat suitability model and   TNC           Identifies the optimal locations for          6 months
       analysis                                      restoration based on pilot studies
                                                     undertaken during feasibility in addition
                                                     to new analysis. From these analyses,
                                                     restorable bottom area targets for each
                                                     restorable site are defined.

       Identification of suitable      TNC           Identifies the project(s) most suitable for   9 months
       community                                     community          engagement          and
       engagement/volunteering                       volunteering (e.g. shell recycling, fish
       activites                                     monitoring,     reef    building,   oyster
                                                     gardening)

       2.        Reef restoration and long-term management

       Long-term               reef    Noosa         Outlines the long-term management plan        12 months
       management plan                 Council       and agency responsibilities, including
                                                     public    access,     anchoring,    oyster
                                                     resource        extraction,      signage,
                                                     compliance,      liability    and     risk
                                                     management. Requires consultation/
                                                     negotiation        with      Queensland
                                                     Government.

       Construction permits            TNC           Submission     and    procurement        of   18 months
                                                     construction and scientific permits




  Noosa River Partnership                                                                              Page | 11

Section 12

The Nature Conservancy


     Reef      design           and    TNC            Final construction designs and briefs and     24 months
     engineering                                      engineering recommendations. Includes
                                                      site management plan for construction.

     Procurement management            TNC            Procurement tenders, legal contracts          Ongoing
                                                      and bid management associated with
                                                      procurement of reef materials and reef
                                                      construction.

     Reef construction                 Contractors    Construction of reef base from materials      24 months
                                                      such as recycled shells, limestone or
                                                      indigenous rock. May also include
                                                      addition of oyster spat from hatchery if
                                                      necessary.

     5.0.     Community engagement and volunteering

     Community      volunteering       Partner        May comprise of one or more of the            Ongoing
     project(s) (TBD)                  (supported     following:    shell   recycling,  oyster      (established
                                       by TNC)        gardening, OysterWatch, fish monitoring,      by        12
                                                      oyster reef construction and monitoring.      months)
                                                      Final project(s) to be determined during
                                                      initial stakeholder meetings during
                                                      planning stage.

     Community           information   TNC            Includes public presentations and regular     Ongoing,
     sessions                                         information sessions                          regular

     Volunteer management              Partners and   Includes risk assessments, public liability   12 months
                                       TNC            and    management       protocols      for
                                                      volunteers

     4.       Monitoring, evaluation and reporting

     Monitoring, evaluation and        TNC            Provides the framework and rational for       9 months
     reporting plan                                   monitoring, evaluation and reporting

     Six monthly report cards          TNC            Provides a 2 page progress summary in         6 monthly
                                                      report card format                            from year 2

     Annual Project Report             TNC            Provides a details report on the status of    Annual
                                                      all project objectives and deliverables

     Annual            Technical       TNC            Provides a detailed report on the             Annual
     Monitoring Report                                monitoring and analysis of project
                                                      measures of success

     Annual project review             TNC            In person annual review meeting for           Annual
                                                      project funders and Project Advisory
                                                      Group members and including external
                                                      independent reviewers




  Noosa River Partnership                                                                               Page | 12

Section 13

The Nature Conservancy


5.0.      RESTORATION APPROACH

     The Nature Conservancy follows the international Society for Ecological Restoration’s
     principles and key concepts for ecological restoration4. In brief, this includes:

          1. The use of a reference ecosystem or model ecosystem which is uses to set
             ecological targets for the project, taking environmental change into account
          2. Identifying the target ecosystem’s key attributes prior to developing goals and
             objectives
          3. Focusing on creating the ecological ‘enabling conditions’ that lets nature restore
             itself
          4. Seeking ‘highest and best effort’ progression towards full recovery
          5. Drawing on all available relevant knowledge sources to inform decisions
          6. Early, genuine and active engagement with all stakeholders

In addition to the above principles, The Nature Conservancy also applies current best
practice approaches for shellfish reef restoration as outlined in: A Practitioners Guide to
Shellfish Restoration Design and Monitoring5. Importantly, our process includes principles
of adaptive management, whereby lessons learnt from prior research studies, pilot projects
and other restoration projects in Australia and the US are incorporated into the design and
monitoring of current and future restoration.

     6.1. Project Construction Phases

     The restoration or construction element of the project is split into three phases that
     allow for a review of progress, targets and lessons learnt and incorporation of these
     into subsequent construction periods (i.e. adaptive management principles). These
     phases align with the concepts of a feasibility or pilot phase (Phase I), replicable reef
     unit development (Phase II) and full restoration (Phase III).

          Phase I (2016-2018)

          Phase I of the project was largely undertaken by University of Sunshine Coast with
          support and co-funding from Noosa Council, Noosa Parks Association, The Thomas
          Foundation and Noosa Biosphere Reserve Foundation. The key objectives and
          lessons learnt from Phase I include:

                •    An understanding of oyster recruitment potential, growth and survival at 16
                     different locations in the lower estuary. This information will be used in Phase
                     II to assist with identification of priority sites and methods for restoration
                •    An understanding of state government permitting and regulatory
                     requirements required to undertake reef restoration
                •    To a lesser degree, an understanding of material use, reef stability and
                     design of reefs
                •    To a lesser degree, an understanding of community assemblages likely to be
                     associated with restored shellfish ecosystems

4
  McDonald T, Gann GD, Jonson J, and Dixon KW (2016) International standards for the practice of ecological
restoration – including principles and key concepts. Society for Ecological Restoration, Washington, D.C.
5
  Brumbaugh, R. D., Beck, M. W., Coen, L. D., Craig, L., & Hicks, P. (2006). A practitioners guide to the design & monitoring of shellfish
restoration projects: an ecosystem services approach. P. Hicks. 2006. A Practitioners' Guide to the Design and Monitoring of Shellfish
Restoration Projects: An Ecosystem Services Approach. The Nature Conservancy, Arlington, VA.

    Noosa River Partnership                                                                                                         Page | 13

Section 14

The Nature Conservancy



The project was also successful in raising awareness amongst the local community of the
need to restore oyster reefs.


       Phase II (2019-2020)

       Phase II of this project seeks to identify the most appropriate design for a replicable
       ‘reef unit’ that will be deployed during Phase III at multiple sites across the estuary.
       Specifically, the goal of Phase II is to confirm the most cost-effective and
       appropriate construction materials, reef design and deployment methods. Once
       confirmed, the most appropriate reef ‘unit’ will then be replicate at multiple locations
       across the estuary during Phase III. Phase II will occur at only one or two locations
       within the estuary and would seek to test and determine the cost-effectiveness and
       appropriate use of:

           1. Different ratios of recycled shells vs limestone or other rock materials (cost of
              deployment vs reef stability vs suitability for oysters and marine life)
           2. Seeding vs not seeding the reef base with oysters (oyster density)
           3. Using bagged vs non-bagged materials (structural integrity)
           4. Different methods of reef construction (e.g. commercial barges, community
              support)
           5. Reef design (e.g. optimal length, width and height of reef base)

The outcome of Phase II will determine the most cost effective, replicable reef unit that can
be easily deployed at multiple sites across the estuary during Phase III.

Phase III (2020-2021)

       Phase III will take the most optimal design from Phase II and replicate this at other
suitable locations across the estuary (identified through the habitat suitability modelling).
This phase is analogous to a ‘roll out’ or ‘full restoration’, where the majority of works are
carried out as a maritime construction project.

Costs required to construct Phase III are not included in the draft budget (Section 2.3) but
are anticipated to cost approximately $1.2M.




  Noosa River Partnership                                                               Page | 14

Section 15

The Nature Conservancy


    2016 - 2018                                     2020 - 2021
     PHASE I (USC)                                  PHASE III (TNC)

       Feasibility                                  Full restoration




                              2019 - 2020                                2021 - beyond
                              PHASE II (TNC)                                  PHASE IV

                             Habitat suitability                           Investigation of
                               Site selection                             other restorative
                            Optimal reef design                                actions
                             and construction


Figure 1. TNC’s phased approach to determining optimal sites and methods for restoration.



       6.2.     Critical Assumptions

Our critical Theory of Change assumptions are:

   1) That the community will advocate for and support oyster reef restoration if the
      environmental, social and economic benefits and outcomes of the project are
      clearly articulated and they are included in key decision points;

   2) That private and philanthropic investors will invest in PHASE II and PHASE III if a
      clear business and/or philanthropic (ecological, social, economic) return on
      investment proposition is presented;

   3) That partners and stakeholders will continue to support and invest in similar natural
      infrastructure projects as a result of capacity building and improved confidence after
      the completion of this project.

   4) That oyster reefs will persist and thrive if a sufficient population of native rock
      oysters is established through ecological restoration and their main threats
      managed sufficient to sustain oyster populations.




  Noosa River Partnership                                                                     Page | 15

Section 16

The Nature Conservancy


       6.3.     Assessment of Options

A mix of qualitative and quantitative assessments of different construction options are
provided in the table below:

 Option                  Benefit             Cost              Risk                   Response
 Construct               Reef                Requires          Unlikely to            Undertake
 reefs in staged         construction        multiple barge    result in              staged
 approach over           method can be       or other plant    complete reef          approach to
 two phases              improved over       equipment         failure but may        restoration.
                         time (adaptive      mobilization/     result in need to      Incorporate
                         management).        demobilization    deploy oysters         pilot project
                         Possible            costs.            over several           lessons into
                         improved oyster     Depending on      time periods.          reef design.
                         survival/           size of barge     This is still likely   Work with local
                         enhanced            required this     to be cheaper          coastal
                         biodiversity for    could be up to    ($20-50k) than         engineers to
                         reefs               an additional     multiple barge         optimize final
                         established in      $100k per         mobilization           reef design for
                         later years         deployment.       costs.                 location to
                                                                                      minimize
                                                                                      threats.
 Use recycled            Lower cost          Requires          May result in          Work with local
 shell as reef           compared to         sufficient        slumping/              coastal
 base                    using rock as       recycled shell    spreading/             engineers and
                         reef base.          material to be    smothering of          ecologists to
                         Likely results in   available,        reef base due          optimize final
                         greater reef        biosecurity       to lightweight         reef design and
                         extent and cost     protocols and     nature of              materials for
                         effectiveness       permits in        materials and          locations.
                                             place.            lower reef
                                                               profile.
 Use only                Lower cost          Requires          Recruitment is         Assess the
 natural                 compared to         sufficient        less than              need for
 recruitment as          hatchery            natural spat      required to form       hatchery
 means of                produced            recruitment and   oyster                 produced
 populating              oysters. Does       minimal           reef/sustain           oysters in
 oysters                 not require         biofouling        population             Phase II and
                         translocation       during time of                           monitor natural
                         permit or           recruitment                              recruitment
                         broodstock                                                   over time with
                         harvest.                                                     view to move
                                                                                      away from
                                                                                      hatchery
                                                                                      produced
                                                                                      oysters if
                                                                                      natural
                                                                                      recruitment
                                                                                      sufficient




  Noosa River Partnership                                                                      Page | 16

Section 17

The Nature Conservancy


The final construction design and material specifications will consider the tradeoffs
amongst the reef material, barge size, barge availably and timing of deployment (listed in
the above table) to optimize the efficient use of resources against the primary objective of
creating the maximum amount of oyster reef. This can only be completed once the full-
time Project Manager is in place, who will investigate opportunities to save costs through
local partnerships, donations and in kind support.


6.0.     FUNDING STRATEGY
The Nature Conservancy will endeavor to work with Noosa Council and other partners to
seek an additional $1.2M in investments through local and federal government and private
and philanthropic sources to fund the cost of Phase III construction. The Conservancy has
a track record of securing private and public funding for oyster reef restoration in Australia;
for instance in South Australia, The Nature Conservancy leveraged an initial $600,000 SA
State Government commitment into a $4.1M public-private partnership; and in Victoria, The
Nature Conservancy has leveraged the Victorian State Government’s $1M commitment into
a $2.5M public-private partnership.
The funding strategy and funding procurement will be led by The Nature Conservancy’s
Business Development Team.


7.0.     LOCAL CONTENT AND PROCUREMENT

The resources required to construct and monitor the reef will primarily be sourced from
local suppliers, including:

   •     Project Coordinator based locally in Noosa
   •     All rock/shells required to build the reef base sourced from nearby quarries
   •     Local trucking companies will be hired to move rock/shells from the quarry to wharf
   •     Queensland based research institutions (e.g. USC, JCU, UQ), commercial divers
         and engineering firms given priority for sub-contractor work
   •     Local oyster farmers in adjacent estuaries may be paid a fee if ongoing
         management of juvenile oysters is required
   •     All small vessels used for reef integrity checks/monitoring will be hired locally
   •     Interstate personnel to stay locally in Noosa, contributing to local economy
   •     Local plant equipment hire and maritime construction companies to be given priority
         over interstate companies if bids are otherwise similar
       The Nature Conservancy has a set of global Standard Operating Procedures which it
       must abide by for all procurement processes (provided on request). The Nature
       Conservancy will also seek to source goods and services locally where possible and
       align with the procurement policy of Noosa Council.




  Noosa River Partnership                                                              Page | 17

Section 18

The Nature Conservancy


8.0.   TRADITIONAL OWNER ENGAGMENT

PHASE I of this project had limited consultation with Kabbi Kabbi, the Traditional Owners
of the Noosa River land and waters. This project has intent to engage Kabbi Kabbi
Traditional Owners as key stakeholders from the beginning, and ideally as project partners
(as defined below). Traditional ecological knowledge will be an important source of
information to support restoration suitability modelling in addition to supporting education
activites associated with the cultural importance of oysters, oyster middens and the Noosa
River to Traditional Owners. Depending on the extent and desire for engagement by Kabbi
Kabbi, additional opportunities that support the project such as Indigenous rangers, project
support officers, aquaculture and tourism ventures will be explored.


10.0 PROJECT LEAD, PARTNERS AND STAKEHOLDER ROLES

A brief description of the project partners, roles and governance structure is provided below.
This will be finalized in the Project Plan where all parties can agreed to the project
governance structure, roles and responsibilities.


Project Lead

The Project Lead is the principle point of contact between the project partners and has the
primary responsibility and accountability for project delivery and financial spend.
Specifically, the Project Lead is responsible for assembling the project team and ensuring
all parties perform duties and tasks adequately, all project partners (and where appropriate
project stakeholders) are consulted in major decision-making, all project partners and
stakeholders are adequately kept informed of project progress, oversees a work plan with
appropriate goals, timelines and budgets, makes day-to-day project decisions and
develops and executes a media/communications strategy. The Project Lead is expected to
have a high level understanding of all activities associated with the project.

TNC will act as the Project Lead throughout the duration of this project.

Project Partner

Project Partners provide financial and organisational support and expertise to the project.
They provide technical and logistical support to the Project Lead and other project partners
and stakeholders required to deliver project tasks and activities. Project Partners are
included in major decision-making but may not necessarily be involved in day-to day
project management. The Project Partners are responsible for various tasks and
responsibilities related to the project and in some instances assisting in the execution of
media and communications strategies.

Project Stakeholders

Project Stakeholder(s) are any group that have an interest or may be affected (positively or
negatively) by the project. They may be responsible for delivering non-core project related
activities but are more likely to be involved in consultation and decision making to ensure
the project does not negatively affect their operations and/or provides benefits. Examples
of Project Stakeholders include:


  Noosa River Partnership                                                             Page | 18

Section 19

The Nature Conservancy


   •   Local oyster growers
   •   Commercial fishers
   •   Commercial recreational fishing guides
   •   Foreshore residents
   •   Environmental community groups
   •   Restaurants, seafood wholesalers
   •   Boat and recreational equipment hire businesses
   •   Hotels and accommodation providers
   •   Sunfish and Ozfish Unlimited
   •   Local Member of Parliament
   •   Queensland Minister(s)
   •   Federal Ministers(s)
   •   Stage Government agencies

Project Stakeholders require regular dialogue and information to ensure they are kept
informed of the project’s status and outcomes and are involved in major decisions.

11.0 SUPPORTING DOCUMENTS

Report to The Thomas Foundation and Noosa Parks Association on assessment of
aquatic restoration and management options for Noosa Estuary and Lakes. 2015. The
Nature Conservancy, January 9, 2015.

Restoration of Noosa Estuary: An Assessment of Oyster Recruitment. 2015. The Nature
Conservancy and Ecological Service Professionals. July, 2015.

Historical ecology of the Noosa Estuary fisheries. Report to: Noosa Council, The Nature
Conservancy and The Thomas Foundation. 2015. Thurston R. University of Queensland.
2015.

Gillies et al. 2018. Australian Shellfish Ecosystems: past distribution, current status and
future management. PLoS ONE 13(2):e0190914.
https://doi.org/10.1371/journal.pone.0190914

Monitoring of the Noosa River Oyster Reefs: November 2017 - November 2018. Report to
Noosa Council, and Queensland Department of Agriculture and Fisheries. 2018. University
of Sunshine Coast. December 2018.




  Noosa River Partnership                                                              Page | 19

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.