Officer:	Glen Conforti
Direct Telephone:	07 53296241
Our Reference:	GCONFORTI:MCU15/0014
Your Reference:	15010

4 August 2015

Tea Tree Property Pty Ltd
C/- KHA Development Managers
PO Box 6380
MAROOCHYDORE BC  QLD  4558

[email protected]

Dear Sir/Madam

Decision Notice
Sustainable Planning Act 2009

I refer to your application and advise that on 3 August 2015, Council decided to approve the application in full subject to conditions.

Details of the decision are as follows:
APPLICATION DETAILS

Application No:	MCU15/0014
Street Address:	279 Gympie Tce NOOSAVILLE  QLD  4566
Real Property Description:	Lot 2 RP 51970
Planning Scheme:	The Noosa Plan (16 September 2013)

DECISION DETAILS

The following type of approval has been issued:
Development Permit for Material Change of Use of Premises - Multiple dwelling Type 4 Conventional (3 units)

RELEVANT PERIOD OF APPROVAL

The relevant period for this development approval is 4 years starting the day that this development approval takes effect.

ASSESSMENT MANAGER CONDITIONS

PLANNING
When Conditions must be Complied With
Unless otherwise stated, all conditions of this Decision Notice must be complied with prior to the use commencing, and then compliance maintained at all times while the use continues.
Approved Plans
Development undertaken in accordance with this approval must generally comply with the approved plans of development. The approved plans are listed in the following table unless otherwise amended by these conditions.
Plan No.	Rev.	Plan/Document Name	Date
SD.101	S7	Site Plan, prepared by Kidd + Co	18.06.15
SD.102	S7	Site Plan, prepared by Kidd + Co	18.06.15
SD.201	S7	Ground Floor Plan, prepared by Kidd + Co	18.06.15
SD.202	S7	Garage Plan, prepared by Kidd + Co	18.06.15
SD.203,	S7	First Floor Plan, prepared by Kidd + Co	18.06.15
SD.204	S7	Penthouse, prepared by Kidd + Co	18.06.15
SD.205	S7	Roof Plan, prepared by Kidd + Co	18.06.15
SD.501	S7	Elevations, prepared by Kidd + Co	18.06.15
SD.502	S7	Elevations, prepared by Kidd + Co	18.06.15
SD.601	S7	Sections, prepared by Kidd + Co	18.06.15
Building Height
The maximum height of the development must not exceed 12 metres above the finished ground level and the natural ground level and 3 storeys.
Certification must be submitted to Council from a Licensed Surveyor which certifies that the building does not exceed the maximum height requirement of this Decision Notice.
Performance Bond
Security in the form of a cash bond or trading bank guarantee to the sum of $15,000 must be submitted to Council, to secure performance of all conditions of this approval, prior to the issue of a Development Permit for Operational Works. The cash bond or trading bank guarantee will be returned on performance of the conditions of approval less any costs incurred by Council in respect of enforcing performance of this permit. Council reserves the right to call upon the bond or guaranteed sum to effect compliance with conditions.
Street Identification
The street address of the development must be clearly visible and discernible from the primary frontage of the site by the provision of a street number and, where appropriate, the building name.
Water & Sewer Connections
An underground connection to reticulated water and sewerage must be provided to each lot in accordance with the standards and requirements of Northern SEQ Distributor–Retailer Authority (Unitywater).
A Certificate of Completion from the Northern SEQ Distributor–Retailer Authority (Unitywater) must be submitted to Council that certifies an underground connection to reticulated water and sewerage has been provided to the development site.
Building Appearance
All air conditioning units or other mechanical equipment must be fully enclosed or screened such that they are not visible from the street frontages nor adjoining properties.
All deck and balcony areas must not be enclosed by permanent fixtures such as shutters, louvres, glass panelling or the like.
The pool cabana may be roofed.
Fencing and Walls
Any street fencing must be set back an average of 1 metre from the front property boundary. Any fencing on the front boundary must either:
not exceed a maximum height of 1.2m
be of open construction.
The area of land between the fence and the front property boundary must be densely landscaped to screen any fencing from the street.
Clothes Drying Areas
Each dwelling unit must be provided with access to an outdoor clothes line which is screened from public view.
Community Management Statement
Any proposed Community Management Statement required for the development pursuant to the Body Corporate and Community Management Act 1997 must be submitted to Council for endorsement at the same time as submission of the Building Format Plan (or similar) to Council for compliance assessment.
All clauses and by-laws of the proposed Community Management Statement must accord with the requirements of this Decision Notice.
Landscaping Works
The development site must be landscaped. The works must be undertaken in accordance with an Operational Works approval, the approved plans and Planning Scheme Policy PSP3 Landscaping Plants and Guidelines and must include in particular:
the landscape strip along the western boundary adjacent to the driveway must be densely landscaped with plants that grow to at least 3m at maturity
screening vegetation along the eastern boundary with plants that grow to a minimum of 6m at maturity. Plantings must have a maximum spacing of 3m (centres)
screening vegetation to the perimeter of the site
vegetated screening of any electrical transformers, bin storage areas and the like from the road frontage.
All landscape works must be established and maintained in accordance with the approved design for the life of the development, and in a manner that ensures healthy, sustained and vigorous plant growth. All plant material must be allowed to grow to full form and be refurbished when its life expectancy is reached.
External Works
Gympie Terrace must be upgraded for the length of its frontage to the subject site.  The works must be undertaken in accordance with an Operational Works approval and must include in particular:
construction of a pedestrian footpath in accordance with the conditions of this Decision Notice
removal of the existing property access and reinstatement of the kerb, footpath and verge area to match the balance of the site frontage, including the provision of topsoil and turf where the existing verge is grassed
relocation of the existing on-street parking bays affected by the proposed access driveway
Site Access and Driveways
A sealed access driveway must be provided from Gympie Terrace to all parking and manoeuvring areas of the development. The works must be undertaken in accordance with an Operational Works approval and must include in particular:
IPWEAQ standard drawing SEQ R-050
any proposed gate must be located a minimum of 6 metres from the front boundary
suitable signage at the entry to the garaging advising drivers to “Give Way” to incoming vehicles on the driveway. The type and location of the signage must be clearly shown on any plans submitted as part of an Operational Works application.
Car Parking
A minimum of 6 covered and 1 uncovered car parking spaces must be provided and marked on the site. The works must be undertaken in accordance with an Operational Works approval and must include in particular:
1 visitor parking space within the total, which is clearly marked for that purpose and accessible at all times for visitor use
Crossfalls, gradients and dimensions in accordance with Australian Standard AS2890: Parking Facilities
All car parking areas and access driveways must be maintained exclusively for vehicle parking and manoeuvring and kept in a tidy and safe condition at all times.
Directional signage must be provided to direct visitors to the car parking spaces provided on site.
Pedestrian and Bicycle Facilities
Pedestrian and bicycle facilities must be provided for the development.  The works must be undertaken in accordance with an Operational Works approval and must include in particular:
a 1.8 metre wide concrete footpath within the road verge for the entire length of the site’s frontage to Gympie Terrace
Stormwater Drainage
All stormwater drainage must be collected and discharged so there is no net increase in stormwater runoff from the site.
The site must be provided with a stormwater drainage system connecting to a lawful point of discharge.  The works must be undertaken in accordance with an Operational Works approval and must include in particular the works generally shown on the drawing No 25133-C1.1 prepared by SCG Consulting Engineers
Undergrounding of Existing Overhead Powerlines
The existing overhead electricity reticulation connection to the site must be removed and any new connection must be provided underground from the overhead electricity reticulation mains.
Easements
Unless otherwise agreed in writing by the relevant service provider, any public or third party infrastructure located on the subject site must be placed within an easement registered against the title of the property.
All easements must be designed in accordance with the planning scheme and granted at no cost to the Grantee.  Where the Grantee is Council or a service authority, the easement documentation must be in accordance with the Grantee’s standard easement terms.  Draft easement documentation must be submitted to Council for endorsement.
All works must be kept clear of any existing or proposed easements on the subject land, unless agreed otherwise in writing by the Grantee.
Earthworks and Retaining Walls
Filling works required on site must be carried out in accordance with Council’s Planning Scheme Policy PSP5 – Engineering Design Standards, so as not to cause the additional ponding of water on any adjoining lands or the blockage of, or interference with, any natural watercourses. Detailed site surveys indicating natural surface levels and contours of the adjoining properties must be provided with the application for a Development Permit for Operational Works.
This may require the design and construction of drainage pipes and/or an overland flow-path within the development site that caters for drainage from the adjoining sites for a 1%AEP design storm. A private easement for the Drainage of Water encompassing the drainage pipes or overland flow-path will also be required. In this regard a Development Permit for Operational Works must be obtained.
Should evidence be provided to Council indicating that no additional ponding of stormwater will occur on the adjoining properties the requirement for the drainage pipes, overland flow-path and easement shall not apply
All fill and associated batters must be undertaken in accordance with an Operational Works approval, and contained entirely within the subject site unless written permission from the respective landowner(s) is provided to Council.
Damage to Services and Assets
Any damage caused to existing services and assets as a result of the development works must be repaired at no cost to the asset owner at the following times:
where the damage would cause a hazard to pedestrian or vehicle safety, immediately; or
where otherwise, upon completion of the works associated with the development.
Any repair work which proposes to alter the alignment or level of existing services and assets must first be referred to the relevant service authority for approval.
ENVIRONMENTAL HEALTH
Building Demolition/Removal/Relocation
A Waste Management Plan (construction and demolition) must be submitted and approved by Council’s Environmental Health Officer prior to issue of a development permit for operational works.
A Waste Management Plans (construction and demolition) must be submitted in accordance with Planning Scheme Policy 11, Waste Management Plans.
Waste storage areas must provide adequate separation of all reusable, recyclable and waste materials. These must be located so that they are convenient and safe to use.
The Plan must contain the following information:
The site area for the storage and separation of waste is to be shown on the plan drawings accompanying the application.
A waste management table as indicated below is to be completed showing how waste material is to be segregated - recycled – reused or disposed.

Table – Waste Management Table
MATERIALS ON-SITE	DESTINATION
	Re-use and Recycling	Disposal
Expected waste materials	Estimated volume(m³)	On-site            *specify proposed re-use or on-site recycling methods	Off-site              *specify contractor and recycling outlet	*specify contractor and landfill site or other disposal site
Excavation material				
Green waste				
Bricks				
Concrete				
Timber-please specify				
Plasterboard				
Metals - please specify				
Asbestos				
Other - please specify				
Note * If a demolition contractor is undertaking works, then the Waste Management table is to be completed by the demolition contractor.
Waste Storage
The developer must provide waste storage and disposal facilities to the development site in accordance with Planning Scheme Policy 9, Waste Management, including an external imperviously paved area correctly sized for all refuse and recycling containers and suitably screened from public places and neighbouring properties.
The development site must be provided with a bin wash area with a cold-water tap, hose and drain outlet connected to sewer, via a bucket trap. The drain outlet is to be designed to prevent storm water entry to the sewerage system which can be achieved by a bunded area, with a nib wall height of 100mm maximum, enclosing a wash area of 700mm x 700mm minimum (max 0.7m²).  Alternatively, the waste area can be roofed or any other appropriate design approved by Council.
Noise
Written certification is required from a suitably qualified person confirming that sound pressure levels from all mechanical plant and equipment comply with the following :
Air-conditioning and Refrigeration
7am to 10pm: Maximum level allowable = background + 5dB(A)
10pm to 7am: Maximum level allowable =  background + 3dB(A)
Pumps
7am to 7pm: Maximum level allowable = background + 5dB(A)
7pm to 10pm: Maximum level allowable = background + 3dB(A)
10pm to 7am: No audible noise.
Assessment and certification is required immediately after installation of the equipment and prior to any occupation of the building.  All equipment should be operating at the same time to test the overall noise level created, with the measurement location at either the residential boundary or outside the most exposed part of an affected building - whichever is the closest to the plant/equipment.
The certification must be submitted to Council, which certifies that operational noise from any fixed plant and equipment complies with the requirements of this Decision Notice.

REFERRAL AGENCIES

Not Applicable.

ADVISORY NOTES

The following notes are included for guidance and information purposes only and do not form part of the assessment manager conditions:
Equitable Access and Facilities
The plans for the proposed building work have NOT been assessed for compliance with the requirements of the National Construction Code - Building Code of Australia (Volume 1) as they relate to people with disabilities.  Your attention is also directed to the fact that in addition to the requirements of the National Construction Code as they relate to people with disabilities, one or more of the following may impact on the proposed building work:
the Disability Discrimination Act 1992 (Commonwealth);
the Anti-Discrimination Act 1991 (Queensland); and
the Disability (Access to Premises – Buildings) Standards.
Development Compliance Inspection
Prior to the commencement of the use, please contact Council's Development Assessment Department to arrange a Development Compliance Inspection.
Building and Construction Industry (Portable Long Service Leave) Levy
The QLeave levy must be paid prior to the issue of a development permit where it is required. Council will not be able to issue a Decision Notice without receipt of details that the Levy has been paid. QLeave contact: 1800 803 481 (free call) or (07) 3212 6855.
Co-ordination of Operational Works Assessment
Additional application fees apply to Operational Work applications where the different aspects of the works are lodged separately. Significant savings in application fees will result if all works are lodged in a single application.
Preparation of a Preliminary Construction Management Plan
A preliminary Construction Management Plan must be submitted with the Operational Works application and must address the following:
traffic management during all aspects of the construction phase including:
a Traffic Management Control Plan in accordance with the Manual of Uniform Traffic Control Devices (MUTCD) detailing all temporary signage and traffic control measures prior to construction
maintenance of safe pedestrian access for the areas affected by the works during and after daily construction has ceased
proposed fencing to the site during the construction phase of the development
provision for worker car parking
maintenance and protection of water quality and existing drainage lines through the construction site, through the implementation of appropriate erosion and sediment control measures
works programme identifying key components of the works and their respective durations
establishment of a communication protocol with the general public, adjoining owners, emergency services and local businesses to advise of agreed construction times, impacts on traffic, services and other relevant issues
identification of complaint management procedures including:
contact details for the on-site manager
dispute resolution procedures
details on the location of external fill dump sites, the haulage route, type of vehicle to be utilised during excavation operations and frequency of usage.  NB any damage to the existing road system as a result of haulage operations shall be fully repaired at the applicant’s expense
it is acknowledged that the preliminary Construction Management Plan will be a draft document requiring finalisation upon appointment of the Principal Contractor employed to construct the works and a final document will be required to be submitted at the Pre-Start Meeting for the project.
Acoustic Advice & Design
It is highly recommended the developer seek the advice and design input of a qualified acoustic consultant at the plan development stage to ensure the development does not cause a noise nuisance under the Environmental Protection Act 1994.  Attention should be given to the following (but not limited to) :
building design and construction
design, selection and installation of fixed plant and equipment
the location of air conditioning and heating units, refrigeration plant, pumps, mechanical exhausts and plant rooms etc
the use of acoustic enclosures/screens around noisy plant and  equipment
operating times
Environmental Protection
The development should be undertaken in a manner that causes no unlawful environmental nuisance under the Environmental Protection Act 1994 by the creation of excessive noise, lighting, waste, atmospheric pollutants (including dust or odours) or other releases to the environment.
In accordance with the Environmental Protection Act 1994, all sand, silt, mud, paint, cement, concrete, builder’s waste or other prescribed contaminants should not to be released to or be placed where it could reasonably be expected to move into a roadside gutter, storm water drain or a watercourse.  On the spot fines apply for such offences.

PROPERTY NOTES

Not Applicable.

PRELIMINARY APPROVAL OVERRIDING PLANNING SCHEME

Not Applicable.

FURTHER DEVELOPMENT PERMITS REQUIRED

Development Permit for Operational Work (Access, stormwater, frontage works, carparking, electrical and landscaping)
Development Permit for Building Work (All Building Works)
Compliance Certificate for Document (Plan Sealing)

SELF ASSESSABLE CODES

Not Applicable.

SUBMISSIONS

There was 1 properly made submission about the application.  In accordance with Sustainable Planning Act 2009, the name and address of the principal submitter for each properly made submission is provided and attached.

REASONS / GROUNDS FOR APPROVAL DESPITE CONFLICT WITH SCHEME

Not Applicable.

RIGHTS OF APPEAL

You are entitled to appeal against this decision.  A copy of the relevant appeal provisions from the Sustainable Planning Act 2009 is attached.

During the appeal period, you as the applicant may suspend your appeal period and make written representations to Council about the conditions contained within the development approval.  If Council agrees or agrees in part with the representations, a “negotiated decision notice” will be issued.  Only one “negotiated decision notice” may be given.  Taking this step will defer your appeal period, which will commence again from the start the day after you receive a “negotiated decision notice”.

OTHER DETAILS

If you wish to obtain more information about Council’s decision, electronic copies are available on line at www.noosa.qld.gov.au, or at Council Offices.

Yours faithfully

Glen Conforti
DEVELOPMENT PLANNER

Enc:	Infrastructure Charges Notice]
Approved Plans/Documents
List of Submitters
Appeal Rights

cc	Unitywater

	List of Submitters SUSTAINABLE PLANNING ACT 2009 & SUSTAINABLE PLANNING REGULATION 2009

Only Properly Made Submissions are to be included in this notice (s335 (1) (l))

Mr & Mrs D Gray
31/287 Gympie Tce
NOOSAVILLE  QLD  4566

	Appeal Rights SUSTAINABLE PLANNING ACT 2009 & SUSTAINABLE PLANNING REGULATION 2009

The following is an extract from the Sustainable Planning Act 2009  (Chapter 7).
MATERIAL CHANGE OF USE, RECONFIGURING A LOT & OPERATIONAL WORKS

Division 8 	Appeals to court relating to development applications and approvals

461 	Appeals by applicants
(1) 	An applicant for a development application may appeal to the court against any of the following—
(a) 	the refusal, or the refusal in part, of the development application;
(b) 	any condition of a development approval, another matter stated in a development approval and the identification or inclusion of a code under section 242;
(c) 	the decision to give a preliminary approval when a development permit was applied for;
(d) 	the length of a period mentioned in section 341;
(e) 	a deemed refusal of the development application.
(2) 	An appeal under subsection (1)(a), (b), (c) or (d) must be started within 20 business days (the applicant’s appeal period) after—
(a) 	if a decision notice or negotiated decision notice is given—the day the decision notice or negotiated decision notice is given to the applicant; or
(b) 	otherwise—the day a decision notice was required to be given to the applicant.
(3) 	An appeal under subsection (1)(e) may be started at any time after the last day a decision on the matter should have been made.

462 	Appeals by submitters—general
(1) 	A submitter for a development application may appeal to the court only against—
(a) 	the part of the approval relating to the assessment manager’s decision about any part of the application requiring impact assessment under section 314; or
(b) 	the part of the approval relating to the assessment manager’s decision under section 327.
(2) 	To the extent an appeal may be made under subsection (1), the appeal may be against 1 or more of the following—
(a) 	the giving of a development approval;
(b) 	any provision of the approval including—
(i) 	a condition of, or lack of condition for, the approval; or
(ii) 	the length of a period mentioned in section 341 for the approval.
(3) 	However, a submitter may not appeal if the submitter—
(a) 	withdraws the submission before the application is decided; or
(b) 	has given the assessment manager a notice under section 339(1)(b)(ii).
(4) 	The appeal must be started within 20 business days (the submitter’s appeal period) after the decision notice or negotiated decision notice is given to the submitter.

463 	Additional and extended appeal rights for submitters for particular development applications
(1) 	This section applies to a development application to which chapter 9, part 7 applies.
(2) 	A submitter of a properly made submission for the application may appeal to the court about a referral agency’s response made by a prescribed concurrence agency for the application.
(3) 	However, the submitter may only appeal against a referral agency’s response to the extent it relates to—
(a) 	if the prescribed concurrence agency is the chief executive (environment)—development for an aquacultural ERA; or
(b) 	if the prescribed concurrence agency is the chief executive (fisheries)—development that is—
(i) 	a material change of use of premises for aquaculture; or
(ii) 	operational work that is the removal, damage or destruction of a marine plant.
(4) 	Despite section 462(1), the submitter may appeal against the following matters for the application even if the matters relate to code assessment—
(a) 	a decision about a matter mentioned in section 462(2) if it is a decision of the chief executive (fisheries);
(b) 	a referral agency’s response mentioned in subsection (2).

464 	Appeals by advice agency submitters
(1) 	Subsection (2) applies if an advice agency, in its response for an application, told the assessment manager to treat the response as a properly made submission.
(2) 	The advice agency may, within the limits of its jurisdiction, appeal to the court about—
(a) 	any part of the approval relating to the assessment manager’s decision about any part of the application requiring impact assessment under section 314; or
(b) 	any part of the approval relating to the assessment manager’s decision under section 327.
(3) 	The appeal must be started within 20 business days after the day the decision notice or negotiated decision notice is given to the advice agency as a submitter.
(4) 	However, if the advice agency has given the assessment manager a notice under section 339(1)(b)(ii), the advice agency may not appeal the decision.

465 	Appeals about decisions relating to extensions for approvals
(1) 	For a development approval given for a development application, a person to whom a notice is given under section 389, other than a notice for a decision under section 386(2), may appeal to the court against the decision in the notice.
(2) 	The appeal must be started within 20 business days after the day the notice of the decision is given to the person.
(3) 	Also, a person who has made a request under section 383 may appeal to the court against a deemed refusal of the request.
(4)	An appeal under subsection (3) may be started at any time after the last day the decision on the matter should have been made.

466 	Appeals about decisions relating to permissible changes
(1) 	For a development approval given for a development application, the following persons may appeal to the court against a decision on a request to make a permissible change to the approval—
(a) 	if the responsible entity for making the change is the assessment manager for the application—
(i) 	the person who made the request; or
(ii) 	an entity that gave a notice under section 373 or a pre-request response notice about the request;
(b) 	if the responsible entity for making the change is a concurrence agency for the application—the person who made the request.
(2) 	The appeal must be started within 20 business days after the day the person is given notice of the decision on the request under section 376.
(3) 	Also, a person who has made a request under section 369 may appeal to the court against a deemed refusal of the request.
(4)	An appeal under subsection (3) may be started at any time after the last day the decision on the matter should have been made.

467 	Appeals about changing or cancelling conditions imposed by assessment manager or concurrence agency
(1) 	A person to whom a notice under section 378(9)(b) giving a decision to change or cancel a condition of a development approval has been given may appeal to the court against the decision in the notice.
(2) 	The appeal must be started within 20 business days after the day the notice of the decision is given to the person.

[word/footer1.xml]
Page 13 of 13

[word/footer2.xml]
PO Box 141		P. (07) 5329 6500	[email protected]	
	TEWANTIN  QLD  4565	F. (07) 5329 6501	www.noosa.qld.gov.au
				Page 1 of 13

[word/header1.xml]
MCU15/0014

[Attachment: image4.png (image text)]
 
 
 

 
 
 

a
mm

  

NOOSA
COUNCIL

Used in these records

About this file

File size
107 KB (small file)
File type
DOCX

No other editions are linked here.

Original file

Log in to download the original file

MCU15_0014 Approved Decision Notice.docx · 107 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.