ATTACHMENT 1




          Zero Emissions Noosa Inc. Partnership
                   Alliance Agreement


               Operational Report to Council for 2024




                                                        1
Log in to download the original file

ATTACHMENT 1_ZEN Inc. Report on Partnership Alliance Agreement to Council 2024.pdf · 1.1 MB (small file)

Full text of the other 75 pages

Page 2

   1. Introduction to the Organisation
ZEN Inc. is seen to be at the forefront of community energy as both a regional influencer and a
model for other community energy groups to follow.

ZEN Inc. is the community energy group assisting Council in the Noosa Shire Community to
implement key Council plans, including the Corporate Plan across the following themes:
   1. Environment-
   ➢ Noosa Environment Strategy 2019 (Sustainable living & Climate change adaptation and
        resilience)
   ➢ Climate Change Response Plan 2021(all 8 themes)
   ➢ Noosa Transport Strategy 2017 - 2027 (development of a new movement and connectivity
        strategy).

    2. Liveability
    ➢ Noosa Transport Strategy 2017 - 2027 - development of a new movement and connectivity
       strategy
    ➢ - Cycling and Walking Strategy and Implementation Plan 2020
    ➢ - Noosa Trails Masterplan and Implementation Plan 2020 (use of completed plan).
    ➢ - Noosa Housing Strategy 2022 (Energy efficiency cost savings & emissions reduction)
    ➢ - Noosa Social Strategy and Social Justice Charter – Community Strategy (Energy efficiency
       cost savings & emissions reduction)
    ➢ - Noosa Health and Wellbeing Plan & Implementation (through pillars of the Corporate Plan)

  3. Excellence
➢ Community Engagement Framework (through Community batteries, Electrify Everything &
   Transport forums/workshops)

    4. Prosperity
    ➢ Economic Development Strategy 2021 – Smart Biosphere (through Community batteries,
       Electrify Everything & Transport projects)
    ➢ Waste to Resource Strategy 2023-2028 (renewable energy)
       &
    5. Future
    ➢ Community Strategy – as above.
    ➢ Climate Change Response Plan – as above
    ➢ Noosa Design Principles (Sustainable Passive Design for energy efficiency)
    ➢ Disaster Management Plan (use of renewable energy)
    ➢ Local Disaster Recovery Plan(use of renewable energy
    ➢ Destination Management Plan (transport alternatives & emissions reduction strategy)
    ➢ Economic Development Strategy (through Community batteries, Electrify Everything &
       Transport projects)
    ➢ Waste to Resource Strategy 2023-2028 (renewable energy)

With the Climate Change Response Plan being the key driver for ZEN Inc’s work.

ZEN Inc. has a close and collaborative relationship with Noosa Council and is helping Council to step
up as a leader in the emissions reduction space.



                                                                                                        2

Page 3

It is governed by a Board of up to 10 people, which oversees three Working Groups – ZEN E (Energy),
ZENTAG (Transport) & Expo Working Group. The board’s work is supported in it’s operations by
three sub-committees:
      ➢ Governance & Operations
      ➢ Finance & Fundraising and
      ➢ Communications & Advocacy.

A Public Fund Account Committee oversees Tax Deductible donations. See Appendix A for ZEN Inc’s
Organisational Chart.

   2. Current ZEN Inc. Strategic plan and 2024-2025 & Action Plans
ZEN Inc. reviews it’s strategic plan annually in August. Following a complete review in August 2023,
a review of the ZEN E & ZENTAG Action Plans were undertaken in 2024.The Expo Working group
Workplan was reviewed in Nov., 2024, once the decision to go ahead with a 7th EV & Electrify Expo
was made. See Appendix B.

The two key objectives are to:

Goal 1: Promoting community actions to achieve net zero emissions.
We will provide leadership and management of projects, advocacy, education and community
engagement that help the Noosa community on its journey towards net zero emissions (our core
business)

Goal 2: To be a sustainable organisation.
To fulfill its vision and mission, ZEN Inc must be a well-resourced and efficient organisation.

Objectives
The objectives to achieve these goals are outlined in Appendix B, along with their associated
Outcomes/ Measures of Success.

Strategies
The key priorities and higher-level elements identified through our SWOT analysis have informed our
strategies. The strategies inform the ZEN E and ZEN TAG action plans and the activities of our three
sub-committees.

The 2024-2025 ZEN Inc Operational Plan is in fact the Action Plans for the ZEN E (Energy) Group and
ZENTAG (Transport) groups. Both groups undertake projects, some of them at the cutting edge of
community energy.

ZEN E (Energy) Group, ZENTAG (Transport) Group Action Plans & Expo Working Group Workplan
Attached as Appendices C, D & E are the action plans for ZEN Inc’s three Working Groups, where
project work is carried out.

   3. Significant developments concerning ZEN Inc. activities
ZEN Inc. is a regional influencer and change agent for the Noosa Community in assisting them to move
towards the goal of net zero greenhouse gases. In 2024, we made significant progress with projects
and engaging with the Noosa Shire community to m o v e f u r t h e r towards zero net greenhouse
gas emissions. Many ZEN Inc. projects are cutting edge, ground breaking and future focused
renewable energy projects, leading the way in Queensland and in many cases nationally. Some of our
flagship projects included:

                                                                                                       3

Page 4

 1. Community Batteries - with both:

        a. A Qld. Govt. Dept. of Environment & Science Community Sustainability Action Grant

The Business Plan for a Network of Community Batteries in the Noosa Local Government Area to
reduce emissions was completed in May, 2024, Follow up meetings have been held with Energy Qld.,
the former Department of Energy & Climate and various community energy groups across Aust. have
used this report to inform their work in the planning and funding applications for community
batteries. This report also was done in tandem with the planning and development of the Noosaville
Community Battery and was a of great assistance in informing this work. It was a key milestone in the
3+ years of ZEN Inc’s volunteer work in this space.

        b. Noosaville Community Battery

The consortium working on the $500,000 federally funded community battery in Noosaville, of ZEN
Inc., Noosa Council and Yarra Energy Foundation (YEF) undertook a huge amount of work to negotiate
the planning and progressing of this project in 2024.

ZEN Inc. led the way in advocating with 54 stakeholders across regulators, government (state &
federal level), industry and consumer energy groups for reduced tariffs and connection fees to make
this and other community batteries financially viable. ZEN Inc. was instrumental in persuading Energy
Qld. to make this battery, the only community owned community battery in Qld., a pilot on the
community energy sector, with Energy Qld. agreeing to cover the tariffs for 5 years, while more work
is done to investigate future financial viability for this and other community batteries.

ZEN Inc. has undertaken the Community Battery consultation for YEF as part of the consortium and
will again in early 2025 to inform and involve the community about the operation of the battery for
community benefit. For further detail see the ZEN Inc. 2024 Annual Report.


 2. 2024 6th Annual Electric Vehicle & Electrify Everything Expo
With 5,500 visitors, 65+ exhibitors, saw 80.3% came to learn about electric transport, 69.7% came to
learn about how to save money on home energy e.g. solar, battery, heat pumps. 52% of Expo visitors
will or may purchase an EV in the next 12 months.

The scope of the Expo was expanded in 2024 to include Electrify Everything to assist in household
behaviour change re electricity use and how they can save money, while reducing their emissions.

Thanks to Noosa Council for their final year of MOU financial support for the Expo. For further detail
see the ZEN Inc. 2024 Annual Report.

 3. Rewiring Noosa – Electrify Everything

Where ZEN Inc. on behalf of the Noosa Shire community, was chosen to work with Saul Griffiths
Rewiring Aust. project as one of the original community partners.

Mid-year, ZEN Inc. launched our Rewiring Noosa Toolkit developed for us by Rewiring Australia,
followed by making of 7 video testimonials by Noosa Shire community members who have moved
from traditional energy sources to power highly energy efficient appliances, coupled with solar and
monitoring systems. These tools are to ensure all Noosa Shire community members (home owners
and renters alike) can benefit by saving money, AND reducing their carbon footprint.

Thanks to Noosa Council for their grants funding for this project. For further detail see the ZEN Inc.

                                                                                                     4

Page 5

2024 Annual Report.

 4. Solar for Strata

ZEN Inc. is adding impact and value to previous Council grant funded projects by continuing to
promote them with the relevant target audience. The Solar for Strata on line toolkit and Solar
Champions video are examples of this. While they were completed in 2024 and despite the project
leader stepping down mid-year, ZEN Inc. was able to hold a successful forum, working jointly with
Tourism Noosa to promote these tools to the strata accommodation community.

 5. E Bike Library

ZEN Inc. was successful in Nov., 2024 with a grant of $22.392 from the Dept. of Transport & Main
Roads for the Bike Riding Encouragement Program (BREP) Innovation Grant to be able to set up an e
bike library so people can borrow different types of e bikes for a period of two weeks and try them
out to help them make a purchasing decision. This program will get underway in 2025.

All our projects and activities are outlined in detail in our Annual Report.

ZEN Inc. is very appreciative of funding from Noosa Council, the Federal and Queensland
Governments, and the patrons and sponsors of our Expo to assist our work. We are also fortunate
to have a collaborative working relationship with a number of key stakeholders, especially Noosa
Council, Yarra Energy Foundation (YEF), Tourism Noosa and Noosa Junction Assoc., and Noosa
Biosphere Reserve Foundation (NBRF) and Energy Qld. to name a few. We thank them all for their
support.

 6. The Role of Council Alliance Partnership Funding for 2024

The Council Alliance Partnership Funding is the enabler that allows ZEN Inc. to undertake its
administration, internal organisation and operations through a combination of volunteers and an
Administration Coordinator who began working 24 hours per week in October, 2023, in both
administration and some limited communications work. This was intended to enable some ZEN Inc.
volunteers, especially the ZEN Inc. Chair, to spend some more time to undertake ZEN Inc’s cutting-
edge project work.

In the first half of 2024, the Alliance Partnership Funds for the following positions were funded by
the $65,000 from the Year 1 2023 -2024 funding:

    1. Administration & Communications $50,000 (a small amount used in 2023 and most was
         used in the first half of 2024 as year 1 funding was not received until Oct. 2023) and
    2. Communications Package $15,000 (a small component was used in 2023 and part used in
         the first half of 2024 for marketing for the EV Expo. )
as outlined in Appendix F.

In the second half of 2024, after the Alliance Grant Year 2 of funding was received on 23 Oct., 2024,
only $14,393.32 was spent before 31 Dec., 2024. The reasons for this are explained below.

The Administration role was for 21 hours per week, with 3 hours per week to assist with some
Communications work that assisted ZEN Inc. with limited website updating and production s of
regular newsletters, some assistance for volunteers with writing of print media and social media
posts, including for the EV & Electrify Everything, in addition to organising community forums,
promoting ZEN Inc’s resources e.g. tool kits and videos, through various media channels to help raise

                                                                                                        5

Page 6

awareness in the Noosa community of ways to save money and reduce emissions.

The Communications Package was to assist ZEN Inc. with website updating/revision & marketing
advice for ZEN Inc. generally & the EV Expo or similar, in addition to education and advocacy about
emissions reduction to the Noosa Shire community, including ZEN Inc’s project work, through
various media channels.

This was only partially used to engage a Marketing and PR business to develop social media tiles to
promote the Expo to help improve the geographic and demographic reach of ZEN Inc., with
disappointing results. Hence, that business was not engaged any further to assist in implementing
the full Communications Package from June 2024 on. Also, due to HR issues with the ZEN Inc’s
employee in the Admin./Coordinator role, and the recruitment of the Program/Project Manager
role, ZEN Inc. was unable to appoint a suitable business to implement the Communications Package
until early 2025.
Hence some Year 2 Council Alliance Partnership funds that should have been used for in 2024 have
been carried over for use in 2025.

The desired outcome of having the Administration/Coordination position with some
communications assistance was to enable the ZEN Chair to spend more time working at the strategic
level to develop collaborative relationships and be involved in strategically important projects, e.g.
to step into the project leader role for the Community Battery project as long-time volunteer project
leaders stepped back and to step back from the lead role in the Expo organisation each year.

As it became obvious during 2024, that the skill set of the person in the Administration/Coordination
role was more communications aligned than administration aligned and also to help fit in with the
employee’s family needs, the number of work hours the employee worked, were reduced at her
request. Hence, the support from this role to the ZEN Inc. Chair in particular, was less than expected.
In addition, as the ZEN Inc. Chair is also Chair of the Communications and Advocacy Committee,
being diverted to deal with HR issues meant that the appointment of another media and marketing
organisation to work with ZEN Inc. has not been possible until early 2025.


Following the Alliance Partnership Funds being raised to $125,000 per year for years 2 & 3 of the
agreement from July, 2024, this enabled ZEN Inc. to employ a Program and Project Manager in Nov.,
2024 for 19 hours per week, as well as the same person in the Administration /Secretariat role for
10 hours per week. These roles were established to help keep the organisation working, and take
the majority of admin. work and some project work from the volunteer ZEN Inc. Chair, who has
been working as a volunteer CEO for 40 – 50 hours per week.

As these positions were only filled in Nov., 2024, it was too early to include an evaluation of the
effectiveness of these roles in this report for 2024, but there are some very promising signs for ZEN
Inc. with the new employee.




                                                                                                        6

Page 7

      7. Annual Report against the Utilisation of 2024 Funding/Projects and
           Status, including % of projects completed within target time frames
     All of the funded projects have been or will be completed within the required timeframe. One of the
     grants from Noosa Council, Energy Assessments and Upgrades for Low Income and Vulnerable
     Households, has required a variation to re-focus the project, due to the difficulty of engaging with
     organisations to select the households to be involved.

Source             Amount           Description                        Project Status         Acquitted/Acquittal
                                                                                              Due
Noosa Council      $7,500           2024 Electric Vehicle Expo Final Completed. 2024          Year 3
                   (+GST)           year of MOU for “Seed Funding” Expo completed             finished 30
                                                                     successfully5,500        July, 2024
                                                                     people attended. 52% within
                                                                     of Expo visitors will or timeframe.
                                                                     may purchase an EV
                                                                     in the next 12 months
Noosa Council      $7,169           Solar for Strata Stage 3 -        Completed. Video        31 July 2024
                   (+ GST)          Supporting Solar Champions        made. Lives on ZEN Within extended
                                    Video (Climate Change Grants)     inc. website. You       timeframe
                                                                      Tube Snap shot
                                                                      Videos were made.
                                                                      Video referred to at
                                                                      Tourism Noosa
                                                                      Forum Nov. 2024 &
                                                                      shown to Team Body
                                                                      Corporate & Other
                                                                      solar for Satra
                                                                      enquiries in Noosa
                                                                      Shire & interstate.
Noosa Council      $ 19,455         Rewiring Noosa – Electrify        Completed. 8            30 June, 2024 within
                   (+GST)           Everything Toolkit & 8 videos     community forums at timeframe
                                                                      Libraries, community
                                                                      centres, Expo, RACV
                                                                      resort.
Qld. Govt. Dept.   $49,100          Community Sustainability Action Completed.                30 May 2024
of Environment     (+GST)           Grant – Develop a Business Plan Investigate storage within timeframe
& Science                           for a Network of Community        and solar PV
                                    Batteries in the Noosa Local      opportunities,
                                    Government Area to reduce         Research for sites,
                                    emissions.                        Stakeholder
                                                                      discussion,
                                                                      Community
                                                                      consultation
                                                                      completed. Final
                                                                      Report written &
                                                                      distributed to key
                                                                      stakeholders and
                                                                      Community energy
                                                                      groups.
Noosa Council      $29,000 (+GST)   Energy Assessments and            In progress.            30 June, 2025
                                    Upgrades for Low Income and       Grant variation on
                                    Vulnerable Households             29 Jan., 2025 as
                                                                      very difficult to find
                                                                      low-income homes
                                                                      to participate in
                                                                      energy audits.
Noosa Council      Remainde         Alliance Partnership Agreement    Completed               30 June 2024 Was
                   r of             Administration of ZEN Inc. as a                           be completed within
                   $65,000          small business and some                                   timeframe
                   (+GST)           Communications – Marketing &
                   for 2023-        PR work

                                                                                                               7

Page 8

                  2024



Noosa Council     $125,000                Alliance Partnership Agreement          In progress               30 June, 2025
                  for 2024-               Administration/Secretariat of
                  2025                    ZEN Inc. and Program/Project
                                          Manager roles to help run ZEN
                                          inc. as an efficient & effective
                                          Not for Profit, and for
                                          Communications – Marketing &
                                          PR assistance
    NB: For 2024 total grants = $179,669 using only 50% of grant figures that go across 2023-2024 & 2024 -2025


      8. Leveraging achieved from Council funding calculated as a total of funded
           projects compared with Council approved project funding.

                                                       ROI = 21.3

                                                                                                             $1,102,643+
                   $922,360                                                                                  (direct &
                                                                 $633,060                                    indirect)

            7,695 In Kind                                 Additional
            volunteer hours                               Contributions

             The value of ZEN                              Grants,                                        Goods and services
             Inc. volunteer board                          sponsorships                                   sales resulting from
             and working groups                            &/or in-kind                                   ZEN Inc’s projects
             hours on projects                             contributions                                  EV EXPO
             and related                                   received from                                  ($1,102643) + $ YEF,
             facilitation                                  other                                          Saul Griffith’s
                                                           organizations,                                 Rewiring Aust., E
                                                           state or federal                               Racing teams &
                                                           government                                     others)
                                          (excl.
                                          industry
                                          expertise
                                           Projects & Activities = 1,463,097 people
    Number of People reached with ZEN Inc.uncosted
                                          e.g. YEF)
                  ZEN Inc.’s ROI & Contributions to Council’s bottom line
                     1. “Value adds” $2,659,103 + for the rate payer dollar

         2. Is $2,659,10+ per annum saving to Council i.e. If ZEN Inc. didn’t exist, the work
                                 ZEN Inc. does would cost Council *
    * Based on an av, value of ZEN Inc volunteers at $120 per hour, way below market rate for much of its project work.
    Not only is this a massive contribution to the Noosa community, but it enables Council to leverage
    massively from the volunteer work done by ZEN Inc., in addition to contributing to emissions
    reduction and climate change impact in the Noosa Shire community.




                                                                                                                            8

Page 9

Source             Amount        Description                       Funding Leveraged     Volunteer In Kind
                                                                                         Hours
Noosa Council      $7,500        2024 EV & Electrify Everything    $96,000 +            Tony 25
                   (+GST)        Expo MOU for “Seed Funding”                            hrs per
                                 Project Leader Tony Clark                              week x 4
                                 5,500 people attended                                  weeks
                                 both expos                                             100 hrs
                                                                                        per month
                                 52% will make a purchasing
                                 decision in the next 12 months.                        x for 8
                                                                                        months =
                                                                                        800 hrs
                                                                                        @$120
                                                                                        per hour

                                                                   $7,680               NJA 2 hrs
                                                                                        x 4 weeks
                                                                                        =8 per
                                                                                        month x 8
                                                                                        months =
                                                                                        64 hrs @
                                                                                        $120 per
                                                                                        hour


                                                                   $8,000 +             Vols. on
                                                                     $1,102643          day 20 x
                                                                    Economic            8 hours =
                                                                    value               160 hrs x
                                                                                        $50 per
                                                                                        hour =
                                                                                        $8,000
Noosa Council      $7,169        Solar for Strata Stage 3 -        $4,800               Jenny 40 hrs @
                   (+ GST)       Supporting Solar Champions                             $120 per hour
                                 Video (Climate Change Grants)
                                 Project Leader: Jenny Clement
Noosa Council      $ 19,455      Rewiring Noosa – Electrify        $38,400                Mark & Anne or
                   (+GST)        Everything                        Working with Saul      other vol.
                                 Project Leader: Mark Purcell      Griffiths Rewiring     8 forums = 20hrs
                                                                   Australia as one of 10 x 8 = 160 vol.
                                                                   pilot communities      hours x 2 people
                                                                                          = 320 hrs @ $120
                                                                                          per hour
Qld. Govt. Dept.   $49,100        Community Sustainability Action   $38,400               Geoff 10 hrs x 4
of Environment     (+GST)         Grant – Develop a Business Plan                         weeks = 40 x 5
& Science                         for a Network of Community                              months = 320 hrs
                                  Batteries in the Noosa Local                            @ 120 per hour
                                  Government Area to reduce
                                  emissions. Project Leaders: Geoff $9,420                 Vivien 7hrs x 4
                                  Acton & Vivien Griffin                                   weeks = 70 hrs x
Noosaville         $10,000        Develop a Community                                      11 months =
Community          (+GST)         Consultation Plan with Noosa                             77hrs x $120
Battery                           Council & undertake                  + Community battery per hour
Commun       ity                  Community Consultation               $500,000
Consultation                      Project Leaders: Geoff Acton &
                                  Vivien Griffin
ROI Calculator     No funding.    Project Leader: Rosemary Grundy $24,000                  10 hours per
                                                                                           week x 20 weeks
                                                                                           = 200 hrs x $120
                                                                                           per hour
ZENDURO            No funding.   EV related project at Schools         $5,760              John F 2hrs per
                                 Project leader: John Fuller following                     week x 8 hrs per
                                 up leads                                                  month x 6 mths =
                                                                                           48 hours @ $120

                                                                                                              9

Page 10

                                                                           per hour.



Noosa Council     $65,000     Partnership Agreement          $264,000 +   Anne 2024 50 hrs
                  (+GST)      Grant Leader Anne Kennedy                   x 4 weeks = 200
                              Coordinating administration of              hrs x 11 months
                              ZEN Inc. as a small business &              =2,200 hrs @
                              supervising one staff member                $120
                              Grant enables ZEN Inc. to do                Colin incl.
                              Admin. & Communications work                Treasurer’s role) -
                                                                          30 hrs x 4 weeks
                                                             $158,400     = 120 hrs x 11
                                                                          mths = 1,320 hrs
                                                                          @ $120

ZEN Inc.            No        Board                          $48,000       Board
volunteers          Funding                                                9 meetings x 5
working in & on                                                            hours incl. Prep.
the organisation,                                                          Time = 40 hours
media, projects                                                            x 10 people =
(in addition to the                                                        400hours @
project leaders                                                            $120 =
hours included
above)                        Governance & Operations,       $4,320        2 meetings x 2
                                                                           hours= 4 hrs x 5
                                                                           people =20 hours
                                                                           @ $120 per hour


                              Finance & Fundraising,         $11,520       6 meetings x 2
                                                                           hours = 12 x 3
                                                                           people= 36 hours
                                                                           @ 120 per hour

                              Communications & Advocacy     $ 26,400       8 meetings x 2
                              meetings & follow up work,                   hours=16 hours x
                                                                           6 people = 96
                                                                           hours @ $120
                                                                           per hou


                              print media                                  2024
                                                             $52,800
                                                                           Jenny 5 hrs x 4
                                                                           weeks = 20 hrs x
                                                                           11 months = 220
                                                                           hrs@ $120

                              social media                   $15,840       Duncan 10 x
                                                                           4weeks x 11
                                                                           mths = 44hrs @
                                                                           $120
                                                                           John 3 hrs x
                                                                           4weeks = 12
                                                                           hours x 11
                                                                           months = 132 hrs
                                                                           $120

                                                                           Rosemary &
                                                             $38,400       Gerry 8 videos x
                                                                           20 hrs each =
                                                                           160 hrs x 2
                                                                           people = 320 hrs
                                                                           @ $120 per hour
                              data gathering, IT &


                                                                                            10

Page 11

                                        Website;


ZEN Inc.            No                  ZEN E                           $26,400             Mark = 20 hrs x
volunteers          Funding                                                                 11 months = 220
working in & on                                                                             hrs@ $120
the organisation,
media, projects
                                                                        $14,400             ZEN E Group - 6
(in addition to the
project leaders                                                                             people x 2 hrs
hours included                                                                              per month = 12
above)                                                                                      hrs x 10
                                                                                            meetings = 120
                                                                                            hrs @ $120
                                        ZENTAG                          $21,600            Carina - 5 hrs x 4
                                                                                           weeks = 20 hrs x
                                                                                           9 months = 180
                                                                                           hrs@ $120

                                                                                            ZENTAG Group
                                        Expo Working Group meetings     $7,200              3 people x 2 hrs
                                                                                            x 10 meetings =
                                                                                            60 hrs @ $120


ZEN Inc.            No                  Strategic Planning Review Day   $9,840              12 people x 6 hrs
volunteers          Funding                                                                 = 72 hrs + 6
working in & on                                                                             hours for Cathy
the organisation,                                                                           write up + 4 hrs
media, projects                                                                             briefing = 82 hrs
(in addition to the                                                                         @ $120
project leaders
hours included
above)
Expo related        $53,086
revenue –
sponsorships,
donors,
exhibitors
Community           $500,00
Battery

                 $608,686                                               $923,400            7,695 vol. hours
                 contributions to the
                 Noosa Community
                 in non-council
                 grants/funding
                 plus sponsorships
                 and in- kind
                 contributions Incl.
                 community battery
                 & EV Expo)



      9. Range of methods of communication and estimated audience reach –

     Number of People reached with ZEN Inc. Projects & Activities = 1,463,097 people

      EV Expo                           5,500 visitors + 126 businesses in Noosa Junction + 65 Exhibitors +
                                        120 potential exhibitors
      Community Battery Group           200 in Regional groups
                                        54 Key stakeholder groups in CB advocacy

                                                                                                               11

Page 12

 Solar for Strata Forum         25 body corporate related entities
 with Tourism Noosa
 Studies
 Solar for Strata Stage 3       500people across Aust.
 Supporting Solar Champions
 Video
 Saul Griffith Electrify        250 people
 Everything Bris, Forum
 8 Electrify Everything         160 people
 Forums in Noosa Shire
 Green Drinks Electrify         50 people
 Everything @ RACV Resort
 Solar Citizens Forum @         50 people
 Maroochydore
 Biz to Zero Talk               100 people
 Energy Qld. Network            30 people
 Pricing Group
 Noosa Council Staff            7 Crs. + 15 Council staff
 ZEN Inc. newsletters           1,110 x 14 = 15,400 people
 NBRF newsletters               500 x 2 = 1,000 people
 Tourism Noosa                  Social media & newsletters x 2 = 452,000
 Coalition for Community        300 people
 Energy Conf. (C4Ce)
 ZEN Inc. website               7,900
 ZEN Expo website               5,800
 ZEN Inc. Facebook              3,100
 ZEN Instagram                  77
 Print media Noosa Today        22,000 people x 23 issues = 506,000 people
 Your Local Lifestyle (YLL)     8,000 x 6 times per year = 48,000
 Radio Hot 91 @ Expo            500,000 people
 ABC Sunshine Coast             275,000
 SEA/MIX FM                     97,400
 Tress for Tourism              50 people
 LREZ Launch @ Caloundra        50 people
 NBRF Awards                    120 people
 Senate submission              300 people
 ZEN Inc. Members & Public      63
 Fund Account Committee
 Total                          1,463,097 people


 10. Financial Statements for 2024
Please note: ZEN Inc’s Financial Year is Jan. – Dec., 2024

    a. P&L For Jan. – Dec., 2024
The Profit & Loss Statement for the above period shows:

Gross Profit was                   $194,868.86
Total Operating Expenses           $ 61,523.69
Net Operating Profit               $ 133,345.17

                                                                             12

Page 13

While this might look like a healthy bank balance, the majority of these funds are project based from
grants and so are allocated to a specific projects. Refer to Appendix H for details.

b. P&L for Projects Jan. – Dec., 2024
The Profit & Loss Statement by Project shows that for the period 01 Jan., 2024 to 31 December 2024
all $150,144.89 of funds were spent as per project plans.
Refer to Appendix I for details.

c. Balance Sheet- as at 31 Dec., 2024
ZEN Inc. total assets were $244,570.032, with total liabilities $13,195.73 and net assets were
$231, 379.79 and equity at $231, 379.79. See Appendix J.

 11. Audited financial report for financial year
The accounts audited by Louise McNeich, auditor, LMC Financial Group at Cooroy.
Refer to Appendix K. As the audited accounts were only provided by the Auditor recently, they are
attached unsigned as it has not been possible to get them signed by both parties prior to submitting
this report.

 12. Donations - DGR funds
Zero Emissions Noosa Inc. was granted DGR status with immediate effect by the Assistant Minister
for Competition, Charities and Treasury on 23 September 2022. The balance of the account has
varied, as funds have been transferred to the Operating Account to meet expenses, on an as needs
basis, particularly for the 2024 EV & Electrify Everything Expo. The expenditure of these funds have
been agreed by the ZEN Inc. Public Fund Account Committee, as meeting the objectives of the
organisation.

 Date               Balance
 01 Jan. 2024       $1,728.05
 Nov. 2023          $18239.04 following donations to ZEN Inc.
 26 Aug., 2024      $1,778.94 after funds from this account were used to assist the objectives of
                    ZEN Inc., including the 2024 Expo.
 31 Dec., 2024      $2,309.24 following further donations

ZEN Inc. is actively seeking donations to it’s Public Fund Account.

    13. Any significant delays in performing the ZEN Inc. program for this
    Agreement
The biggest risk for Council and ZEN Inc. is finding sufficient volunteers to be project leaders and to
actively drive projects and source future funding sources. Hence, the ability to appoint a part time
Program/Project Manager in late 2024, will partly assist our volunteers in 2025 with projects..
Getting dedicated volunteers, with time, since COVID has been difficult, and many of the very active
volunteers who have been involved with ZEN Inc since it’s inception or for many years, after having
given thousands of hours of volunteer time to ZEN Inc. & Council, have stepped back from being
actively involved in ZEN Inc. projects.




                                                                                                     13

Page 14

Appendix A ZEN Inc. 2024 Org. Chart




                             ZEN Inc Board




  Governance &        Finance &              Communications &
   Operations        Funding sub-              Advocacy sub-
      sub-            committee                 committee
   committee

                                                                Public Fund
                                                                  Account
        ZEN E                                                   Management
     (Electricity)   ZEN Transport     EV Expo Working           Committee
    Working group    Working Group          Group
      (Projects)       (Projects)




                                                                              14

Page 15

Appendix B
                          ZERO EMISSIONS NOOSA Inc

                   ZEN Inc STRATEGIC PLAN 2023-2026




Introduction

Our vision is for net zero emissions in Noosa Shire.

Zero Emissions Noosa Inc seeks to make Noosa Shire a leading local government region in zero
emissions. We seek to do this by supporting the community in the transition to net zero emissions
through project leadership, advocacy, and the provision of information to all sections of the Noosa
community.

Our strategic plan outlines how we will achieve this mission as we seek to seize new opportunities
and meet the challenges of the future. While our strategic plan is future focussed it is grounded in our
contemporary operating environment which is heavily influenced by the pressures on our resource
base – both financial and human.

Since ZEN Inc was founded in 2016, the need to reduce emissions is more pressing than ever if we
are to avoid catastrophic climate change. The transition to a cleaner energy future has seen more
changes and challenges than at any time in recent years. Meeting the needs of our community in this
space is a major challenge, but also a significant opportunity.

This strategic plan sets out our vision for the future and a framework for its delivery over the next
three years. It includes:

    •   our vision for net zero emissions in Noosa Shire.
    •   the roles that define where we will work to deliver the vision.
    •   our aims within those roles; and
    •   an outline of our priorities in delivering those aims.

Through our planning process we have developed strategic priorities for the next three years framed
around our two key goals:

    •   Promoting community actions to achieve net zero emissions.
    •   Developing a sustainable organisation

This strategic plan is not a static document and the Board, and its working groups will give ongoing
consideration to ideas and suggestions that have been put to us as well as giving consideration to an
increasingly dynamic and challenging environment throughout the period of this plan.
Each year we will report on how we have delivered on this strategy at our annual general meeting and
through our annual report.

Organisational Description

Zero Emissions Noosa Inc (ZEN Inc), established in 2016, is an incorporated, not-for-profit,
community organisation with the key objective of assisting the Noosa community achieve net zero
emissions in the Noosa local government area. ZEN Inc has been actively pursuing several strategies
aimed at achieving this objective.


                                                                                                        15

Page 16

It is the leading community organisation in this field and the only community organisation solely
dedicated to emissions reduction across the Noosa Shire.

The two key objectives of the organisation have been to drive projects in the stationary electricity and
transport areas aimed at assisting individuals, businesses, and the community at large, in contributing
to emissions reduction.

The core work of the organisation is carried out by two working groups – ZEN E (Electricity) and ZEN
TAG (Transport). The focus of ZEN E’s work is on projects that assist in reducing emissions in the
stationary electricity sector with initiatives that assist a greater uptake of solar as well as storage and
other initiatives. ZEN TAG’s focus is on reducing emissions from transport by encouraging, advocating
and demonstrating low emissions alternatives to the dominant petrol / diesel driven motor vehicle. The
annual EV Expo is ZEN Inc’s flagship event in this regard.

Organisational support is provided through the work of three sub-committees; Finance & Fundraising;
Governance & Operations; and Communications & Advocacy.




                                   ZEN Inc Board




   Governance &             Finance &              Communications &
    Operations             Funding sub-              Advocacy sub-
       sub-                 committee                 committee
    committee

                                                                      Public Fund
                                                                        Account
          ZEN E                                                       Management
       (Electricity)       ZEN Transport      EV Expo Working          Committee
      Working group        Working Group           Group
        (Projects)           (Projects)




Vision

Net zero emissions in Noosa Shire.

Mission

Working with the Noosa community to achieve net zero emissions to address climate change.

Core Values / Values Statement

             Values                            Thinking                               Behaviour
 Honesty                             Independent                           Respected
 Transparency                        Inclusive                             Collaborative
 Accountability                      Evidence based                        Inspirational
 Ethical                             Excellent                             Empowered

Our values statement describes how ZEN Inc works internally and externally.



                                                                                                        16

Page 17

ZEN Inc works independently to provide leadership by empowering its members and stakeholders
with ethical, independent, evidence-based solutions for reducing Noosa’s net greenhouse gas
emissions to zero. We do this by operating in an honest, accountable, collaborative, and inclusive
way.


Goals

Our goals are the key focus areas that will move the organisation to achieve its vision and its mission.

We have identified two goals for 2023 – 2026:

Goal 1: Promoting community actions to achieve net zero emissions.

                We will continue to focus on our core business. We will provide leadership and
                management of projects and initiatives that help the Noosa community on its journey
                towards net zero emissions.

Goal 2: To be a sustainable organisation.

                We recognise that for ZEN Inc to fulfill its vision and mission it must be a well-
                resourced and efficient organisation.

Objectives

Our objectives support the two key goals identified above. Our outcomes describe how we will
measure the progress needed.

                       Objectives                               Outcomes / Measures of success

 1.1 Reduced business and household stationary
     energy emissions.

 ZEN Inc will focus on its core project work to deliver          •   Projects delivered within agreed
 emissions reduction initiatives to the Noosa                        timeframes.
 community.                                                      •   Business and household
                                                                     emissions reduced

 1.2 Reduced transport energy emissions

 ZEN will focus on promoting transport initiatives and           •   Increased use of sustainable
 sustainable transport options that reduce greenhouse                transport options including public
 gas emissions.                                                      transport, unpowered vehicles
                                                                     and walking
                                                                 •   Increased uptake of electric
                                                                     powered vehicles (EVs) and
                                                                     reduced use of internal
                                                                     combustion vehicles (ICEVs)

 1.3 Increased community awareness of initiatives
     to reduce emissions

 ZEN Inc will provide information to the community to            •   Increased community uptake of
 assist in the implementation of emissions reduction                 information and tools
 actions.                                                        •   Effective dissemination of
                                                                     information through ZEN Inc’s
                                                                     website.and other channels.
                                                                 •   Increased participation through
                                                                     community engagement.


                                                                                                        17

Page 18

 2.1 Increased financial sustainability

 ZEN Inc will work to ensure that it is a financially          •   Ongoing funding secured.
 sustainable organisation by aiming to secure ongoing          •   Funding sources diversified
 funding and by diversifying its funding sources.

 2.2 Efficient organisational operations

 ZEN Inc will continue to develop its resource base and        •   Continue a culture of continuous
 review its processes and procedures to be an efficient            improvement.
 and effective organisation.                                   •   Governance & Operational
                                                                   manual developed.
                                                               •   Processes and procedures
                                                                   refined and rationalised

 2.3 Effective external and internal communications

 ZEN Inc will develop effective internal initiatives to        •   Increased community awareness
 enhance the way we work and increase awareness                    of ZEN (who we are; what we do)
 amongst the community of who we are and what we               •   Brand strategy developed
 do.

 2.4 Strong strategic relationships.

 ZEN Inc will build on and further develop strong              •   Increased engagement with
 strategic relationships with our stakeholders to                  stakeholders.
 collaborate in reducing emissions.                            •   Collaborative and productive
                                                                   partnerships strengthened and
                                                                   widened
                                                               •   Respective roles of ZEN Inc and
                                                                   Noosa Council are mutually
                                                                   beneficial.


Situation Analysis

In developing this strategic plan, we examined the internal and external environment in which the
organisation operates with a view to addressing some of the threats that we face while seeking to
maximise the opportunities before us.

Since its formation in 2016, ZEN Inc has had, as its vision, “net zero greenhouse gas emissions
across the Noosa region by 2026”. While progress has been made in reducing emissions across the
Noosa Shire, realistically we have no agreed way of measuring whether we will achieve that goal
within the stated timeframe.

While ZEN Inc remains strongly committed to its mission to achieve net zero emissions, we have
dropped the 2026 timeline from our vision statement and modified it accordingly.

We recognise that we are operating in a rapidly changing environment. While that poses threats as to
whether we have the capacity and resources to manage those challenges, we hope to capitalise on
the opportunities presented by the changing environment. The strength of the organisation lies in a
highly experienced and committed Board and a volunteer and supporter base committed to taking
practical action to help reduce emissions across the Noosa Shire.

Internally, the organisation lacks a strong financial base and some strengthening of our governance
arrangements will assist the way we work. Our undoubted strength is our commitment to several key
project initiatives that have firmly placed the Noosa Shire as a leading local government area on the
road to a net zero emissions future. However, while our key focus remains on our project work, we
recognise that our project teams need to be supported by a well-resourced and efficient organisation.


                                                                                                      18

Page 19

Building on our signature strength of innovative project work, our strategic plan continues to focus on
project delivery that helps the community move towards a reduction in net zero emissions. For
example, the “Electrify Australia” movement led by Saul Griffith offers significant opportunities for ZEN
Inc to assist the community at the local level. Providing guidance in helping households to “electrify
the home” while also developing initiatives that will assist in “electrifying everything” presents us with
several opportunities.

Federal Government policy and funding initiatives also provide opportunities which ZEN Inc will
continue to embrace.

While we have enjoyed several high-profile successes, there is a recognition that our communications
could be improved to maximise the impact of our initiatives and more time needs to be spent on
stakeholder engagement. The benefits that our work brings to the community, as the leading source of
information on emissions reduction in the Noosa LGA, needs to be better explained.

Demonstrating how we deliver benefits to the Noosa community is both a challenge and an
opportunity.

A lack of brand identity could be strengthened as there is a perception that ZEN Inc’s. is done by
Council.
There is an opportunity for both ZEN Inc and Noosa Council to clarify our respective roles to work
collaboratively to assist the Noosa community on its journey to net zero emissions.

The provision of community education on emissions reduction strategies offers an ongoing
opportunity.

Strategies

The key priorities and higher-level elements identified through our SWOT analysis have informed our
strategies. The strategies inform the ZEN E and ZEN TAG plans and the activities of our three sub-
committees.




                                                                                                       19

Page 20

                                                      ZEN’s GOALS, OBJECTIVES & STRATEGIES

                                        GOAL 1                                                                                              GOAL 2

       Promoting community actions to achieve net zero                                                                  To be a sustainable organisation
                       emissions

  OBJECTIVE 1.1                 OBJECTIVE 1.2                     OBJECTIVE 1.3                  OBJECTIVE              OBJECTIVE 2.2           OBJECTIVE 2.3          OBJECTIVE 2.4
                                                                                                    2.1

 Reduced business and         Reduced transport energy           Increased community            Increased financial           Efficient          Effective external       Strong strategic
  household stationary              emissions                  awareness of initiatives to         sustainability          organisational           and internal           relationships
   energy emissions                                                reduce emissions                                          operations          communications


    STRATEGIES                    STRATEGIES                       STRATEGIES                   STRATEGIES               STRATEGIES              STRATEGIES              STRATEGIES

Undertake targeted, large    Promote transport initiatives     Greater direct engagement           Build a strong          Strengthen well      Increase awareness    Strengthen and broaden
   impact projects to        that reduce greenhouse gas      initiatives with the Noosa Shire   financial position to      connected and             amongst the          collaborative and
  maximise emissions                  emissions                          community                  support our         collaborative working    community of who     productive partnerships
       reduction                                                                                    projects and          groups and sub-       we are and what we
                                                                                                      activities              committees                   do
 Encourage community           Encourage walking and           Develop online toolkits to        Apply for Federal,         Develop clear       Maintain ZEN Inc as      Increase reach and
 initiatives that support         cycling initiatives        facilitate energy transition and    State and Council      processes to support         a significant    influence as the leading
  uptake of renewable                                               emissions reduction               funding            the organisation in        contributor to    community organisation
          energy                                                                                                            the delivery of     emissions reduction    advocating emissions
                                                                                                                         projects, events &       within the Noosa            reduction.
                                                                                                                               programs                  Shire.
  Develop the “electrify       Promote carbon capture            Effectively disseminate         Diversify funding                 .             Ensure benefits of       Work with Noosa
   everything” concept       technologies and initiatives    information through ZEN Inc’s           sources                                         projects and     Council in differentiated
 across the Noosa Shire           to offset car travel              website and other                                                                activities are   roles for mutual benefit.
                                                                communication channels.                                                           communicated to
                                                                                                                                                     stakeholders
Ensure battery initiatives    Review Noosa Council’s                                            Examine potential                                  Foster effective
  are delivered within        Transport Strategy and                                            revenue streams                                    communication
  agreed timeframes           make recommendations                                                                                                 pathways both
                                                                                                                                                    internally and
                                                                                                                                                       externally
Implement Solar for Strata   Review commitment to EV                                                                                               Develop a ZEN
       initiatives                    Expo..                                                                                                       brand strategy




                                                                                                                                                                                             20

Page 21

  Progress the concept of           Advocate for, and
 an energy hub at Peregian     demonstrate, sustainable
   Beach / Marcus Beach           transport options for
                                 transport that reduce
                              greenhouse gas emissions.
   Advocate for EUAs for
     residential dwellings,
  including for low-income
 households, landlords and
            tenants
  Examine methodologies
    for carbon accounting


See page 8 to follow




                                                          21

Page 22

Key Actions

The Strategic Plan is our overarching planning document and guides the work of our working groups and
sub-committees.

Specific actions will be progressed through the two working groups and three sub-committees to give
effect to the strategies identified in the Strategic Plan


Monitoring and Evaluation


Our planning and reporting framework is designed to support the implementation of this plan and the
realisation of our vision for an emissions free Noosa.

The strategic plan identifies the key measures of our success and the outcomes that we hope to achieve
as measured against our two key focus areas (goals) and the strategies we will employ.

Performance against these outcomes will be reviewed, where possible, throughout the year but at least
once each year, and reported to enable the Board to monitor progress.

Working groups are encouraged to develop measures of success for their respective projects and
activities as outlined in their action plans.


Prepared:       August 2023 (Org. Chart updated Feb. 2025)


Email:          [email protected]

Website:        www.zeroemissionsnoosa.com.au


Appendix:       The SWOT Analysis

Strengths (Internal)

Committed and experienced Board
Existing runs on the board
Existing connections with groups / individuals
Members and volunteers
Strong relationship with Council
Reputation / credibility
Organisational basics in place
Large database on emissions reduction information
Consistent communication capability
ZEN Inc. uses evidence-based solutions

Weaknesses (Internal)

Over reliance on the ZEN Chair
Insufficient people to delegate to
Insufficient paid human resources
Lack of participation in working groups
Lack of human resources to implement information management systems (shared drive / website)
Lack of financial sustainability

Opportunities (External)

Working with Noosa Council
Other zero emissions communities e.g. ZEB

                                                                                                        22

Page 23

Rewiring Australia (stakeholders, YEF)
Diversification of funding sources
Federal / State governments (engagement, advocacy, grants)
Tap into community sentiment
Clarify carbon accounting (support)
Stakeholders (e.g. universities)
Industry
Community benefits (financial, environmental, sustainability, health)
Information sources


Threats (External

Disbelief within the community
Current 2026 goal maybe unachievable
Too much to do…may get lost
Seen as an “arm” of Noosa Council; who does what (vis a vis ZEN / Council)
Funding resources
ESG (Environmental, Social and Governance)
Changing government priorities
Insufficient paid human resources




                                                                             23

Page 24

Appendix C - 2024 -2025 ZEN E Working Group Action Plan (5)




ZEN Inc. 2024 -2025 ZEN E Working Group Plan Action Plan          Reviewed & Updated Aug., 2024 v. 5. KPI’s updated Feb., 2024
See notes below re links from Council’s Corporate Plan Themes & associated plans to the ZEN E Working Group Action Plan.

 Goal 1 (As per ZEN Inc. Strategic Plan): Promoting community actions to achieve net zero emissions

 OBJECTIVE 1.1 Reduced business and household stationary energy emissions


 ZEN Inc. STRATEGIES          ZEN e Projects         Timeframe / KPI              Project Lead & Group    Noosa Council
                              (What)                 (How)                        Members (Who)           Climate Change
                                                                                                          Response Plan
                                                                                                          (CCRP) Themes &
                                                                                                          Economic
                                                                                                          Development
                                                                                                          Strategy 2021-2030:
                                                                                                          Outcomes & Benefits
     1. Undertake targeted,   All projects           See KPI’s for each project                           Theme 1: Leadership
 large impact projects to                            below                                                and governance
 maximise emissions                                                                                       1.1 Mobilise community
 reduction                                                                                                for climate action
 Community Batteries                                                                                      1.2 Action for low
 Rewiring Noosa -                                                                                         carbon economy &
 “Electrify Everything”                                                                                   resilient
 Solar for Strata                                                                                         community
                                                                                                          1.3 Council is a
      2. Encourage            All projects           See KPI’s for each project                           powerful influencer for
          community                                  below                                                climate action
 initiatives that support
                                                                                                                                    24

Page 25

uptake of renewable
energy
Solar for Strata
Rewiring Noosa -
“Electrify Everything”

    3. Develop the         a.Rewiring Noosa -             Advocate/promote to
         “electrify        “Electrify Everything” –       external organisations &                            Theme 2: Energy
everything” concept        Stage 2 - roll out to trades   speak at 4 forums by June                           efficiency and
across the Noosa Shire     people (Rewiring Noosa                                     Surfers for Climate -   renewable energy
                                                          2025
Rewiring Noosa -                                                                      “Trade Up” (Anne)       1.1 & 1.2
                           Plan says 655 x local jobs     - Clean Energy Council
“Electrify Everything” -
Stages 1 & 2               available)                     roadshows.                  Cleantech Network       Theme 3: Clean low
                           e.g. Surfers for Climate -     In progress                 (Anne)                  emissions industries
                           “Trade Up”;                                                                        3.1 & 3.2
                           -Cleantech Network;                                        TAFE & Environmental
                           -TAFE                                                      Education Hub (Anne);   Theme 7: Resilient &
                           -Environmental Education                                                           adaptive communities
                                                                                      ZENDURO project         &
                           Hub - STEM subjects;
                                                                                      (Gillian Carter);       built environments
                           - ZENDURO project –                                        Electrical Trades       7.1 & 7.2
                           STEM subjects;                                             Association (Mark)
                           - Electrical Trades                                        Plumbing Trades         Theme 6: Sustainable
                           Association;                                               Association (Mark)      agriculture and food
                           - Plumbing Trades                                                                  systems
                           Association;                                                                       6.3 Support agri-
                                                                                                              businesses &
                           - Electrical wholesalers in
                                                                                                              landholders a & b
                           Noosa e.g. Lawrence &
                           Hanson                                                                             Increased number of
                                                                                                              high value jobs that
                                                                                                              retain local talent

                                                                                                              A skilled and talented
                                                                                                              workforce driving
                                                                                                              innovation

                                                                                                                                       25

Page 26

                        b. Powershare (Powervolt)      By March 2026 (if ARENA      Ewan                    Theme 3: Clean low
                        A concept being                funded)                                              emissions industries
                        developed for potential                                                             3.1& 3.2
                        funding from the ARENA         Did not go head.
                        Solar Scale Up                                                                      Theme 7: Resilient &
                                                       Not Funded
                        Competition to bring the                                                            adaptive communities
                        cost of large scale solar to                                                        &
                        less than 30c/watt                                                                  built environments
                        installed, with a potential                                                         7.1 & 7.2
                        site in Noosa.
                                                                                                            Collaborative and
                                                                                                            connected business
                                                                                                            Ecosystems are
                                                                                                            created

                                                                                                            Relevant and
                                                                                                            impactful
                                                                                                            support provided to
                                                                                                            our businesses

    4. Ensure battery   a.Community Batteries:         Noosa Comm Battery           Anne & Colin & ZEN E    Theme 2: Energy
        initiatives     i.Noosa Community              installed by 30 Jun 2025.    Working Group members   efficiency and
are delivered within    Battery                                                                             renewable energy
agreed timeframes        a. Assist with community      By 30 May, 2024              Anne/Colin              1.2 & 1.3
Community Batteries     consultation in park           In progress but delayed
                                                       due to lengthy
                                                       negotiations with Energex    Anne/Colin              Theme 3: Clean low
                                                                                                            emissions industries
                        b.Advocacy for 100 – 200       Ongoing advocacy to                                  3.1 & 3.2.
                        community batteries in         Energy Qld. through LREZ
                        Noosa LGA                      consultation for more                                Theme 7: Resilient &
                                                       community                                            adaptive communities
                                                       batteries/community energy                           & built environments
                                                       resources. Done & Ongoing                            7.1 & 7.2

                                                       By 30 September, 2024                                Infrastructure
                                                       Done                                                 accelerates
                                                                                                                                   26

Page 27

c.Follow up AER response By mid-December, 2024      Anne/Colin & consult    industry development
to Tariff review         Done                       Vivien Griffin          and
submissions.                                                                Smart Precincts

                         By 30 September, 2024      Anne/Colin & consult    Collaborative and
d. Follow up Energy      Done                       Vivien Griffin          connected business
Queensland re final                                                         Ecosystems are
submission of TSS to AER                                                    created

e. Follow up Ausgrid       From Aug. 2024 to        Anne/Colin & consult    Expanded and
LUOS tariff approach to    completion early 2026    Vivien Griffin /Annie   specialised
                           Ongoing                  Nolan                   education and
encourage uptake of
                                                                            research
Community Batteries.                                                        opportunities
(Ausgrid have a positive
approach to encourage                                                       Relevant and
uptake of Community                                                         impactful
Batteries)                                                                  support provided to
                                                                            our
                                                                            businesses
f. Participate in AEMC
                           To be Done               Anne/Mark/Colin         Businesses
Pricing Review TOR                                                          maximising the
development.                                                                global opportunities
                                                                            and
g.Continue advocating to   By March, 2025                                   selling to the world
Energy Qld. for ZEN Inc.   Done in Oct.,2024 & is   Anne/Colin
                           Ongoing
to be represented on a
possible Qld. Consumer
Energy Roadmap
consultative group.

h.Follow up existing       Ongoing                  Anne
relationships with Solar
Citizens and Re-Alliance
re Local Energy Hubs.
                                                                                                   27

Page 28

                           i.Look for opportunities for   Done Jan. 2025 &             Colin/Anne
                           future battery cross over      Ongoing
                                                          See d & f below
                           with the Solar for
                           Business project
                           (apartment batteries).

                           ii. Qld. Govt. Community                                                         As above
                           Battery Roadmap –
                           Business Plan for a
                           Roadmap of Community
                           Batteries in Noosa LGA
                                a. Distribute to key
                                    ZEN Inc.              By 30 Sept.,2024             Anne
                                    stakeholders          Done

                              b. Follow up with           By 30 Nov., 2024             Anne, Colin & Mark
                                 Dept. of Energy &        Done.
                                 Climate re
                                 distribution of key
                                 stakeholders State
                                 -wide

5. Assist for Low Income   c.Energy Efficiency                                         Colin & Jenny        Theme 2: Energy
households                 Assessments &                                                                    efficiency and
                           Upgrades of 20 Low                                                               renewable energy
                           Income Homes                   By 30 Dec. 2024                                   1.3 & 1.4
                           i. Follow up with Coast 2      Done but with very limited
                           Bay; St Vinnies;               success due to difficulty                         Theme 3: Clean low
                           Community Health; You          engaging low income                               emissions industries
                           Turn, etc. for client’s        clients through social                            3.1 & 3.2
                           homes to work with             welfare agencies.
                                                                                       Colin                Theme 7: Resilient &
                           ii. Contact Gary at Energy                                                       adaptive communities
                           Flex & QCOSS                   By 30 Sept., 2024                                 &
                           (Queensland Council of         Done                                              built environments
                                                                                                                                   28

Page 29

                                Community Services)                                                           7.1 & 7.2
                                 for recommendations of
                                an assessor to take part in                                                   Enhancing our
                                the project                                                                   natural
                                                                                             Colin            assets with
                                iii. Appoint assessor(s) for   Assessments by a qualified                     technology
                                energy audits                  energy assessor                                driving value
                                                               Delayed due to difficulty
                                                               engaging low income           Colin/Jenny
                                                               clients through social
                                                               welfare agencies.

                                iv. Energy efficiency          Upgrades by 30 June 2025
                                upgrades e.g. LED lights;      Council Grant variation to
                                curtains & external blinds     now fit solar due to
                                for shading;                   difficulty engaging low
                                                               income clients through
                                                               agencies
6. Implement Solar for Strata   d. Solar for Strata- “value    By 30 June, 2025 -            Jenny & Colin    Theme 2: Energy
         initiatives            add”                           Presentations to Noosa                         efficiency and
                                Promoting on line toolkit &    Chamber of Commerce &                          renewable energy
                                video by:                      Tourism Noosa                                  1.4 & 1.5
                                i.Forums for bodies            Tourism Noosa done.
                                corporates, incl.                                                             Theme 3: Clean low
                                a. Commercial/ industrial      Promotion of Online toolkit   ‘Jenny & Colin   emissions industries
                                                               & videos in newsletter,                        3.1 & 3.2
                                strata case studies
                                                               July/Nov., 2024
                                (Chambers of Commerce)         Discussions ongoing.                           Theme 7: Resilient &
                                                                                                              adaptive communities
                                c.Tourism Strata               Possible forum with           Jenny & Colin    &
                                complexes (Tourism             Tourism Noosa                                  built environments
                                Noosa)                         Done in Oct., 2024.                            7.1 & 7.2

                                                               Possible forum with Noosa     Jenny & Colin    Increased number of
                                d.Residential (Team Body
                                                               Chamber of Commerce                            high value jobs that
                                Corporate)                     Discussions ongoing.                           retain local talent

                                                                                                                                     29

Page 30

                            e.Advocate for LREZ to          Ongoing as opportunities    Anne/Colin/Mark/         A skilled and talented
                            relax Strata Requirements       arise with development of                            workforce driving
                                                            the LREZ Pilots                                      innovation
                                                            Done.
                                                                                                                 Infrastructure
                            f. Investigate Standalone       Dec., 2024, investigate     Colin with Matt Harold   accelerates
                            Batteries as an alternative     suitability for ZEN E                                industry development
                            to solar                        Projects                                             and
                                                            Ongoing                                              Smart Precincts

                                                                                                                 Collaborative and
                                                                                                                 connected business
                                                                                                                 Ecosystems are
                                                                                                                 created

                                                                                                                 Relevant and
                                                                                                                 impactful
                                                                                                                 support provided to
                                                                                                                 our
                                                                                                                 businesses

7. Assist with EV &         a.EV & Electrify                By June, 2025               Expo Working group       Theme 2: Energy
Electrify Everything Expo   Everything Expo                 In Progress                                          efficiency and
                            Work in conjunction with                                                             renewable energy
                            Expo Working group for                                                               2.1 & 1.6
                            “Electrify Everything”
                            component                                                                            Theme 3: Clean low
                            EV mini expos (show &           2  mini expos show & tell   Expo Working group       emissions industries
                            tell) – book location, invite      by 30 Jun 2025                                    3.1 & 3.2
                            EV owners to come, invite       Not go ahead due to
                            public to come                  insufficient volunteers                              Theme 7: Resilient &
                                                                                                                 adaptive communities
                                                                                                                 & built environments
                                                                                                                 7.1 & 7.2

                                                                                                                 As for no. 6 above

                                                                                                                                          30

Page 31

8. Solar For         a. Solar For                 Ongoing, including              Colin & Anne   Theme 2: Energy
Business/Community   Business/Community           connection to community                        efficiency and
Buildings            Buildings - Energy           batteries project                              renewable energy
                     Sharing with VPP’s
                                                  Vivien to send Colin original   Colin & Anne   Theme 3: Clean low
                     Solar/Energy Sharing                                                        emissions industries
                                                  database by 15 Sept., 2024
                     i.explore stakeholders &                                                    3.1 & 3.2
                     opportunities in:            Done
                     a. residential                                               Colin          Theme 7: Resilient &
                     neighbourhoods                                                              adaptive communities
                     b. C&I estates e.g. Noosa    Delayed due to shortage         Anne           &
                     Chocolate Factory as a       of volunteers                                  built environments
                     case study; [email protected] & 7.2
                     Cooroy

                                                  For info. on possible C&I                      As for no. 6 above
                     ii.Liaise with Cleantech                                     Colin
                     Network members &            clustering by 30 Nov., 2024
                     Chamber of Commerce.         Ongoing


                     iii. Use Nearmaps (to
                     assess and identify          Check ZEN’s subscription        Colin
                     businesses within Noosa      to Nearmaps
                     Shire which do not           Done
                     currently have solar)

                     iv. Schools – Follow up
                     from Race 2 Zero Schools     Liaise with Dalia @ Noosa
                                                  EE Hub by 30 Nov., 2024         Colin & Anne
                     (large roof areas usage
                     only during schools hours    Not done due to volunteer
                     e.g. Good Shephard & St      overload
                     Therese’s). Do a Financial                                   Mark P
                     ROI feasibility              Mark to develop a Financial
                     presentation to show the     ROI / Feasibility
                     financial reward of          Presentation by 30 Nov.,

                                                                                                                        31

Page 32

                        installing large scale solar   2024 Not done due to
                        and batteries to create        volunteer overload
                        additional income stream

                        v.Investigate potential to     By 30 Nov., 2024           Colin
                        work with Sollar Alliance /    Delayed due to of
                        Clear Sky Solar. LINKS:        volunteer overload
                        ClearSky Solar
                        Investments, Solar
                        Alliance - Solar Alliance
9. Gather Data & data   a. Data                        By Dec., 2024              Rosemary   Theme 2: Energy
Analysis                i. Develop usage vs            Delayed due to                        efficiency and
                        savings calculator matrix.     volunteers stepping back              renewable energy
                                                       from ZEN Inc.                         2.2 & 1.7
                        UQ have data available
                        for general usage.                                        Brian      Theme 3: Clean low
                        ii. Gamify Local Data          Description - Colin to
                                                                                             emissions industries
                                                       provide
                                                                                             3.1 & 3.2

                                                                                             Theme 7: Resilient &
                                                                                             adaptive communities
                                                                                             &
                                                                                             built environments
                                                                                             7.1 & & 7.2

                                                                                             Theme 6: Sustainable
                                                                                             agriculture and food
                                                                                             systems
                                                                                             6.3 Support agri-
                                                                                             businesses &
                                                                                             landholders to:
                                                                                                 a. Reduce their
                                                                                                    emissions
                                                                                                    technology
                                                                                                    implementation

                                                                                                                     32

Page 33

                                                                                                                 b. Take up
                                                                                                                    opportunities for
                                                                                                                    income
                                                                                                                    generation
                                                                                                                    through carbon
                                                                                                                    drawdown

                                                                                                              As for no. 3 above
10. Examine               Emissions reduction          Work with Noosa Council        Noosa Council           Theme 3: Clean low
methodologies             barometer                    Discussions starting with                              emissions industries
for carbon accounting                                  NBRF & Council                                         3.1 & 3.2

                                                                                                              Theme 7: Resilient &
                                                                                                              adaptive communities
                                                                                                              &
                                                                                                              built environments
                                                                                                              7.1 & 7.2

                                                                                                              As for 6a above.
OBJECTIVE 1.3 Increased community awareness of initiatives to reduce emissions
STRATEGIES                 ZEN e Projects             Timeframe / KPI          Project Lead & Group
                           (What)                     (How)                    Members (Who)
     1. Greater direct     Community engagement i.Libraries – one per quarter Mark, Colin, Anne,              Theme 2: Energy
         engagement        forums on:                 till 30 June, 2025       Rosemary                       efficiency and
initiatives with the Noosa a. Rewiring Noosa -        In progress                                             renewable energy
Shire community            “Electrify Everything” - &                                                         2.3 & 1.8
                           promotion of On Line
         .                 “Electrify Everything”                                                             Theme 3: Clean low
                           Toolkit & Videos                                                                   emissions industries
                                                                                                              3.1 & 3.2
                          b. Community Group           ii.3 presentations by 30 Jun   Colin, Mark, Adrian,
                          Forums on:                   2025 to Clubs e.g. Rotary,     Brian, Anne, ZEN E      Theme 7: Resilient &
                          Rewiring Noosa -             Probus, Lions, U3A, etc        Working Group members   adaptive communities
                          “Electrify Everything” - &    In progress with U3A.                                 &
                          promotion of On Line         Probus & service Clubs                                 built environments
                          “Electrify Everything”       not interested.                                        7.1 & 7.2
                          Toolkit & Videos
                                                                                                                                        33

Page 34

                                                                                    As for no. 3 above
C i. Community                  2 presentations by 30 Jun     Colin/ Mark           Theme 2: Energy
Education Forums e.g.           2025                                                efficiency and
Energex’s planned 2 way                                                             renewable energy
pricing & “Demand”              Presentations by Mark/Colin   Colin/ Mark           2.4 & 1.9
pricing; Controlled load bill   Delayed due to volunteer
reading;                        overload                                            Theme 3: Clean low
household & business                                                                emissions industries
energy efficiencies; smart                                                          3.1 & 3.2
home products &
solutions for timing energy                                                         Theme 7: Resilient &
use (solar & use of smart                                                           adaptive communities
meters) for time of use;                                                            &
Better estimates of pay                                                             built environments
back periods & More                                                                 7.1 & 7.2
information about feed-in
tariffs; complete off grid                                                          As for nos. 6 & 9
set up; cheaper chargers                                                            above
for work solar carparks;
EV comparison websites;
Grants or government
rebates; Financing; Green
energy purchasing;
Rebates for people to
change to
electrify.

ii. Solar/storage &             Incorporated into Solar for   Matt Harold/Gareth/
electrification for Strata,     Strata talks                  Ewan                  As for nos. 6 above
Businesses & Residential
(includes stand- alone
batts)

iii. Carbon Footprint           Delayed due to volunteer      Colin
Presentation to Board &         overload                                            As for nos. 6 above
associated ZEN reps. &
business
                                                                                                           34

Page 35

                               b.EV & Electrify           By June, 2025                  Expo Project Working
                               Everything Expo            In progress                    group                     As for nos. 6 above

                               c. Community Batteries     By Dec., 2024                  Vivien Griffin, Anne
                               – community consultation   Preparation in progress.       Kennedy & Annie Nolan
                               for Noosaville Battery     Delayed due to lengthy         (Council)                 As for nos. 4 above
                                                          negotiations with Energex
    2. Promote online          a.Rewiring Noosa -                                                                  As for no. 1a above.
         toolkits/reports to   “Electrify
facilitate energy transition   Everything” – see 1a
and emissions reduction        above

                               b. Solar for Strata –      See 3a above.                                            As for 1d above.
                               Toolkit & Videos                                                                    As for nos. 6 above

                               c.Community Batteries -    Distribute to key              Anne Kennedy & ZEN        As for no. 1bi & ii
                               a Business Plan for a      stakeholders & other LGAs      Inc. Admin. Coordinator   above.
                               Network of Community       as needed.
                               Batteries in Noosa LGA     Done & in progress                                       As for nos. 4 above

    3. Effectively             a.Work with Comms. &       Ongoing so all project         Chair ZEN E & Chair       Theme 2: Energy
       disseminate             Advocacy Committee to      promoted at least x2 per       C&A & ZEN Comms.          efficiency and
information through ZEN        promote all ZEN E          year                           Officer                   renewable energy
Inc’s website and other        projects using:            In progress                                              2.5 & 1.10
communication channels.
                               i. Print media             i. Fortnightly columns in                                Theme 3: Clean low
                                                          Noosa Today & monthly                                    emissions industries
                                                          columns in Your Local                                    3.1 & 3.2
                                                          Lifestyle In progress
                               ii. Social media           ii.Fortnightly posts about                               Theme 7: Resilient &
                                                          one ZEN Inc. project                                     adaptive communities
                                                          In progress                                              &
                               iii. Website               iii. Ongoing project updates                             built environments
                                                          In progress                                              7.1 & 7.2
                               iv. Newsletters            iv. Feature a ZEN Inc.
                                                          project every month                                      As for nos. 6 & 9

                                                                                                                                          35

Page 36

                                                          In progress                                         above

   A. Noosa Council’s Corporate Plan themes & Associated Plans relevant to the ZEN E Working Group Action Plan

 Corporate Plan theme     Relevant Associated Plans to ZENTAG Action Plan
    1. Environment        Noosa Environment Strategy 2019
                          Climate Change Response Plan
                          Noosa Transport Strategy 2017 - 2027 - development of a new movement and connectivity strategy.

    2. Liveability        Noosa Transport Strategy 2017 - 2027 - development of a new movement and connectivity strategy
                          - Cycling and Walking Strategy and Implementation Plan 2020
                          - Noosa Trails Masterplan and Implementation Plan 2020.
                          Noosa Housing Strategy 2021
                          Noosa Social Strategy and Social Justice Charter – new Community Strategy.
                          - Noosa Health and Wellbeing Plan 2019 -2024.
    3. Prosperity          Economic Development Strategy 2021 – Smart Biosphere
                           Waste to Resource Strategy
    4. Future             Community Strategy – New Community Strategy.
                          Climate Change Response Plan
                          Noosa Design Principles
                          Disaster Management Plan
                          Local Disaster Recovery Plan
                          Destination Management Plan
                          Economic Development Strategy
                          Waste Strategy (currently under development)
    5. Excellence         Community Engagement Framework


   B. Noosa Council Climate Change Response Plan (CCRP) Themes relevant to the ZEN E Working Group Action Plan
Theme 2: Energy efficiency and renewable energy
1.1 ….100% renewable energy incl. low income & vulnerable residents, businesses, incl. strata tenants
1.2 ….Develop a climate aware and empowered community for reducing climate risks & emissions
1.3 Develop a climate aware and empowered community for reducing climate risks & emissions
1.4 Develop a climate aware and empowered community for reducing climate risks & emissions
1.5 Develop a climate aware and empowered community for reducing climate risks & emissions
1.6 Develop a climate aware and empowered community for reducing climate risks & emissions
                                                                                                                            36

Page 37

1.7 Develop a climate aware and empowered community for reducing climate risks & emissions
1.8 Develop a climate aware and empowered community for reducing climate risks & emissions
1.9 Develop a climate aware and empowered community for reducing climate risks & emissions
1.10 Develop a climate aware and empowered community for reducing climate risks & emissions
Theme 3: Clean low emissions industries
3.1 …..shift to clean, green low emission industries & technology
3.2 ….. Facilitate emissions reduction & environmental sustainability for local businesses
Theme 7: Resilient & adaptive communities &
built environments
7.1 Create a resilient built environment for householders, businesses, vulnerable people, property & infrastructure
7.2 Build community awareness & preparedness for climate change & extreme weather events

Theme 6: Sustainable agriculture and food systems
6.3 Support agri-businesses & landholders to:
    a. Reduce their emissions technology implementation
    b. Take up opportunities for income generation through carbon drawdown
C. Noosa Council Economic Development Strategy 2021-2030: Outcomes & Benefits relevant to the ZEN E Working Group Action Plan
1. Increased number of high value jobs that retain local talent
2. A skilled and talented workforce driving innovation
3. Infrastructure accelerates industry development and Smart Precincts
4. Collaborative and connected business Ecosystems are created
5. Expanded and specialised education and research opportunities
6. Relevant and impactful support provided to our businesses
7. Businesses maximising the global opportunities and selling to the world
8. Enhancing our natural assets with technology driving valu




                                                                                                                                37

Page 38

Appendix D - ZEN Inc. 2024 – 2025 ZENTAG Working Group Action Plan (4)




ZEN Inc. 2024 ZENTAG Working Group Action Plan                             Reviewed & Updated Sept.., 2024 v. KPI’s updated Feb., 2024

*Subject to funding – application has been submitted. Awaiting outcome.
See notes below re links from Council’s Corporate Plan Themes & associated plans to the ZENTAG Working Group Action Plan.

 Goal 1 (As per ZEN Inc. Strategic Plan): Promoting community actions to achieve net zero emissions

 OBJECTIVE 1.2 Reduced transport energy Emissions

 ZEN Inc. STRATEGIES         ZENTAG Projects               Timeframe / KPI                  Project Lead & Group        Noosa Council Climate
                             (What)                        (How)                            Members (Who)               Change Response
                                                                                                                        Plan (CCRP) Themes
                                                                                                                        & Economic
                                                                                                                        Development Strategy
                                                                                                                        2021-2030: Green
                                                                                                                        Economy Plan
      1. Promote transport   a. *E-bike Library (Subject   30 Nov, 2025 & then possibly     Jenny Clement, Phil         Theme 1: Strong
 initiatives that reduce     to funding that has been      ongoing.                         Goldsmith, Darren Walters   leadership and
 greenhouse gas              applied for)                  Trail started Feb., 2025.                                    governance
 emissions                                                 Launch in June, 2025                                         1.1 Mobilise community for
                             b.*E-bike tours (Subject to   30 June, 2025 (Subject to        Jenny Clement, Darren       climate action
                             Council funding that has      funding) & then ongoing.         Walters                     1.2 Action for low carbon
                             been applied for) – see no.   Not running, as ZEN Inc. was                                 economy & resilient
                             2a below                      unsuccesful in 2024                                          community
                                                           Community Grants for this                                    1.3 Council is a powerful
 6. Advocate for, and                                      project. May merge into an                                   influencer for climate action
 demonstrate, sustainable                                  activity under the E-bike
 transport options for                                     Library                                                      Theme 2: Energy
 transport that reduces      c.ZENDURO (with Cooroy        End of term 1, 2025              Anne Kennedy/John           efficiency and renewable
 greenhouse gas              State School &/or Sunshine    Previous volunteer project       Fuller/Gwenn Davidson       energy
 emissions.                  Beach State High School)      leader unable to assist in 2nd                               1.3 Develop a climate
                                                                                                                                                        38

Page 39

                               half of 2024, due to work                                   aware and empowered
                               commitments. New Project                                    community for reducing
                               leader discussing with schools                              climate risks & emissions
                               for term 2 in 2025.
d.Idle free Noosa in school    End of term 1, 2025               Phil Goldsmith & Carina   Theme 3: Clean low
zones (Investigate)            Research into Idle Free           Anderson                  emissions industries
                               strategies completed. Need to                               3.1 …..shift to clean, green
                               investigate if there is an                                  low emission industries &
                               appetite for this in schools,                               technology
                               Council and ZEN., but not
                               progressing at this stage due                               3.2 ….. Facilitate
                               to lack of volunteers time.                                 emissions reduction &
e.Transport Advocacy           Review Dec., 2024                 Vivien Griffin/Jenny      environmental
(incl. Noosa Council's         In progress after deputation to   Clement                   sustainability for
transport plan, Kinetic        Council in Jan.,2025.                                       local businesses
contract/people movers & E     3 consultations end Feb/early
buses at Expo) (Investigate)   March                                                       Theme 4: Sustainable
i. Deputation to Council       Transport Summit with                                       Transport
ii. Community                  community and business                                      4.1 Accelerate public &
forums/Workshops               sectors planned to March.                                   active transport
iii. Council Workshop                                                                      infrastructure investment &
iv. Transport Summit                                                                       community usage through
v.                                                                                         the implementation of
f.EV Chargers - Investigate    Presentations to tourism /        Colin Lambie              Council’s Transport
promotion of destination EV    strata / business orgs. by                                  Strategy and Walking and
chargers to raise              June, 2025                                                  Cycling Plan.
awareness; Good EV             In progress, Options paper
comparison websites; Solar     being developed; articles                                   4.2 Transition Council &
panels over car parks          planned for Noosa Today                                     community to sustainable
(Investigate & Subject to      Will be discussed at March                                  transport use
funding being available)       consultations.                                              and zero-emissions
                                                                                           vehicles
g.*Electrify Noosa River       June, 2025                        Gillian Carter/ Carina
project proposal               Not progressing at this stage     Anderson                  Theme 7: Resilient &
(Investigate & Subject to      as volunteers had to withdraw                               adaptive communities &
funding being available)       due to heavy work                                           built environments
                               commitments.                                                7.1 Create a resilient built
h.*ZEN certification           June 2025                         Gillian Carter            environment for
concept (Investigate &         Not progressing at this stage                               householders, businesses,
subject to funding) Liaise     as volunteers had to withdraw                               vulnerable people, property

                                                                                                                          39

Page 40

                           with Anthony Wynne           due to heavy work                                      & infrastructure
                           Holcher re Plastic Free      commitments.
                           Noosa @ Tourism Noosa &                                                             7.2 Build community
                           Jordan Vance in Ec. Dev. @                                                          awareness & preparedness
                           Council                                                                             for climate
                                                                                                               change & extreme weather
                                                                                                               events

                                                                                                               Infrastructure
                                                                                                               accelerates industry
                                                                                                               development and Smart
                                                                                                               Precincts

                                                                                                               Enhancing our natural
                                                                                                               assets with technology
                                                                                                               driving value
    2. Encourage walking      a. See 1b above           30 June, 2025 (Subject to   Jenny Clement, Darren      Theme 4: Sustainable
        and                                             funding) & then ongoing.    Walters, Carina Anderson   Transport
cycling initiatives                                     In progress.                                           4.1 & 4.2 as above.

                                                                                                               Theme 7: Resilient &
                                                                                                               adaptive communities
                                                                                                               &
                                                                                                               built environments
                                                                                                               7.1 as above
                           b.*Shade trees to promote    Dec. 2024                   Carina Anderson            Theme 5: Healthy &
                           active transport             Progressing as part of                                 resilient natural systems
                           (Investigate & Subject to    Transport Advocacy.                                    & carbon drawdown
                           funding being available)                                                            5.1 Increase revegetation,
                                                                                                               restoration & urban
                                                                                                               greening, reduce urban
                                                                                                               heating

                                                                                                               Infrastructure
                                                                                                               accelerates industry
                                                                                                               development and Smart
                                                                                                               Precincts

                                                                                                               Enhancing our natural

                                                                                                                                            40

Page 41

                                                                                                                       assets with technology
                                                                                                                       driving value

     3. Promote carbon      a. See in no. 1a above                                                                     As above
         capture
technologies and
initiatives to offset car   b. Tree planting               X2 yearly with Tourism          Anne Kennedy                Theme 6: Sustainable
travel                      Trees for Tourism &            Noosa/Noosa Landcare.                                       agriculture and food
                            Landcare tree plantings        1 Trees for Tourism in 2024.                                systems
                                                           In progress. 1 planned on 02                                6.3 Support agri-
                                                           April.                                                      businesses & landholders
                                                                                                                       to:
                                                                                                                           a. Take up
                                                                                                                               opportunities for
                                                                                                                               income generation
                                                                                                                               through carbon
                                                                                                                               drawdown

                            c. Landcare tree data for      Dec. 2024                       Carina Anderson             Theme 5: Healthy &
                            promotion (Investigate)        Not progressing at this stage                               resilient natural systems
                                                           as volunteers had to withdraw                               & carbon drawdown
                                                           due to heavy work                                           5.1 as above.
                                                           commitments.
   4. Review Noosa          a. Transport Advocacy          To be reviewed Dec. 2024.       Vivien Griffin/Jenny        Theme 4: Sustainable
       Council’s            (incl. Noosa Council's         Progress as per 1 e above.      Clement                     Transport
Transport Strategy and      transport plan, Kinetic                                                                    As above
make recommendations        contract & People Movers);
                            Smaller electric buses, more                                                               Infrastructure
                            electric public transport;                                                                 accelerates industry
                            more active and public                                                                     development and Smart
                            transportation                                                                             Precincts
                            routes (Investigate)
                                                                                                                       Enhancing our natural
                                                                                                                       assets with technology
                                                                                                                       driving value
    5. EV & Electrify       a.2025 EV & Electrify          By Sept. 2024.                  Expo Working group incl.    Theme 4: Sustainable
       Everything Expo.     Everything Expo                In Progress. Only one           ZEN Inc. Program/Project    Transport
                            ZENTAG Reps. to be part of     volunteer available as other    Manager, plus Paul Lewis.   As above
                            Expo Working group             volunteers have stepped away
                                                           due to work commitments.                                    Enhancing our natural

                                                                                                                                                   41

Page 42

                                                                                                                         assets with technology
                                                                                                                         driving value

OBJECTIVE 1.3 Increased community awareness of initiatives to reduce emissions

     1. Greater direct       a. See 1a above               As for 1a above                 As for 1a above               All themes previously
         engagement                                                                                                      mentioned above
initiatives with the Noosa
Shire community
EV & Electrify Everything
                             b. See 1b above

                             c. See 1c above               As for 1c above                 As for 1c above

                             d. See 1 d above              As for 1d above                 As for 1d above

                             e. See no. 1f above           As for 1e above                 As for 1e above

                             f. See no. 1g above           As for 1g above                 As for 1g above

                             a.2025 EV & Electrify         As for 5a above                 As for 5a above
                             Everything Expo see 5a.
                             above
    2. Develop online        See ZEN E Working Group       By 30 June, 2024.               Mark Purcell - See Rewiring
        toolkits to          Rewiring Noosa - “Electrify   Completed.                      Noosa - “Electrify
facilitate emissions         Everything” Toolkit that                                      Everything” Toolkit
reduction                    includes EV’s


    3. Effectively           a.Work with Comms. &          Ongoing so all project          Chair ZEN E & Chair C&A
       disseminate           Advocacy Committee            promoted at least x2 per year   & Chair ZENTAG
information through ZEN      using the Comms. &            Ongoing
Inc’s website and other      Advocacy Plan to promote
                             all ZEN E projects using:
communication channels
                             i. Print media

                                                                                                                                                  42

Page 43

                              ii. Social Media
                              iii. Website
                              iv. Newsletter

   C. Noosa Council’s Corporate Plan themes & Associated Plans relevant to the ZENTAG Working Group Action Plan

 Corporate Plan theme     Relevant Associated Plans to ZENTAG Action Plan
    6. Environment        Noosa Environment Strategy 2019
                          Climate Change Response Plan
                          Noosa Transport Strategy 2017 - 2027 - development of a new movement and connectivity strategy.

    7. Liveability        Noosa Transport Strategy 2017 - 2027 - development of a new movement and connectivity strategy
                          - Cycling and Walking Strategy and Implementation Plan 2020
                          - Noosa Trails Masterplan and Implementation Plan 2020.
                          Noosa Social Strategy and Social Justice Charter – new Community Strategy.
                          - Noosa Health and Wellbeing Plan 2019 -2024.
    8. Prosperity          Economic Development Strategy 2021 – Smart Biosphere
                           New Waste Strategy
    9. Future             Community Strategy – New Community Strategy.
                          Climate Change Response Plan
                          Disaster Management Plan
                          Local Disaster Recovery Plan
                          Destination Management Plan
                          Economic Development Strategy
                          Urban Greening Project

    10. Excellence        Community Engagement Framework


   D. Noosa Council Climate Change Response Plan (CCRP) Themes Relevant to the ZENTAG Working Group Action Plan
Theme 2: Energy efficiency and renewable energy
1.1 ….100% renewable energy incl. low income & vulnerable residents, businesses, incl. strata tenants
1.11 ….Develop a climate aware and empowered community for reducing climate risks & emissions
1.12 Develop a climate aware and empowered community for reducing climate risks & emissions
1.13 Develop a climate aware and empowered community for reducing climate risks & emissions
1.14 Develop a climate aware and empowered community for reducing climate risks & emissions
                                                                                                                            43

Page 44

1.15   Develop a climate aware and empowered community for reducing climate risks & emissions
1.16   Develop a climate aware and empowered community for reducing climate risks & emissions
1.17   Develop a climate aware and empowered community for reducing climate risks & emissions
1.18   Develop a climate aware and empowered community for reducing climate risks & emissions
1.19   Develop a climate aware and empowered community for reducing climate risks & emissions
Theme 3: Clean low emissions industries
3.1 …..shift to clean, green low emission industries & technology
3.2 ….. Facilitate emissions reduction & environmental sustainability for local businesses
Theme 4: Sustainable Transport
4.1 Accelerate public & active transport infrastructure investment & community usage through the implementation of Council’s Transport Strategy and
    Walking and Cycling Plan.
4.2 Transition Council & community to sustainable transport use and zero-emissions vehicles

Theme 6: Sustainable agriculture and food systems
6.3 Support agri-businesses & landholders to:
    c. Reduce their emissions technology implementation
    d. Take up opportunities for income generation through carbon drawdown
Theme 7: Resilient & adaptive communities &
built environments
7.1 Create a resilient built environment for householders, businesses, vulnerable people, property & infrastructure
7.2 Build community awareness & preparedness for climate change & extreme weather events
    a. Take up opportunities for income generation through carbon drawdown
C. Noosa Council Economic Development Strategy 2021-2030: Outcomes & Benefits relevant to the ZEN E Working Group Action Plan
1. Infrastructure accelerates industry development and Smart Precincts
2. Enhancing our natural assets with technology driving value




                                                                                                                                                      44

Page 45

45

Page 46

Appendix E - 2025 EV & Electrify Everything Work-plan

Task Allocation DRAFT v1 (Oct. 2024)
                                                                                   Start
Objective / Tasks                                       Allocated to   Status            Deadline Notes/Comments
                                                                                   date
2024 EV EXPO REVIEW, EVALUATION
RECOMMENDATIONS
                                                        ZEN - shared /
Compilation, analyse and report on Survey data                         Completed
                                                        tbc
Review and summarise debrief meetings with NSC,         ZEN - shared /
                                                                       Completed
NJA & other key stakeholders                            tbc
Prepare report for Council & Board                      ZEN Chair      Completed

BOARD CONSULTATION
Prepare and present final Expo report to Board          ZEN Chair      Completed
                                                                                                 Board agreed to go ahead with 2025 EV &
Consider and decide on report recommendations           ZEN Board      Completed
                                                                                                 Electrify Expo
                                                        ZEN - shared /
Oversee completion of Board-approved changes                           Completed
                                                        tbc

THANK YOU & FOLLOW UP TO PATRONS,
PARTNERS, SPONSORS, & EXHIBITORS
E Mails, photos, video link & survey results sent to
above, plus a report on how we sgowcaysed them in ZEN Assist           Completed                 Meghan
markiting & media

NOOSA SHIRE COUNCIL (NSC) - TEMPORARY
EVENT PERMIT (TEP)
Meet with NSC staff to determine preliminaries (event                                            NSC = Renee Black & Julie Duncan &
date, MOU, letter of support, cash and in-kind                      In                           Anne Nolan
                                                      ZEN Chair
support, communications, temporary event permit                     Progress                     ZEN = Anne Kennedy, Tony Clark &
(TEP) application process & documents)                                                           Thorsten Kels
                                                      ZEN Event Co-
Lodge preliminary TEP application (to secure date)                  Completed
                                                      ord.

                                                                                                                                       46

Page 47

Complete all tasks related to the finalisation of the
                                                      Event              To be
TEP application (inc. attach EMP, TMP, site plans,
                                                      Manager            done
permits etc)
Act as the primary contact with Council on all        Event              To be
matters related to the TEP                            Manager            done
Prepare a post-event report with recommendations to Event                To be
ZEN related to the TEP                                Manager            done

SITE PLAN
                                                            Event
                                                                                        review number and size options for sites.
                                                            Manager &     To be
Review previous and confirm new event Site Plan                                         Confirm access Zones, with input from
                                                            ZEN Event Co- done
                                                                                        ZEN Inc. Chair
                                                            ord.
                                                            Event
Visit site and identify all access areas, infrastructure, Manager &       To be
site/zone locations, car parks, public toilets, power       ZEN Event Co- done
                                                            ord.
Update CAD site plan map as needed to reflect               Event         To be
                                                                                        ? NSC updates site plan $95/hr.
approved changes                                            Manager       done
Allocate exhibitors and expo infrastructure (stage,
                                                            Event         To be
barriers, toilets, bins, water filling station etc) to site                       May
                                                            Manager       done
plan
                                                            Event         To be
Infrastructure planning i.e toilets, barriers
                                                            Manager       done
                                                            Noosa         To be
Encourage cafés & dining businesses to stay open
                                                            Junction Ass done
                                                            ZEN Chair &
                                                                          To be
Confirm continuation Trial Ride zone                        ZEN Event Co-
                                                                          done
                                                            ord.
                                                            Event         To be
Book site infrastructure as per below
                                                            Manager       done

TRAFFIC MANAGEMENT PLAN (TMP)
Review previous TMP and any recommendations,            Event            To be
amend (if needed) and confirm TMP with contractor,      Manager          done
                                                                                                                                47

Page 48

send to ZEN
Adopt finalised TMP. Respond to TMP inquiries,       Event         To be
oversee delivery with TMP contractor                 Manager       done
Report on TMP post-event & make recommendations      Event         To be
if needed                                            Manager       done
                                                     ZEN Event Co- To be
ZEN Inc. sign off on final TMP
                                                     ord.          done

EVENT MANAGEMENT PLAN (EMP)
                                                    Event
Review existing EMP, adopt Board-approved           Manager &     To be
changes. Finalise EMP and circulate to stakeholders ZEN Event Co- done
                                                    ord.
Notify Translink event inc. re-routing, change bus  Event         To be
stops,. Confirm approval.                           Manager       done
                                                    Event         To be
Adopt ZEN Waste Management Plan
                                                    Manager       done
                                                    Event         To be
Adopt ZEN Noise Management Plan
                                                    Manager       done
                                                    Event
Adopt ZEN Sustainability Plan                                     Completed
                                                    Manager
                                                    Event
Prepare Site Evacuation plan and issue to relevant  Manager &     To be       scenarios, assembly points, incident
participants / stakeholders                         ZEN Event Co- done        control,
                                                    ord.
Review and issue run-sheet/s (lead up, delivery and Event         To be
wind down of the event.)                            Manager       done

EMERGENCY SERVICES
Notify Police, oversee issuing of road closure permit. Event      To be       Contact SC Michael Phelan. Meet with all
Circulate permit to relevant event stakeholders.       Manager    done        parties early February.
Notify QAS of event. Attend to any issued conditions Event        To be
/ requests.                                            Manager    done
Notify QFES of event. Attend to any issued             Event      To be
conditions / requests.                                 Manager    done
                                                                                                                         48

Page 49

RISK MANAGEMENT PLAN - (RMP)
                                                      Event
Review, recommend changes, amend, adopt and           Manager &     To be
revise RMP                                            ZEN Event Co- done
                                                      ord
Distribute, present, Implement RMP to relevant        Event         To be
stakeholders                                          Manager       done
Adopt Event Sustainability Plan into event planning   Event         To be
decisions                                             Manager       done
Confirm current insurance policies are in place for   Event         To be
the event (Pub&Prod, PersonAcc, Assoc'n)              Manager       done
Keep record of Trial Ride exhibitors' insurance CoC   Event         To be
                                                                            exhibitor database includes "CoC"
which notes ZEN and NSC as interested parties         Manager       done

VOLUNTEERS
                                                      Event
                                                      Manager &     To be
Determine and monitor required Volunteer Roles
                                                      ZEN Event Co- done
                                                      ord.
                                                                            ZEN Event Co-ord. & Expo Assist. For
                                                      ZEN Event Co- To be
Develop and undertake volunteer recruitment plan                            past volunteers, ZEN membership,
                                                      ord.          done
                                                                            GoVolunteer, FB,
Maintain Volunteer database (availability, role                    To be
                                                      ZEN Assist            ZEN Event Co-ord. & Expo Assist.
interest, ZEN inc. T Shirts),                                      done
                                                                   To be
Develop and maintain Volunteer Roster                 ZEN Assist
                                                                   done
Assess Volunteer Uniform ZEN inc. T Shirts and                     To be
                                                    ZEN Assist
source                                                             done
Volunteer Booklet, roles identified and described,  Event          To be
                                                                            With ZEN Inc. Assist.
maps, rosters                                       Manager        done
Communicate with Volunteers to ensure they are well Event          To be
                                                                            With ZEN Inc. Assist.
informed and engaged                                Manager        done
Create and distribute Volunteer Information         Event          To be
                                                                            With ZEN Inc. Assist.
document                                            Manager        done
                                                                                                                   49

Page 50

                                                    Event          To be
Conduct Volunteer Induction & Information session                             With ZEN Inc. Assist.
                                                    Manager        done
                                                    Event          To be
Establish and manage volunteer hub (check-in/out)                             marquee or vacant shop provided by NJA
                                                    Manager        done
                                                                   To be
Record volunteers hours                             ZEN Assist
                                                                   done
                                                                   To be
Provide report on Volunteers                        ZEN Assist                With ZEN Inc. Assist.
                                                                   done
                                                                   To be
Provide volunteers thank-you function               ZEN - shared
                                                                   done

EVENT MANAGER
                                                    ZEN - shared / In
Seek and secure Event Manager                                                 ZEN Expo Working Group
                                                    tbc            Progress
                                                    Event
                                                    Manager &      To be
Finalise Contract Event Manager                                               ZEN Expo Working Group
                                                    ZEN Event Co- done
                                                    ord.



POLICY
                                                    ZEN Chair &
                                                                  To be       ZEN Inc. Expo Coordinator prepare for
Adopt Event Accessibility and Inclusion Plan        ZEN Event Co-
                                                                  done        Dec. Board meeting
                                                    ord.



NOOSA JUNCTION ASSOC. (NJA)
                                                 ZEN Chair &
Meet with NJA and confirm commitment to upcoming               To be
                                                 ZEN Event Co-
event, finalise MOU                                            done
                                                 ord.
Revise and circulate event notification to local Noosa         To be
                                                                              Judi Lalor @NJA
businesses                                       Junction Ass done
Liaison with and confirm NJA in-kind sponsors,   Noosa         To be
notify ZEN of secured sponsors                   Junction Ass done

                                                                                                                      50

Page 51

Add NJA sourced sponsors to sponsors and            ZEN Event Co- To be     Liaise with Anne & Colin as Sponsor
exhibitors list.                                    ord           done      Coordinators
Encourage local Cafés & Restaurants to stay open    Noosa         To be
and expect good business                            Junction Ass done



SITE INFRASTRUCTURE
                                                      ZEN Chair &
                                                                    To be
Confirm need for stage.                               ZEN Event Co-
                                                                    done
                                                      ord.
                                                      ZEN Event Co- To be
Seek quotes & Book stage (if agreed))
                                                      ord.          done
                                                      Event         To be
Seek quotes & Book Bins x 7 @                                               Only if cannot be provided by NJA
                                                      Manager       done
                                                      Event         To be
Seek quotes & Book Toilets x 5 @
                                                      Manager       done
Seek quotes & Book Chairs stage TBC if have           Event         To be   200 Only of have a stage or 12 if just have
Speakers Stage                                        Manager       done    opening ceremony on small platform
                                                                    To be
Seek quotes & Book First-aid services                 ZEN Assist
                                                                    done
                                                      Event         To be
Seek quotes & Power Supply                                                  V2L used from Evs
                                                      Manager       done
Seek quotes & Book exhibitor-requested marquees if Event
needed, paid at exhibitors expense & added to         Manager &     To be   for exhibitors travelling from afar, or
exhibitor fees, (not paid by ZEN Inc.who then had to ZEN Event Co- done     Sponsors
seek reimbursement as in 2023)                        ord.
                                                      Event
Seek quotes & Book other infrastructure as identified Manager &     To be
and approved                                          ZEN Event Co- done
                                                      ord.
                                                      ZEN Event Co- To be
Book Unitywater bottle filling van                                          on-line booking open 1-Jan-24.
                                                      ord.          done
                                                      Event
Confirm event signage requirements, seek quotes,                    To be
                                                      Manager &             Some 2024 signage that can be reused
oversee delivery, erect signs                                       done
                                                      ZEN Event Co-

                                                                                                                      51

Page 52

                                                      ord.
                                                                             as per TMP, install 2 wks prior . (add Expo
Book VMS board, oversee delivery & and collection,                  To be    Info. as community info. for as well as
                                                      Council
displayed text,                                                     done     road closure details) ZEN inc. Coordinator
                                                                             to check Expo is mentioned.

EXHIBITOR MANAGEMENT
                                                       ZEN Event Co- To be   In consultation with ZEN E Working Group
Identify new prospective exhibitors (esp Electrify)
                                                       ord           done    Leader & ZEN Inc. Chair
                                                       ZEN Chair &
Review and Confirm Exhibitor Pricing Schedule                        To be
                                                       ZEN Event Co-
@ZEN                                                                 done
                                                       ord.
                                                       Event
                                                       Manager &     To be   include option for accommodation and
Update, finalise Exhibitor Invitation package
                                                       ZEN Event Co- done    shade tent
                                                       ord.
                                                                     To be
Invite Exhibitors                                      ZEN Assist
                                                                     done
Maintain exhibitor database (prospects, confirmed,                   To be
                                                       ZEN - shared          Anne, Colin Lambie & ZEN Inc. Treasurer
invoice request, @ZEN                                                done
                                                                     To be
Prepare invoices for confirmed exhibitors              ZEN Treasurer         invoices issued with exhibitor agreement
                                                                     done
Review, amend, confirm and distribute Exhibitor On- Event            To be
                                                                             Bump In & Out etc
Day Logistics Information                              Manager       done
Obtain Trial Rides Exhibitors Cert. of Currency with Event           To be
ZEN and NSC noted as interested parties                Manager       done
                                                       Event
                                                       Manager &     To be   With input from ZEN Event Coordin. &
Create Exhibitor location plan / site plan
                                                       ZEN Event Co- done    ZEN Inc. Chair who is sponsor liasion
                                                       ord.
                                                       Event         To be
Act as contact point for exhibitors re event logistics
                                                       Manager       done
                                                                     To be
Exhibitor listing (on line, newsletters, socials)      ZEN - shared
                                                                     done
Notify ZEN of Exhibitor Invoice Requests @ZEN          ZEN - shared To be

                                                                                                                      52

Page 53

                                                                    done



VIP INVITES & OPENING SPEAKERS, OPENING
CERMENONY
                                                     ZEN Chair &
                                                                   To be
Seek Welcome to Country representative               ZEN Event Co-           Lyndon Davis
                                                                   done
                                                     ord.
                                                     ZEN Chair &
                                                                   To be
Review VIP Invite List                               ZEN Event Co-
                                                                   done
                                                     ord.
                                                                   To be
Invitee Update @ZEN                                  ZEN Chair
                                                                   done



EVENT SURVEY
                                                                             include number of night stays,
Identify key survey data topics and target survey    ZEN Event Co- To be
                                                                             stakeholder related data, tourism, spends,
groups to be analysed.                               ord           done
                                                                             purchase etc
Create event survey/s, and method of collecting
                                                                     To be   ?Google forms or similar. Ease of use by
survey (paper, QR code, volunteers, on-line form and ZEN - shared
                                                                     done    vols. ? Random prizes.
device collection) @ZEN vols
Conduct survey/s to target groups at optimal time for                To be
                                                      ZEN - shared
each group @                                                         done
                                                      ZEN - shared / To be
Maintain database of responses @ZEN
                                                      tbc            done
                                                      ZEN Event Co- To be
Provide a report of key survey findings @ZEN
                                                      ord            done

DATA MANAGEMENT
Ownership by ZEN, with provide set access rights to                 To be
                                                    ZEN - shared
EvMgr                                                               done

SPONSORSHIP
                                                                                                                        53

Page 54

                                                   ZEN Chair &
                                                                  To be     ask NJA and TN for feedback on
Review Sponsorship Proposal package                ZEN Event Co-
                                                                  done      prospectus
                                                   ord.
                                                   ZEN Chair &
Identify/develop prospective sponsors (EV industry                To be
                                                   ZEN Event Co-            Anne & Colin
and "electrify" industry). Update database                        done
                                                   ord.
Make contact with potential sponsor, Send                         To be
                                                   ZEN Chair                Anne & Colin
prospectus as requested. Follow up.Update database                done
                                                   Event          To be
Issue agreements
                                                   Manager        done
                                                   ZEN - shared / To be
Invoices to secure sponsors
                                                   tbc            done
                                                                  To be
Prepare sponsor invoices                           ZEN Treasurer            invoice sent with sponsor agreement
                                                                  done
                                                   Event
                                                   Manager &      To be
Prioritise Sponsor preferred Site Allocations                               Input from Anne also
                                                   ZEN Event Co- done
                                                   ord.
                                                                  To be
Ensure In-kind Sponsorships deliverables are met   ZEN - shared             Anne & Colin
                                                                  done
                                                   ZEN - shared / To be
Update secured sponsors onto Exhibitor database
                                                   tbc            done

MAIN STAGE (if agreed))
                                                   ZEN Event Co- To be
Infrastructure quotes
                                                   ord.          done
                                                   ZEN Event Co- To be
Stage TBC
                                                   ord.          done
                                                   Event
Marquee ?????? Not sure why this is in here????
                                                   Manager
                                                   Event         To be      Or was this done by ZEN Expo Co-
AV equipment
                                                   Manager       done       ordinator?
                                                                            In past speakers program has been done
                                                   ZEN - shared /
Speakers TBC/MC                                                   On Hold   by a ZEN Inc. volunteer. Is not
                                                   tbc
                                                                            recommended for 2025 Expo.

                                                                                                                     54

Page 55

                                                      Event
                                                      Manager &     To be
Signage                                                                       Done jointly as it is sponsor signage.
                                                      ZEN Event Co- done
                                                      ord.
                                                      Event
                                                                              In past speakers program has been done
                                                      Manager &
Program Development                                                 On Hold   by a ZEN Inc. volunteer. Is not
                                                      ZEN Event Co-
                                                                              recommended for 2025 Expo.
                                                      ord.

MARKETING / BRANDING /
                                                      ZEN Chair &
Update event logos and livery on logos, graphics,                    To be
                                                      ZEN Event Co-           add "Electrify", update 2024 date
letterhead, website, newspaper advert copy etc                       done
                                                      ord.
Develop a marketing strategy / plan that identifies   ZEN - shared / To be
target demographics, promotion plan, etc              tbc            done



PROMOTION
                                                      ZEN - shared / To be
Newsletter Process
                                                      tbc            done
                                                      ZEN - shared / To be
JAN EDM
                                                      tbc            done
                                                      ZEN - shared / To be
FEB EDM
                                                      tbc            done
                                                      ZEN - shared / To be
MARCH EDM
                                                      tbc            done
                                                      ZEN - shared / To be
APRIL EDM
                                                      tbc            done
                                                      ZEN - shared / To be
MAY EDM
                                                      tbc            done
                                                      ZEN - shared / To be
JUNE EDM
                                                      tbc            done
SOCIAL MEDIA
                                                      ZEN - shared / To be
Facebook posts
                                                      tbc            done
                                                                                                                       55

Page 56

                                                     ZEN - shared / To be
Instagram posts
                                                     tbc            done

WEBSITE
                                                     ZEN - shared / To be
Website updated with dates and links @ZEN
                                                     tbc            done
                                                     ZEN - shared / To be
Website updated with exhibitors
                                                     tbc            done
                                                     ZEN - shared / To be
Website updated with sponsors
                                                     tbc            done
                                                     ZEN - shared / To be
Website updated with program
                                                     tbc            done
                                                     ZEN - shared / To be
Website updated with Event time
                                                     tbc            done
                                                     ZEN - shared / To be
Website updated with registration
                                                     tbc            done
Website updated with sustainability and disability   ZEN - shared / To be
section                                              tbc            done
                                                     ZEN - shared / To be
Event Logo updated
                                                     tbc            done

ADVERTISING
                                                     ZEN Chair &
                                                                   To be
Identify newspaper                                   ZEN Event Co-
                                                                   done
                                                     ord.
                                                     Event         To be
Seek quotes, submit to ZEN Event Co-ord.                                    Done by ZEN Expo Co-ordinator?
                                                     Manager       done
                                                     ZEN Chair &
                                                                   To be
Approve quotes and advert schedule                   ZEN Event Co-
                                                                   done
                                                     ord.
Book adverts and supply copy as per agreed           Event         To be
                                                                            Done by ZEN Expo Co-ordinator?
schedule                                             Manager       done
                                                     Event         To be
Sunny Coast Times                                                           Done by ZEN Expo Co-ordinator?
                                                     Manager       done
Advertisements Noosa Today                           Event         To be    Done by ZEN Expo Co-ordinator?
                                                                                                             56

Page 57

                                                        Manager        done
                                                        Event          To be
IN Noosa - maybe not                                                           Not in 2025
                                                        Manager        done
                                                        Event          To be
Your local lifestyle: Noosa Hinterland                                         Done by ZEN Expo Co-ordinator?
                                                        Manager        done
                                                        Event          To be
Eumundi Voice                                                                  Done by ZEN Expo Co-ordinator?
                                                        Manager        done
                                                        Event          To be
Coolum Advertiser                                                              Done by ZEN Expo Co-ordinator?
                                                        Manager        done
                                                        Event          To be
Sunshine Coast Daily                                                           Done by ZEN Expo Co-ordinator?
                                                        Manager        done
                                                        ZEN - shared / To be
Noosa Today advertising feature                                                Done by ZEN Expo Co-ordinator?
                                                        tbc            done
                                                        ZEN Social     To be
Facebook paid boosts
                                                        Media          done

GRANTS
                                                        ZEN Chair &
                                                                      To be
Identify and apply for suitable grants                  ZEN Event Co-
                                                                      done
                                                        ord.
                                                        ZEN Event Co- To be
Ensure to grant deliverables are fully met
                                                        ord.          done
                                                        ZEN Event Co- To be
Report on and Acquit grants
                                                        ord.          done

BUDGET & FINANCIALS
                                                        ZEN Chair &
                                                                      To be
Set and monitor event budget                            ZEN Event Co-
                                                                      done
                                                        ord.
                                                        ZEN Chair &
Seek quotes related to the Event Manager tasks and                    To be
                                                        ZEN Event Co-
submit for approval                                                   done
                                                        ord.
Attend to financial transactions, invoice generation,                 To be
                                                        ZEN Treasurer
A/R, A/P, P&L, cash flow, financial reports                           done

                                                                                                                57

Page 58

ENTERTAINMENT
                                                      Event
                                                      Manager &     To be
Confirm buskers and entertainers
                                                      ZEN Event Co- done
                                                      ord.
                                                      Event         To be
Book and manage buskers on-site logistics
                                                      Manager       done

COMMUNICATIONS & DATA
Communicate with stakeholders e.g. Translink,          Event          To be
Police, Ambulance, etc                                 Manager        done
Maintain on-line data sharing & access rights of key ZEN - shared /
                                                                              Event Manager to be provide access rights
event documents, database, graphics, photos            tbc
Set and maintain databases to help manage              ZEN - shared / To be
volunteers, exhibitors, sponsors, surveys, etc.        tbc            done
Communicate as required to stakeholders, sponsors, Event              To be
exhibitors, volunteers to ensure delivery of the event Manager        done
                                                       ZEN Chair &
                                                                      To be
Communicate with media.                                ZEN Event Co-
                                                                      done
                                                       ord.
                                                       Event
Maintain timely communications on all matters          Manager &      To be
related to the successful delivery of the event        ZEN Event Co- done
                                                       ord.

Opening event or media launch TBC




                                                                                                                     58

Page 59

                                                                                         Appendix F
Use of Alliance Partnership Funds from Council for 2024
The revised Administrator/Coordinator role for Jan. 01, 2024 to Nov. 30, 2024 was Admin. for
21 hours per week and Communications for 3 hours per week for a total of $ 55,018.67 made up of
$50,577.76 wages & on costs & ($44,584.01 Gross pay + Superannuation $4,972.37. Workcover $1,021.38)
and $4440.62 Operating Expenses. The budgeted amount was $50,000 per annum for Admin. & some Comms.
component. However, as the same person did both roles, and that person did not start
until late Oct., 2023, the amount paid has all come out of the admin. part of the funding.

The Communications Package $15,000 - while $15,000 was budgeted out of the Alliance funds for marketing
advice for ZEN Inc. overall $7,958.07 was used for marketing advice for the EV Expo due to the issues outlined
in section 6 above. $4440.62 was used for communications related operating expenses as outlined in the
admin. package and the admin. overrun of $577.76 was also covered from this Comms. Package. Therefore
there is a balance of $6,464.17 from the 2023-2024 Alliance Partnership Communications Package remaining
to put towards this work in 2025.



     1. Administration & Communications Package $50,000
     A. Administration (80 hours per month)
 Activity or Event        Date/Time         Amount of             Impact/Outcome
                                            Time Per
                                            Month
     1. Board and                           35 hours per          Strengthen ZEN Inc’s
          Working Group                     month                 internal Operations so
     a. Attend Board &                                            volunteers can
          Working group                                           concentrate on projects
          meetings                                                Sec. resigned and unable
     b. Working group                                             to be replaced so this
          notes                                                   task went to this position
     c. Board meeting
          minutes &
          follow
          up/actions


     2. Membership                             5 hours per        Building
     a. Keeping                                month              membership/volunteer
        membership                                                base to assist with
        records                                                   project work/education
     b. Contact with                                              /advocacy
        members

     3. Operations                             10 hours per       Strengthen ZEN Inc’s
     a. Governance &                           month              internal Operations so
        Operations                                                volunteers can
        Manual                                                    concentrate on projects
     b. Updating
        Shared Drives &
        E files
                                                                                                            59

Page 60

    4. General Admin.                          25 hours per Strengthen ZEN Inc’s
       & Following Up                          month        internal Operations so
       Queries                                              volunteers can
                                                            concentrate on projects
    5. Governance                                           Strengthen ZEN Inc’s
    a. AGM                                 5 hours per      internal Operations so
       Preparation                         month            volunteers can
                                                            concentrate on projects
    B. Communications Total = 3 hours per week or 12 hours per month

Activity or Event         Date/Time/Location      Amount of     Impact/Outcome
                                                  Time Per
                                                  Month
    1. Newsletter         Developing &            4 hours per   Public education & Advocacy
                          Coordinating content    month

    2. Coordinating       Writing them and        6 hours per   Public education & Advocacy
       Noosa Today        coordaining others      month
       articles or        writing them
       media releases

    3. Website            Minor updates to ZEN    2 hours
       updates            Inc. & Expo websites
       Total                                                    $50,000
2. Communications Package $15,000
Task                  Action                                    $ Amount
Upgrade & Update      Update outdated Info.                     $3,000
website to be more    Review & Re organise information
user friendly         for ease of access
Did not occur in 2024 Add project info. & regular updates -
                      Expand Partner’s page
Videos                Commercially produced Major               $2,500
Were done from        Project videos
project budgets           • Community Batteries

Telling ZEN Inc’s story   Strengthening ZEN Inc’s               $1,800
Outreach by               communication through:
monitoring for                1. Newsletter Production &
trolls/provocative                Media Releases
posts– currently only         2. Professionally written
posting, no                       social media presence
monitoring possible
with volunteers.
Marketing ZEN inc. &      Marketing advice and developing       $7,700 (up to)
EV Expo                   and implementing a marketing plan
Only done to a very
limited extent.
                                                                $15,000

                                                                                              60

Page 61

                                                                                Appendix G
 Additional Funding Components - Itemised budget for Council Alliance Partnership
 Funding for 2025-2026
1. ZEN Inc. Program/Project Manager Role $49,400 for 2025 - 2026

 Tasks currently done by        Move to ZEN Inc.               Frees ZEN Inc. Board
 ZEN Inc. Chair /Board          Program/Project Manager        members up to do
 members
 Additional Finances & funding
 Some sponsorship &             Full sponsorship &             Work on diversifying ZEN
 coordination of the EV &       coordination of the EV &       Inc. Income sources
 Electrify Expo                 Electrify Expo
 Some Financial monitoring      Full Financial monitoring of   Expand sponsorship and
 of projects, including project projects, including project    donations so EV Expo is
 budgeting & grant              budgeting & grant              self- sustaining by 2025.
 coordination                   coordination                   Council MOU expires 2024.
 Additional Program/Project Coordination
 Assist project leaders with    Assist all project leaders     Revisit & revise MOU’s with
 monitoring, coordination and with monitoring,                 partners & develop
 implementation                 coordination and               collaborative projects
                                implementation

 Project Admin. and reporting Project Admin. and reporting Work on strategic direction
 e.g. including project       e.g. including project       of organisation & projects
 budgeting                    budgeting                    (that are at cutting edge of
                                                           renewable energy/E
                                                           transport development)

                                                            $49,400
 Additional Admin./Secretariat Role - Internal relations – Building a stronger
 organisation
 Admin. for Recruitment of   Admin. for recruitment of      Building relationships with
 new Board members           new Board members              Board & ZEN Inc. members
 annually, including         annually                       Find linkages between
 organising short listing,                                  members skill sets for better
 interviewing & reference    AGM preparation                project leverage
 checks & AGM preparation
 Annual report               Input, formatting & photo
                             layout of Annual report        Strengthen ZEN Inc.
                             Membership                     internally
 Operations Manual           Operations Manual
                                                            $5,200
 Additional to Marketing & Comms. Role - External relations (Education & Advocacy)
                             Implement our strategic        Developing strategic
                             marketing plan for the         relationships
                             organisation as a whole,
                             (not just for the Expo) by     More extensive networking
                             engaging a professional        & relationship building
                             marketing person for
                             additional hours per month     More time on advocacy of
                             to help us better engage       strategic issues
                                                                                             61

Page 62

                           with our audience and get
                           them to ACT!.
                                                       $12,000
Total Additional “Ask” Amount                          $66,400

Anne Kennedy, Colin Lambie & Mark Purcell
Feb., 2024




                                                                 62

Page 63

P&L For Jan. – Dec., 2024                Appendix H

Profit and Loss
Zero Emissions Noosa Inc
For the year ended 31 December
2024
Cash Basis

Account                          2024

Trading Income
Donations                     7,361.10
Exhibitor Fees                8,086.36
Grant Funding               225,100.00
Interest Income               2,039.28
Member Fees                   1,789.14
Sponsorship                  45,000.00
Total Trading Income        289,375.88

Cost of Sales
Grant Associated Expenses    94,507.02
Total Cost of Sales          94,507.02

Gross Profit                194,868.86

Operating Expenses
Advertising                      50.00
Bank Fees                        18.56
Consulting & Accounting       3,585.68
General Expenses                 23.45
Membership Fees                 162.50
Office Expenses                 325.00
Subscriptions                   696.06
Superannuation                5,404.75
Wages and Salaries           50,600.40
Workcover                       657.29
Total Operating Expenses     61,523.69

Net Profit                  133,345.17




                                                      63

Page 64

                                                                                                                      Appendix I

Profit and Loss by Project
Zero Emissions Noosa Inc
For the 3 years ended 31 December 2024
Cash Basis

                                                                              Noosaville    QLD Gov -
                            Alliance      Alliance     Energy
                                                                  EV Expo       Battery    Community
Account                   Agreement     Agreement          Eff                                               Total
                                                                     2025      Project -      Battery
                                   1             2     Assess
                                                                                   YEF        Project

Trading Income
Grant Funding               65,000.00    125,000.00   29,000.00   10,000.00    10,000.00     48,831.38   287,831.38
Total Trading Income        65,000.00    125,000.00   29,000.00   10,000.00    10,000.00     48,831.38   287,831.38

Cost of Sales
Grant Associated
                             9,066.27       686.80         0.00    2,208.55    10,000.00     43,362.72    65,324.34
Expenses
Total Cost of Sales          9,066.27       686.80         0.00    2,208.55    10,000.00     43,362.72    65,324.34

Gross Profit                55,933.73    124,313.20   29,000.00    7,791.45         0.00      5,468.66   222,507.04

Operating Expenses
Advertising                      0.00        45.45         0.00        0.00         0.00          0.00        45.45
Bank Fees                       18.55         0.01         0.00        0.00         0.00          0.00        18.56
Consulting & Accounting      2,745.68       840.00         0.00        0.00         0.00          0.00     3,585.68
Credit card surcharge
                                 1.69          0.00        0.00        0.00         0.00          0.00         1.69
fees
General Expenses               335.45          0.00        0.00        0.00         0.00          0.00       335.45
Membership Fees                 50.00          0.00        0.00        0.00         0.00          0.00        50.00
Office Expenses                431.02          0.00        0.00        0.00         0.00          0.00       431.02
Recruitment                    925.00          0.00        0.00        0.00         0.00          0.00       925.00
Subscriptions                  279.78        582.42        0.00        0.00         0.00          0.00       862.20
Superannuation               4,972.37      1,073.76        0.00        0.00         0.00          0.00     6,046.13
Wages and Salaries          44,584.01     11,847.13        0.00        0.00         0.00      2,039.65    58,470.79
Website                        568.80          0.00        0.00        0.00         0.00          0.00       568.80

                                                                                                                                   64

Page 65

Workcover          1,021.38         0.00        0.00      0.00    0.00      0.00      1,021.38
Total Operating
                  55,933.73    14,388.77        0.00      0.00    0.00   2,039.65    72,362.15
Expenses

Net Profit           (0.00)   109,924.43   29,000.00   7,791.45   0.00   3,429.01   150,144.89




                                                                                                 65

Workcover 1,021.38 0.00 0.00 0.00 0.00 0.00 1,021.38 Total Operating Expenses 55,933.73 14,388.77 0.00 0.00 0.00 2,039.65 72,362.15 65

Page 66

Balance Sheet                                               Appendix J

 Balance Sheet
 Zero Emissions Noosa Inc
 As at 31 December 2024
 Cash Basis

                Account                     31 Dec 2024

 Assets
                Bank
                Business Account              241,858.52
                Debit Card Account                410.09
                Public Fund Account             2,306.41
                Total Bank                    244,575.02
 Total Assets                                 244,575.02

 Liabilities
                Current Liabilities
                GST                            14,219.62
                PAYG Withholdings
                                                1,852.00
                Payable
                Rounding                             0.10
                Superannuation Payable           (585.52)
                Suspense                       (2,290.47)
                Total Current Liabilities      13,195.73
 Total
                                               13,195.73
 Liabilities

                Net Assets                    231,379.29

 Equity
                Current Year Earnings         133,345.17
                Retained Earnings              98,034.12
 Total Equity                                 231,379.29




                                                                         66

Page 67

Appendix K




Association Report
Zero Emissions Noosa Inc
For the year ended 31 December 2024




                                              67

Appendix K Association Report Zero Emissions Noosa Inc For the year ended 31 December 2024 67

Page 68

Contents
3      Committee's Report

4      Income and Expenditure Statement

5      Assets and Liabilities Statement

6      Notes to the Financial Statements

7      True and Fair Position

8      Auditor's Report




Association       Zero Emissions Noosa     Page 2 of
Report            Inc                      76

Page 69

    Committee's Report
    Zero Emissions Noosa Inc
    For the year ended 31 December 2024

   Committee's Report

Your committee members submit the financial report of Zero Emissions Noosa Inc for the financial
   year ended 31 December 2024.


   Operating Result

The surplus for the financial year amounted to: $84,891



   Going Concern
This financial report has been prepared on a going concern basis which contemplates continuity of
    normal business activities and the realisation of assets and settlement of liabilities in the ordinary
    course of business. The ability of the association to continue to operate as a going concern is
    dependent upon the ability of the association to generate sufficient cashflows from operations to
    meet its liabilities. The members of the association believe that the going concern assumption is
    appropriate.

Signed in accordance with a resolution of the Members of the Committee on:




(President)

Date   16 / 02 / 2025


(Treasurer
)

Date         14//2/20/25




    Association     Zero Emissions Noosa                                                             Page 3 of
    Report          Inc                                                                              76

Page 70

Income and Expenditure Statement
 Zero Emissions Noosa Inc
 For the year ended 31 December 2024
                                                2024         2023


 Income
  Income
    Interest Income                             2,039       1,140
    Grants                                   190,492     115,462
    Donations                                   7,361     17,793
    Exhibitor Fees                              9,436       5,100
    Membership                                  1,789       2,118
    Sponsorship                               45,000      34,091
    Total Income                             256,118     175,704

  Total Income                               256,118     175,704

 Cost of Sales
  Project/Grant Expenses
    Projects Other                            109,708      73,052
    Total Project/Grant Expenses             109,708      73,052

  Total Cost of Sales                        109,708      73,052


 Gross Surplus                               146,410     102,652


 Other Income
  Other Revenue                                     -       2,662
  Total Other Income                                -      2,662

 Expenditure
  Audit Fees                                     500          500
  Bank Fees                                       19            2
  Consultant Fees                               3,086         914
  General Expenses                               231          134
  Insurance                                      657            -
  Office Expenses                                325          101
  Superannuation                                5,405       2,449
  Wages and Salaries                          50,600      23,147
  Recruitment Expenses                              -         925
  Website Expenses                                  -         244
  Subscriptions                                  696          166
  Total Expenditure                           61,519      28,582


 Current Year Surplus/ (Deficit)              84,891      76,732




Association           Zero Emissions Noosa              Page 4 of
Report                Inc                               76

Page 71

Assets and Liabilities Statement
 Zero Emissions Noosa Inc
 As at 31 December 2024
                                              NOTES   31 DEC 2024    31 DEC 2023


 Assets
  Current Assets
    Cash at Bank                                          241,859         95,463
    Public Fund Account                                     2,306          1,726
    Direct Debit Account                                      410                  -
    Sundry Debtors                                         26,116         62,700
    Total Current Assets                                 270,691        159,889

  Total Assets                                           270,691        159,889

 Liabilities
  Current Liabilities
    Sundry Creditors                                       16,721                  -
    GST Payable                                            13,554          1,500
    GST on Creditors                                       (1,520)                 -
    GST on Debtors                                          2,374          5,700
    PAYG Withholdings Payable                               1,852            678
    Employee Entitlements                                   1,451            641
    Total Current Liabilities                             34,431          8,519

  Total Liabilities                                       34,431          8,519


 Net Assets                                               236,260       151,369


 Member's Funds
  Capital Reserve                                         236,260        151,369
  Total Member's Funds                                    236,260       151,369




Association            Zero Emissions Noosa                            Page 5 of
Report                 Inc                                             76

Page 72

   Notes to the Financial Statements
   Zero Emissions Noosa Inc
   For the year ended 31 December 2024

  1. Summary of Significant Accounting Policies
The financial statements are special purpose financial statements prepared in order to satisfy the
   financial reporting requirements of the Associations Incorporation Act QLD. The committee has
   determined that the association is not a reporting entity.
The financial statements have been prepared on an accruals basis and are based on historic costs and
   do not take into account changing money values or, except where stated specifically, current
   valuations of non-current assets.
The following significant accounting policies, which are consistent with the previous period unless stated
   otherwise, have been adopted in the preparation of these financial statements.

  Cash on Hand

Cash on hand includes cash on hand, deposits held at call with banks, and other short-term highly
   liquid investments with original maturities of three months or less.

  Revenue and Other Income

Revenue is measured at the fair value of the consideration received or receivable after taking into
   account any trade discounts and volume rebates allowed. For this purpose, deferred
   consideration is not discounted to present values when recognising revenue.
Interest revenue is recognised using the effective interest method, which for floating rate financial
    assets is the rate inherent in the instrument. Dividend revenue is recognised when the right to
    receive a dividend has been established.
Grant and donation income is recognised when the entity obtains control over the funds, which is
   generally at the time of receipt.
If conditions are attached to the grant that must be satisfied before the association is eligible to receive
     the contribution, recognition of the grant as revenue will be deferred until those conditions are
     satisfied.
All revenue is stated net of the amount of goods and services tax.

  Goods and Services Tax (GST)

Revenues, expenses and assets are recognised net of the amount of GST, except where the amount of
   GST incurred is not recoverable from the Australian Taxation Office (ATO). Receivables and
   payables are stated inclusive of the amount of GST receivable or payable. The net amount of GST
   recoverable from, or payable to, the ATO is included with other receivables or payables in the
   assets and liabilities statement.




   Association    Zero Emissions Noosa                                                               Page 6 of
   Report         Inc                                                                                76

Page 73

   True and Fair Position
   Zero Emissions Noosa Inc
   For the year ended 31 December 2024

  Annual Statements Give True and Fair View of Financial Position and Performance of the
  Association
We,       Anne                   , and    Colin           , being members of the committee of Zero
          Kennedy                                             Emissions
                                          Lambie
Noosa Inc, certify that –
The statements attached to this certificate give a true and fair view of the financial position and
   performance of Zero Emissions Noosa Inc during and at the end of the financial year of the
   association ending on 31 December 2024.

Signed:
   Dated: 16//02//2025

Signed:
            Dated:
              /    / 14/02/2026




   Association     Zero Emissions Noosa                                                               Page 7 of
   Report          Inc                                                                                76

Page 74

   Auditor's Report
   Zero Emissions Noosa Inc
   For the year ended 31 December 2024

  Independent Auditors Report to the members of the Association

We have audited the accompanying financial report, being a special purpose financial report, of Zero
    Emissions Noosa
Inc (the association), which comprises the committee’s report,the assets and liabilities statement as at
    31 December 2024, the income and expenditure statement for the year then ended, cash flow
    statement, notes comprising a summary of significant accounting policies and other explanatory
    information, and the certification by members of the committee on the annual statements giving a
    true and fair view of the financial position and performance of the association.

  Committee’s Responsibility for the Financial Report

The committee of Zero Emissions Noosa Inc is responsible for the preparation and fair presentation of
   the financial report, and has determined that the basis of preparation described in Note 1 is
   appropriate to meet the requirements of the Associations Incorporation Act QLD and is
   appropriate to meet the needs of the members. The committee’s responsibility also includes such
   internal control as the committee determines is necessary to enable the preparation and fair
   presentation of a financial report that is free from material misstatement, whether due to fraud or
   error.

  Auditor’s Responsibility
Our responsibility is to express an opinion on the financial report based on our audit. We have
   conducted our audit in accordance with Australian Auditing Standards. Those standards require
   that we comply with relevant ethical requirements relating to audit engagements and plan and
   perform the audit to obtain reasonable assurance whether the financial report is free from material
   misstatement.
An audit involves performing procedures to obtain audit evidence about the amounts and disclosures in
   the financial report. The procedures selected depend on the auditor’s judgment, including the
   assessment of the risks of material misstatement of the financial report, whether due to fraud or
   error. In making those risk assessments, the auditor considers internal control relevant to the
   association’s preparation and fair presentation of the financial report, in order to design audit
   procedures that are appropriate in the circumstances, but not for the purpose of expressing an
   opinion on the effectiveness of the association’s internal control. An audit also includes evaluating
   the appropriateness of accounting policies used and the reasonableness of accounting estimates
   made by the committee, as well as evaluating the overall presentation of the financial report.
We believe that the audit evidence we have obtained is sufficient and appropriate to provide a basis for
  our audit opinion.
  Opinion
In our opinion, the financial report presents fairly, in all material respects (or gives a true and fair view
    –refer to the applicable state/territory Act), the financial position of Zero Emissions Noosa Inc as
    at 31 December 2024 and (of) its financial performance for the year then ended in accordance
    with the accounting policies described in Note 1 to the financial statements, and the requirements
    of the Associations Incorporation Act QLD.

  Basis of Accounting and Restriction on Distribution

Without modifying our opinion, we draw attention to Note 1 to the financial statements, which describes
   the basis of accounting. The financial report has been prepared to assist Zero Emissions Noosa Inc
   to meet the requirements of the Associations Incorporation Act QLD. As a result, the financial
   report may not be suitable for another purpose.
   Association     Zero Emissions Noosa                                                                Page 8 of
   Report          Inc                                                                                 76

Page 75

Auditor’s signature: Louise McNeich
Auditor’s address: PO Box 563, Cooroy Qld 4563
Dated: 14/ 02 /2025




    Association       Zero Emissions Noosa       Page 9 of
    Report            Inc                        76

Page 76

28

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.