Zero Emissions Noosa Inc. (ZEN Inc.) Annual Report · ATTACHMENT 1_ZEN Inc. Report on Partnership Alliance Agreement to Council 2024
ATTACHMENT 1
Zero Emissions Noosa Inc. Partnership
Alliance Agreement
Operational Report to Council for 2024
1
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalFull text of the other 75 pages
Page 2
1. Introduction to the Organisation
ZEN Inc. is seen to be at the forefront of community energy as both a regional influencer and a
model for other community energy groups to follow.
ZEN Inc. is the community energy group assisting Council in the Noosa Shire Community to
implement key Council plans, including the Corporate Plan across the following themes:
1. Environment-
➢ Noosa Environment Strategy 2019 (Sustainable living & Climate change adaptation and
resilience)
➢ Climate Change Response Plan 2021(all 8 themes)
➢ Noosa Transport Strategy 2017 - 2027 (development of a new movement and connectivity
strategy).
2. Liveability
➢ Noosa Transport Strategy 2017 - 2027 - development of a new movement and connectivity
strategy
➢ - Cycling and Walking Strategy and Implementation Plan 2020
➢ - Noosa Trails Masterplan and Implementation Plan 2020 (use of completed plan).
➢ - Noosa Housing Strategy 2022 (Energy efficiency cost savings & emissions reduction)
➢ - Noosa Social Strategy and Social Justice Charter – Community Strategy (Energy efficiency
cost savings & emissions reduction)
➢ - Noosa Health and Wellbeing Plan & Implementation (through pillars of the Corporate Plan)
3. Excellence
➢ Community Engagement Framework (through Community batteries, Electrify Everything &
Transport forums/workshops)
4. Prosperity
➢ Economic Development Strategy 2021 – Smart Biosphere (through Community batteries,
Electrify Everything & Transport projects)
➢ Waste to Resource Strategy 2023-2028 (renewable energy)
&
5. Future
➢ Community Strategy – as above.
➢ Climate Change Response Plan – as above
➢ Noosa Design Principles (Sustainable Passive Design for energy efficiency)
➢ Disaster Management Plan (use of renewable energy)
➢ Local Disaster Recovery Plan(use of renewable energy
➢ Destination Management Plan (transport alternatives & emissions reduction strategy)
➢ Economic Development Strategy (through Community batteries, Electrify Everything &
Transport projects)
➢ Waste to Resource Strategy 2023-2028 (renewable energy)
With the Climate Change Response Plan being the key driver for ZEN Inc’s work.
ZEN Inc. has a close and collaborative relationship with Noosa Council and is helping Council to step
up as a leader in the emissions reduction space.
2
Page 3
It is governed by a Board of up to 10 people, which oversees three Working Groups – ZEN E (Energy),
ZENTAG (Transport) & Expo Working Group. The board’s work is supported in it’s operations by
three sub-committees:
➢ Governance & Operations
➢ Finance & Fundraising and
➢ Communications & Advocacy.
A Public Fund Account Committee oversees Tax Deductible donations. See Appendix A for ZEN Inc’s
Organisational Chart.
2. Current ZEN Inc. Strategic plan and 2024-2025 & Action Plans
ZEN Inc. reviews it’s strategic plan annually in August. Following a complete review in August 2023,
a review of the ZEN E & ZENTAG Action Plans were undertaken in 2024.The Expo Working group
Workplan was reviewed in Nov., 2024, once the decision to go ahead with a 7th EV & Electrify Expo
was made. See Appendix B.
The two key objectives are to:
Goal 1: Promoting community actions to achieve net zero emissions.
We will provide leadership and management of projects, advocacy, education and community
engagement that help the Noosa community on its journey towards net zero emissions (our core
business)
Goal 2: To be a sustainable organisation.
To fulfill its vision and mission, ZEN Inc must be a well-resourced and efficient organisation.
Objectives
The objectives to achieve these goals are outlined in Appendix B, along with their associated
Outcomes/ Measures of Success.
Strategies
The key priorities and higher-level elements identified through our SWOT analysis have informed our
strategies. The strategies inform the ZEN E and ZEN TAG action plans and the activities of our three
sub-committees.
The 2024-2025 ZEN Inc Operational Plan is in fact the Action Plans for the ZEN E (Energy) Group and
ZENTAG (Transport) groups. Both groups undertake projects, some of them at the cutting edge of
community energy.
ZEN E (Energy) Group, ZENTAG (Transport) Group Action Plans & Expo Working Group Workplan
Attached as Appendices C, D & E are the action plans for ZEN Inc’s three Working Groups, where
project work is carried out.
3. Significant developments concerning ZEN Inc. activities
ZEN Inc. is a regional influencer and change agent for the Noosa Community in assisting them to move
towards the goal of net zero greenhouse gases. In 2024, we made significant progress with projects
and engaging with the Noosa Shire community to m o v e f u r t h e r towards zero net greenhouse
gas emissions. Many ZEN Inc. projects are cutting edge, ground breaking and future focused
renewable energy projects, leading the way in Queensland and in many cases nationally. Some of our
flagship projects included:
3
Page 4
1. Community Batteries - with both:
a. A Qld. Govt. Dept. of Environment & Science Community Sustainability Action Grant
The Business Plan for a Network of Community Batteries in the Noosa Local Government Area to
reduce emissions was completed in May, 2024, Follow up meetings have been held with Energy Qld.,
the former Department of Energy & Climate and various community energy groups across Aust. have
used this report to inform their work in the planning and funding applications for community
batteries. This report also was done in tandem with the planning and development of the Noosaville
Community Battery and was a of great assistance in informing this work. It was a key milestone in the
3+ years of ZEN Inc’s volunteer work in this space.
b. Noosaville Community Battery
The consortium working on the $500,000 federally funded community battery in Noosaville, of ZEN
Inc., Noosa Council and Yarra Energy Foundation (YEF) undertook a huge amount of work to negotiate
the planning and progressing of this project in 2024.
ZEN Inc. led the way in advocating with 54 stakeholders across regulators, government (state &
federal level), industry and consumer energy groups for reduced tariffs and connection fees to make
this and other community batteries financially viable. ZEN Inc. was instrumental in persuading Energy
Qld. to make this battery, the only community owned community battery in Qld., a pilot on the
community energy sector, with Energy Qld. agreeing to cover the tariffs for 5 years, while more work
is done to investigate future financial viability for this and other community batteries.
ZEN Inc. has undertaken the Community Battery consultation for YEF as part of the consortium and
will again in early 2025 to inform and involve the community about the operation of the battery for
community benefit. For further detail see the ZEN Inc. 2024 Annual Report.
2. 2024 6th Annual Electric Vehicle & Electrify Everything Expo
With 5,500 visitors, 65+ exhibitors, saw 80.3% came to learn about electric transport, 69.7% came to
learn about how to save money on home energy e.g. solar, battery, heat pumps. 52% of Expo visitors
will or may purchase an EV in the next 12 months.
The scope of the Expo was expanded in 2024 to include Electrify Everything to assist in household
behaviour change re electricity use and how they can save money, while reducing their emissions.
Thanks to Noosa Council for their final year of MOU financial support for the Expo. For further detail
see the ZEN Inc. 2024 Annual Report.
3. Rewiring Noosa – Electrify Everything
Where ZEN Inc. on behalf of the Noosa Shire community, was chosen to work with Saul Griffiths
Rewiring Aust. project as one of the original community partners.
Mid-year, ZEN Inc. launched our Rewiring Noosa Toolkit developed for us by Rewiring Australia,
followed by making of 7 video testimonials by Noosa Shire community members who have moved
from traditional energy sources to power highly energy efficient appliances, coupled with solar and
monitoring systems. These tools are to ensure all Noosa Shire community members (home owners
and renters alike) can benefit by saving money, AND reducing their carbon footprint.
Thanks to Noosa Council for their grants funding for this project. For further detail see the ZEN Inc.
4
Page 5
2024 Annual Report.
4. Solar for Strata
ZEN Inc. is adding impact and value to previous Council grant funded projects by continuing to
promote them with the relevant target audience. The Solar for Strata on line toolkit and Solar
Champions video are examples of this. While they were completed in 2024 and despite the project
leader stepping down mid-year, ZEN Inc. was able to hold a successful forum, working jointly with
Tourism Noosa to promote these tools to the strata accommodation community.
5. E Bike Library
ZEN Inc. was successful in Nov., 2024 with a grant of $22.392 from the Dept. of Transport & Main
Roads for the Bike Riding Encouragement Program (BREP) Innovation Grant to be able to set up an e
bike library so people can borrow different types of e bikes for a period of two weeks and try them
out to help them make a purchasing decision. This program will get underway in 2025.
All our projects and activities are outlined in detail in our Annual Report.
ZEN Inc. is very appreciative of funding from Noosa Council, the Federal and Queensland
Governments, and the patrons and sponsors of our Expo to assist our work. We are also fortunate
to have a collaborative working relationship with a number of key stakeholders, especially Noosa
Council, Yarra Energy Foundation (YEF), Tourism Noosa and Noosa Junction Assoc., and Noosa
Biosphere Reserve Foundation (NBRF) and Energy Qld. to name a few. We thank them all for their
support.
6. The Role of Council Alliance Partnership Funding for 2024
The Council Alliance Partnership Funding is the enabler that allows ZEN Inc. to undertake its
administration, internal organisation and operations through a combination of volunteers and an
Administration Coordinator who began working 24 hours per week in October, 2023, in both
administration and some limited communications work. This was intended to enable some ZEN Inc.
volunteers, especially the ZEN Inc. Chair, to spend some more time to undertake ZEN Inc’s cutting-
edge project work.
In the first half of 2024, the Alliance Partnership Funds for the following positions were funded by
the $65,000 from the Year 1 2023 -2024 funding:
1. Administration & Communications $50,000 (a small amount used in 2023 and most was
used in the first half of 2024 as year 1 funding was not received until Oct. 2023) and
2. Communications Package $15,000 (a small component was used in 2023 and part used in
the first half of 2024 for marketing for the EV Expo. )
as outlined in Appendix F.
In the second half of 2024, after the Alliance Grant Year 2 of funding was received on 23 Oct., 2024,
only $14,393.32 was spent before 31 Dec., 2024. The reasons for this are explained below.
The Administration role was for 21 hours per week, with 3 hours per week to assist with some
Communications work that assisted ZEN Inc. with limited website updating and production s of
regular newsletters, some assistance for volunteers with writing of print media and social media
posts, including for the EV & Electrify Everything, in addition to organising community forums,
promoting ZEN Inc’s resources e.g. tool kits and videos, through various media channels to help raise
5
Page 6
awareness in the Noosa community of ways to save money and reduce emissions.
The Communications Package was to assist ZEN Inc. with website updating/revision & marketing
advice for ZEN Inc. generally & the EV Expo or similar, in addition to education and advocacy about
emissions reduction to the Noosa Shire community, including ZEN Inc’s project work, through
various media channels.
This was only partially used to engage a Marketing and PR business to develop social media tiles to
promote the Expo to help improve the geographic and demographic reach of ZEN Inc., with
disappointing results. Hence, that business was not engaged any further to assist in implementing
the full Communications Package from June 2024 on. Also, due to HR issues with the ZEN Inc’s
employee in the Admin./Coordinator role, and the recruitment of the Program/Project Manager
role, ZEN Inc. was unable to appoint a suitable business to implement the Communications Package
until early 2025.
Hence some Year 2 Council Alliance Partnership funds that should have been used for in 2024 have
been carried over for use in 2025.
The desired outcome of having the Administration/Coordination position with some
communications assistance was to enable the ZEN Chair to spend more time working at the strategic
level to develop collaborative relationships and be involved in strategically important projects, e.g.
to step into the project leader role for the Community Battery project as long-time volunteer project
leaders stepped back and to step back from the lead role in the Expo organisation each year.
As it became obvious during 2024, that the skill set of the person in the Administration/Coordination
role was more communications aligned than administration aligned and also to help fit in with the
employee’s family needs, the number of work hours the employee worked, were reduced at her
request. Hence, the support from this role to the ZEN Inc. Chair in particular, was less than expected.
In addition, as the ZEN Inc. Chair is also Chair of the Communications and Advocacy Committee,
being diverted to deal with HR issues meant that the appointment of another media and marketing
organisation to work with ZEN Inc. has not been possible until early 2025.
Following the Alliance Partnership Funds being raised to $125,000 per year for years 2 & 3 of the
agreement from July, 2024, this enabled ZEN Inc. to employ a Program and Project Manager in Nov.,
2024 for 19 hours per week, as well as the same person in the Administration /Secretariat role for
10 hours per week. These roles were established to help keep the organisation working, and take
the majority of admin. work and some project work from the volunteer ZEN Inc. Chair, who has
been working as a volunteer CEO for 40 – 50 hours per week.
As these positions were only filled in Nov., 2024, it was too early to include an evaluation of the
effectiveness of these roles in this report for 2024, but there are some very promising signs for ZEN
Inc. with the new employee.
6
Page 7
7. Annual Report against the Utilisation of 2024 Funding/Projects and
Status, including % of projects completed within target time frames
All of the funded projects have been or will be completed within the required timeframe. One of the
grants from Noosa Council, Energy Assessments and Upgrades for Low Income and Vulnerable
Households, has required a variation to re-focus the project, due to the difficulty of engaging with
organisations to select the households to be involved.
Source Amount Description Project Status Acquitted/Acquittal
Due
Noosa Council $7,500 2024 Electric Vehicle Expo Final Completed. 2024 Year 3
(+GST) year of MOU for “Seed Funding” Expo completed finished 30
successfully5,500 July, 2024
people attended. 52% within
of Expo visitors will or timeframe.
may purchase an EV
in the next 12 months
Noosa Council $7,169 Solar for Strata Stage 3 - Completed. Video 31 July 2024
(+ GST) Supporting Solar Champions made. Lives on ZEN Within extended
Video (Climate Change Grants) inc. website. You timeframe
Tube Snap shot
Videos were made.
Video referred to at
Tourism Noosa
Forum Nov. 2024 &
shown to Team Body
Corporate & Other
solar for Satra
enquiries in Noosa
Shire & interstate.
Noosa Council $ 19,455 Rewiring Noosa – Electrify Completed. 8 30 June, 2024 within
(+GST) Everything Toolkit & 8 videos community forums at timeframe
Libraries, community
centres, Expo, RACV
resort.
Qld. Govt. Dept. $49,100 Community Sustainability Action Completed. 30 May 2024
of Environment (+GST) Grant – Develop a Business Plan Investigate storage within timeframe
& Science for a Network of Community and solar PV
Batteries in the Noosa Local opportunities,
Government Area to reduce Research for sites,
emissions. Stakeholder
discussion,
Community
consultation
completed. Final
Report written &
distributed to key
stakeholders and
Community energy
groups.
Noosa Council $29,000 (+GST) Energy Assessments and In progress. 30 June, 2025
Upgrades for Low Income and Grant variation on
Vulnerable Households 29 Jan., 2025 as
very difficult to find
low-income homes
to participate in
energy audits.
Noosa Council Remainde Alliance Partnership Agreement Completed 30 June 2024 Was
r of Administration of ZEN Inc. as a be completed within
$65,000 small business and some timeframe
(+GST) Communications – Marketing &
for 2023- PR work
7
Page 8
2024
Noosa Council $125,000 Alliance Partnership Agreement In progress 30 June, 2025
for 2024- Administration/Secretariat of
2025 ZEN Inc. and Program/Project
Manager roles to help run ZEN
inc. as an efficient & effective
Not for Profit, and for
Communications – Marketing &
PR assistance
NB: For 2024 total grants = $179,669 using only 50% of grant figures that go across 2023-2024 & 2024 -2025
8. Leveraging achieved from Council funding calculated as a total of funded
projects compared with Council approved project funding.
ROI = 21.3
$1,102,643+
$922,360 (direct &
$633,060 indirect)
7,695 In Kind Additional
volunteer hours Contributions
The value of ZEN Grants, Goods and services
Inc. volunteer board sponsorships sales resulting from
and working groups &/or in-kind ZEN Inc’s projects
hours on projects contributions EV EXPO
and related received from ($1,102643) + $ YEF,
facilitation other Saul Griffith’s
organizations, Rewiring Aust., E
state or federal Racing teams &
government others)
(excl.
industry
expertise
Projects & Activities = 1,463,097 people
Number of People reached with ZEN Inc.uncosted
e.g. YEF)
ZEN Inc.’s ROI & Contributions to Council’s bottom line
1. “Value adds” $2,659,103 + for the rate payer dollar
2. Is $2,659,10+ per annum saving to Council i.e. If ZEN Inc. didn’t exist, the work
ZEN Inc. does would cost Council *
* Based on an av, value of ZEN Inc volunteers at $120 per hour, way below market rate for much of its project work.
Not only is this a massive contribution to the Noosa community, but it enables Council to leverage
massively from the volunteer work done by ZEN Inc., in addition to contributing to emissions
reduction and climate change impact in the Noosa Shire community.
8
Page 9
Source Amount Description Funding Leveraged Volunteer In Kind
Hours
Noosa Council $7,500 2024 EV & Electrify Everything $96,000 + Tony 25
(+GST) Expo MOU for “Seed Funding” hrs per
Project Leader Tony Clark week x 4
5,500 people attended weeks
both expos 100 hrs
per month
52% will make a purchasing
decision in the next 12 months. x for 8
months =
800 hrs
@$120
per hour
$7,680 NJA 2 hrs
x 4 weeks
=8 per
month x 8
months =
64 hrs @
$120 per
hour
$8,000 + Vols. on
$1,102643 day 20 x
Economic 8 hours =
value 160 hrs x
$50 per
hour =
$8,000
Noosa Council $7,169 Solar for Strata Stage 3 - $4,800 Jenny 40 hrs @
(+ GST) Supporting Solar Champions $120 per hour
Video (Climate Change Grants)
Project Leader: Jenny Clement
Noosa Council $ 19,455 Rewiring Noosa – Electrify $38,400 Mark & Anne or
(+GST) Everything Working with Saul other vol.
Project Leader: Mark Purcell Griffiths Rewiring 8 forums = 20hrs
Australia as one of 10 x 8 = 160 vol.
pilot communities hours x 2 people
= 320 hrs @ $120
per hour
Qld. Govt. Dept. $49,100 Community Sustainability Action $38,400 Geoff 10 hrs x 4
of Environment (+GST) Grant – Develop a Business Plan weeks = 40 x 5
& Science for a Network of Community months = 320 hrs
Batteries in the Noosa Local @ 120 per hour
Government Area to reduce
emissions. Project Leaders: Geoff $9,420 Vivien 7hrs x 4
Acton & Vivien Griffin weeks = 70 hrs x
Noosaville $10,000 Develop a Community 11 months =
Community (+GST) Consultation Plan with Noosa 77hrs x $120
Battery Council & undertake + Community battery per hour
Commun ity Community Consultation $500,000
Consultation Project Leaders: Geoff Acton &
Vivien Griffin
ROI Calculator No funding. Project Leader: Rosemary Grundy $24,000 10 hours per
week x 20 weeks
= 200 hrs x $120
per hour
ZENDURO No funding. EV related project at Schools $5,760 John F 2hrs per
Project leader: John Fuller following week x 8 hrs per
up leads month x 6 mths =
48 hours @ $120
9
Page 10
per hour.
Noosa Council $65,000 Partnership Agreement $264,000 + Anne 2024 50 hrs
(+GST) Grant Leader Anne Kennedy x 4 weeks = 200
Coordinating administration of hrs x 11 months
ZEN Inc. as a small business & =2,200 hrs @
supervising one staff member $120
Grant enables ZEN Inc. to do Colin incl.
Admin. & Communications work Treasurer’s role) -
30 hrs x 4 weeks
$158,400 = 120 hrs x 11
mths = 1,320 hrs
@ $120
ZEN Inc. No Board $48,000 Board
volunteers Funding 9 meetings x 5
working in & on hours incl. Prep.
the organisation, Time = 40 hours
media, projects x 10 people =
(in addition to the 400hours @
project leaders $120 =
hours included
above) Governance & Operations, $4,320 2 meetings x 2
hours= 4 hrs x 5
people =20 hours
@ $120 per hour
Finance & Fundraising, $11,520 6 meetings x 2
hours = 12 x 3
people= 36 hours
@ 120 per hour
Communications & Advocacy $ 26,400 8 meetings x 2
meetings & follow up work, hours=16 hours x
6 people = 96
hours @ $120
per hou
print media 2024
$52,800
Jenny 5 hrs x 4
weeks = 20 hrs x
11 months = 220
hrs@ $120
social media $15,840 Duncan 10 x
4weeks x 11
mths = 44hrs @
$120
John 3 hrs x
4weeks = 12
hours x 11
months = 132 hrs
$120
Rosemary &
$38,400 Gerry 8 videos x
20 hrs each =
160 hrs x 2
people = 320 hrs
@ $120 per hour
data gathering, IT &
10
Page 11
Website;
ZEN Inc. No ZEN E $26,400 Mark = 20 hrs x
volunteers Funding 11 months = 220
working in & on hrs@ $120
the organisation,
media, projects
$14,400 ZEN E Group - 6
(in addition to the
project leaders people x 2 hrs
hours included per month = 12
above) hrs x 10
meetings = 120
hrs @ $120
ZENTAG $21,600 Carina - 5 hrs x 4
weeks = 20 hrs x
9 months = 180
hrs@ $120
ZENTAG Group
Expo Working Group meetings $7,200 3 people x 2 hrs
x 10 meetings =
60 hrs @ $120
ZEN Inc. No Strategic Planning Review Day $9,840 12 people x 6 hrs
volunteers Funding = 72 hrs + 6
working in & on hours for Cathy
the organisation, write up + 4 hrs
media, projects briefing = 82 hrs
(in addition to the @ $120
project leaders
hours included
above)
Expo related $53,086
revenue –
sponsorships,
donors,
exhibitors
Community $500,00
Battery
$608,686 $923,400 7,695 vol. hours
contributions to the
Noosa Community
in non-council
grants/funding
plus sponsorships
and in- kind
contributions Incl.
community battery
& EV Expo)
9. Range of methods of communication and estimated audience reach –
Number of People reached with ZEN Inc. Projects & Activities = 1,463,097 people
EV Expo 5,500 visitors + 126 businesses in Noosa Junction + 65 Exhibitors +
120 potential exhibitors
Community Battery Group 200 in Regional groups
54 Key stakeholder groups in CB advocacy
11
Page 12
Solar for Strata Forum 25 body corporate related entities
with Tourism Noosa
Studies
Solar for Strata Stage 3 500people across Aust.
Supporting Solar Champions
Video
Saul Griffith Electrify 250 people
Everything Bris, Forum
8 Electrify Everything 160 people
Forums in Noosa Shire
Green Drinks Electrify 50 people
Everything @ RACV Resort
Solar Citizens Forum @ 50 people
Maroochydore
Biz to Zero Talk 100 people
Energy Qld. Network 30 people
Pricing Group
Noosa Council Staff 7 Crs. + 15 Council staff
ZEN Inc. newsletters 1,110 x 14 = 15,400 people
NBRF newsletters 500 x 2 = 1,000 people
Tourism Noosa Social media & newsletters x 2 = 452,000
Coalition for Community 300 people
Energy Conf. (C4Ce)
ZEN Inc. website 7,900
ZEN Expo website 5,800
ZEN Inc. Facebook 3,100
ZEN Instagram 77
Print media Noosa Today 22,000 people x 23 issues = 506,000 people
Your Local Lifestyle (YLL) 8,000 x 6 times per year = 48,000
Radio Hot 91 @ Expo 500,000 people
ABC Sunshine Coast 275,000
SEA/MIX FM 97,400
Tress for Tourism 50 people
LREZ Launch @ Caloundra 50 people
NBRF Awards 120 people
Senate submission 300 people
ZEN Inc. Members & Public 63
Fund Account Committee
Total 1,463,097 people
10. Financial Statements for 2024
Please note: ZEN Inc’s Financial Year is Jan. – Dec., 2024
a. P&L For Jan. – Dec., 2024
The Profit & Loss Statement for the above period shows:
Gross Profit was $194,868.86
Total Operating Expenses $ 61,523.69
Net Operating Profit $ 133,345.17
12
Page 13
While this might look like a healthy bank balance, the majority of these funds are project based from
grants and so are allocated to a specific projects. Refer to Appendix H for details.
b. P&L for Projects Jan. – Dec., 2024
The Profit & Loss Statement by Project shows that for the period 01 Jan., 2024 to 31 December 2024
all $150,144.89 of funds were spent as per project plans.
Refer to Appendix I for details.
c. Balance Sheet- as at 31 Dec., 2024
ZEN Inc. total assets were $244,570.032, with total liabilities $13,195.73 and net assets were
$231, 379.79 and equity at $231, 379.79. See Appendix J.
11. Audited financial report for financial year
The accounts audited by Louise McNeich, auditor, LMC Financial Group at Cooroy.
Refer to Appendix K. As the audited accounts were only provided by the Auditor recently, they are
attached unsigned as it has not been possible to get them signed by both parties prior to submitting
this report.
12. Donations - DGR funds
Zero Emissions Noosa Inc. was granted DGR status with immediate effect by the Assistant Minister
for Competition, Charities and Treasury on 23 September 2022. The balance of the account has
varied, as funds have been transferred to the Operating Account to meet expenses, on an as needs
basis, particularly for the 2024 EV & Electrify Everything Expo. The expenditure of these funds have
been agreed by the ZEN Inc. Public Fund Account Committee, as meeting the objectives of the
organisation.
Date Balance
01 Jan. 2024 $1,728.05
Nov. 2023 $18239.04 following donations to ZEN Inc.
26 Aug., 2024 $1,778.94 after funds from this account were used to assist the objectives of
ZEN Inc., including the 2024 Expo.
31 Dec., 2024 $2,309.24 following further donations
ZEN Inc. is actively seeking donations to it’s Public Fund Account.
13. Any significant delays in performing the ZEN Inc. program for this
Agreement
The biggest risk for Council and ZEN Inc. is finding sufficient volunteers to be project leaders and to
actively drive projects and source future funding sources. Hence, the ability to appoint a part time
Program/Project Manager in late 2024, will partly assist our volunteers in 2025 with projects..
Getting dedicated volunteers, with time, since COVID has been difficult, and many of the very active
volunteers who have been involved with ZEN Inc since it’s inception or for many years, after having
given thousands of hours of volunteer time to ZEN Inc. & Council, have stepped back from being
actively involved in ZEN Inc. projects.
13
Page 14
Appendix A ZEN Inc. 2024 Org. Chart
ZEN Inc Board
Governance & Finance & Communications &
Operations Funding sub- Advocacy sub-
sub- committee committee
committee
Public Fund
Account
ZEN E Management
(Electricity) ZEN Transport EV Expo Working Committee
Working group Working Group Group
(Projects) (Projects)
14
Page 15
Appendix B
ZERO EMISSIONS NOOSA Inc
ZEN Inc STRATEGIC PLAN 2023-2026
Introduction
Our vision is for net zero emissions in Noosa Shire.
Zero Emissions Noosa Inc seeks to make Noosa Shire a leading local government region in zero
emissions. We seek to do this by supporting the community in the transition to net zero emissions
through project leadership, advocacy, and the provision of information to all sections of the Noosa
community.
Our strategic plan outlines how we will achieve this mission as we seek to seize new opportunities
and meet the challenges of the future. While our strategic plan is future focussed it is grounded in our
contemporary operating environment which is heavily influenced by the pressures on our resource
base – both financial and human.
Since ZEN Inc was founded in 2016, the need to reduce emissions is more pressing than ever if we
are to avoid catastrophic climate change. The transition to a cleaner energy future has seen more
changes and challenges than at any time in recent years. Meeting the needs of our community in this
space is a major challenge, but also a significant opportunity.
This strategic plan sets out our vision for the future and a framework for its delivery over the next
three years. It includes:
• our vision for net zero emissions in Noosa Shire.
• the roles that define where we will work to deliver the vision.
• our aims within those roles; and
• an outline of our priorities in delivering those aims.
Through our planning process we have developed strategic priorities for the next three years framed
around our two key goals:
• Promoting community actions to achieve net zero emissions.
• Developing a sustainable organisation
This strategic plan is not a static document and the Board, and its working groups will give ongoing
consideration to ideas and suggestions that have been put to us as well as giving consideration to an
increasingly dynamic and challenging environment throughout the period of this plan.
Each year we will report on how we have delivered on this strategy at our annual general meeting and
through our annual report.
Organisational Description
Zero Emissions Noosa Inc (ZEN Inc), established in 2016, is an incorporated, not-for-profit,
community organisation with the key objective of assisting the Noosa community achieve net zero
emissions in the Noosa local government area. ZEN Inc has been actively pursuing several strategies
aimed at achieving this objective.
15
Page 16
It is the leading community organisation in this field and the only community organisation solely
dedicated to emissions reduction across the Noosa Shire.
The two key objectives of the organisation have been to drive projects in the stationary electricity and
transport areas aimed at assisting individuals, businesses, and the community at large, in contributing
to emissions reduction.
The core work of the organisation is carried out by two working groups – ZEN E (Electricity) and ZEN
TAG (Transport). The focus of ZEN E’s work is on projects that assist in reducing emissions in the
stationary electricity sector with initiatives that assist a greater uptake of solar as well as storage and
other initiatives. ZEN TAG’s focus is on reducing emissions from transport by encouraging, advocating
and demonstrating low emissions alternatives to the dominant petrol / diesel driven motor vehicle. The
annual EV Expo is ZEN Inc’s flagship event in this regard.
Organisational support is provided through the work of three sub-committees; Finance & Fundraising;
Governance & Operations; and Communications & Advocacy.
ZEN Inc Board
Governance & Finance & Communications &
Operations Funding sub- Advocacy sub-
sub- committee committee
committee
Public Fund
Account
ZEN E Management
(Electricity) ZEN Transport EV Expo Working Committee
Working group Working Group Group
(Projects) (Projects)
Vision
Net zero emissions in Noosa Shire.
Mission
Working with the Noosa community to achieve net zero emissions to address climate change.
Core Values / Values Statement
Values Thinking Behaviour
Honesty Independent Respected
Transparency Inclusive Collaborative
Accountability Evidence based Inspirational
Ethical Excellent Empowered
Our values statement describes how ZEN Inc works internally and externally.
16
Page 17
ZEN Inc works independently to provide leadership by empowering its members and stakeholders
with ethical, independent, evidence-based solutions for reducing Noosa’s net greenhouse gas
emissions to zero. We do this by operating in an honest, accountable, collaborative, and inclusive
way.
Goals
Our goals are the key focus areas that will move the organisation to achieve its vision and its mission.
We have identified two goals for 2023 – 2026:
Goal 1: Promoting community actions to achieve net zero emissions.
We will continue to focus on our core business. We will provide leadership and
management of projects and initiatives that help the Noosa community on its journey
towards net zero emissions.
Goal 2: To be a sustainable organisation.
We recognise that for ZEN Inc to fulfill its vision and mission it must be a well-
resourced and efficient organisation.
Objectives
Our objectives support the two key goals identified above. Our outcomes describe how we will
measure the progress needed.
Objectives Outcomes / Measures of success
1.1 Reduced business and household stationary
energy emissions.
ZEN Inc will focus on its core project work to deliver • Projects delivered within agreed
emissions reduction initiatives to the Noosa timeframes.
community. • Business and household
emissions reduced
1.2 Reduced transport energy emissions
ZEN will focus on promoting transport initiatives and • Increased use of sustainable
sustainable transport options that reduce greenhouse transport options including public
gas emissions. transport, unpowered vehicles
and walking
• Increased uptake of electric
powered vehicles (EVs) and
reduced use of internal
combustion vehicles (ICEVs)
1.3 Increased community awareness of initiatives
to reduce emissions
ZEN Inc will provide information to the community to • Increased community uptake of
assist in the implementation of emissions reduction information and tools
actions. • Effective dissemination of
information through ZEN Inc’s
website.and other channels.
• Increased participation through
community engagement.
17
Page 18
2.1 Increased financial sustainability
ZEN Inc will work to ensure that it is a financially • Ongoing funding secured.
sustainable organisation by aiming to secure ongoing • Funding sources diversified
funding and by diversifying its funding sources.
2.2 Efficient organisational operations
ZEN Inc will continue to develop its resource base and • Continue a culture of continuous
review its processes and procedures to be an efficient improvement.
and effective organisation. • Governance & Operational
manual developed.
• Processes and procedures
refined and rationalised
2.3 Effective external and internal communications
ZEN Inc will develop effective internal initiatives to • Increased community awareness
enhance the way we work and increase awareness of ZEN (who we are; what we do)
amongst the community of who we are and what we • Brand strategy developed
do.
2.4 Strong strategic relationships.
ZEN Inc will build on and further develop strong • Increased engagement with
strategic relationships with our stakeholders to stakeholders.
collaborate in reducing emissions. • Collaborative and productive
partnerships strengthened and
widened
• Respective roles of ZEN Inc and
Noosa Council are mutually
beneficial.
Situation Analysis
In developing this strategic plan, we examined the internal and external environment in which the
organisation operates with a view to addressing some of the threats that we face while seeking to
maximise the opportunities before us.
Since its formation in 2016, ZEN Inc has had, as its vision, “net zero greenhouse gas emissions
across the Noosa region by 2026”. While progress has been made in reducing emissions across the
Noosa Shire, realistically we have no agreed way of measuring whether we will achieve that goal
within the stated timeframe.
While ZEN Inc remains strongly committed to its mission to achieve net zero emissions, we have
dropped the 2026 timeline from our vision statement and modified it accordingly.
We recognise that we are operating in a rapidly changing environment. While that poses threats as to
whether we have the capacity and resources to manage those challenges, we hope to capitalise on
the opportunities presented by the changing environment. The strength of the organisation lies in a
highly experienced and committed Board and a volunteer and supporter base committed to taking
practical action to help reduce emissions across the Noosa Shire.
Internally, the organisation lacks a strong financial base and some strengthening of our governance
arrangements will assist the way we work. Our undoubted strength is our commitment to several key
project initiatives that have firmly placed the Noosa Shire as a leading local government area on the
road to a net zero emissions future. However, while our key focus remains on our project work, we
recognise that our project teams need to be supported by a well-resourced and efficient organisation.
18
Page 19
Building on our signature strength of innovative project work, our strategic plan continues to focus on
project delivery that helps the community move towards a reduction in net zero emissions. For
example, the “Electrify Australia” movement led by Saul Griffith offers significant opportunities for ZEN
Inc to assist the community at the local level. Providing guidance in helping households to “electrify
the home” while also developing initiatives that will assist in “electrifying everything” presents us with
several opportunities.
Federal Government policy and funding initiatives also provide opportunities which ZEN Inc will
continue to embrace.
While we have enjoyed several high-profile successes, there is a recognition that our communications
could be improved to maximise the impact of our initiatives and more time needs to be spent on
stakeholder engagement. The benefits that our work brings to the community, as the leading source of
information on emissions reduction in the Noosa LGA, needs to be better explained.
Demonstrating how we deliver benefits to the Noosa community is both a challenge and an
opportunity.
A lack of brand identity could be strengthened as there is a perception that ZEN Inc’s. is done by
Council.
There is an opportunity for both ZEN Inc and Noosa Council to clarify our respective roles to work
collaboratively to assist the Noosa community on its journey to net zero emissions.
The provision of community education on emissions reduction strategies offers an ongoing
opportunity.
Strategies
The key priorities and higher-level elements identified through our SWOT analysis have informed our
strategies. The strategies inform the ZEN E and ZEN TAG plans and the activities of our three sub-
committees.
19
Page 20
ZEN’s GOALS, OBJECTIVES & STRATEGIES
GOAL 1 GOAL 2
Promoting community actions to achieve net zero To be a sustainable organisation
emissions
OBJECTIVE 1.1 OBJECTIVE 1.2 OBJECTIVE 1.3 OBJECTIVE OBJECTIVE 2.2 OBJECTIVE 2.3 OBJECTIVE 2.4
2.1
Reduced business and Reduced transport energy Increased community Increased financial Efficient Effective external Strong strategic
household stationary emissions awareness of initiatives to sustainability organisational and internal relationships
energy emissions reduce emissions operations communications
STRATEGIES STRATEGIES STRATEGIES STRATEGIES STRATEGIES STRATEGIES STRATEGIES
Undertake targeted, large Promote transport initiatives Greater direct engagement Build a strong Strengthen well Increase awareness Strengthen and broaden
impact projects to that reduce greenhouse gas initiatives with the Noosa Shire financial position to connected and amongst the collaborative and
maximise emissions emissions community support our collaborative working community of who productive partnerships
reduction projects and groups and sub- we are and what we
activities committees do
Encourage community Encourage walking and Develop online toolkits to Apply for Federal, Develop clear Maintain ZEN Inc as Increase reach and
initiatives that support cycling initiatives facilitate energy transition and State and Council processes to support a significant influence as the leading
uptake of renewable emissions reduction funding the organisation in contributor to community organisation
energy the delivery of emissions reduction advocating emissions
projects, events & within the Noosa reduction.
programs Shire.
Develop the “electrify Promote carbon capture Effectively disseminate Diversify funding . Ensure benefits of Work with Noosa
everything” concept technologies and initiatives information through ZEN Inc’s sources projects and Council in differentiated
across the Noosa Shire to offset car travel website and other activities are roles for mutual benefit.
communication channels. communicated to
stakeholders
Ensure battery initiatives Review Noosa Council’s Examine potential Foster effective
are delivered within Transport Strategy and revenue streams communication
agreed timeframes make recommendations pathways both
internally and
externally
Implement Solar for Strata Review commitment to EV Develop a ZEN
initiatives Expo.. brand strategy
20
Page 21
Progress the concept of Advocate for, and
an energy hub at Peregian demonstrate, sustainable
Beach / Marcus Beach transport options for
transport that reduce
greenhouse gas emissions.
Advocate for EUAs for
residential dwellings,
including for low-income
households, landlords and
tenants
Examine methodologies
for carbon accounting
See page 8 to follow
21
Page 22
Key Actions
The Strategic Plan is our overarching planning document and guides the work of our working groups and
sub-committees.
Specific actions will be progressed through the two working groups and three sub-committees to give
effect to the strategies identified in the Strategic Plan
Monitoring and Evaluation
Our planning and reporting framework is designed to support the implementation of this plan and the
realisation of our vision for an emissions free Noosa.
The strategic plan identifies the key measures of our success and the outcomes that we hope to achieve
as measured against our two key focus areas (goals) and the strategies we will employ.
Performance against these outcomes will be reviewed, where possible, throughout the year but at least
once each year, and reported to enable the Board to monitor progress.
Working groups are encouraged to develop measures of success for their respective projects and
activities as outlined in their action plans.
Prepared: August 2023 (Org. Chart updated Feb. 2025)
Email: [email protected]
Website: www.zeroemissionsnoosa.com.au
Appendix: The SWOT Analysis
Strengths (Internal)
Committed and experienced Board
Existing runs on the board
Existing connections with groups / individuals
Members and volunteers
Strong relationship with Council
Reputation / credibility
Organisational basics in place
Large database on emissions reduction information
Consistent communication capability
ZEN Inc. uses evidence-based solutions
Weaknesses (Internal)
Over reliance on the ZEN Chair
Insufficient people to delegate to
Insufficient paid human resources
Lack of participation in working groups
Lack of human resources to implement information management systems (shared drive / website)
Lack of financial sustainability
Opportunities (External)
Working with Noosa Council
Other zero emissions communities e.g. ZEB
22
Page 23
Rewiring Australia (stakeholders, YEF)
Diversification of funding sources
Federal / State governments (engagement, advocacy, grants)
Tap into community sentiment
Clarify carbon accounting (support)
Stakeholders (e.g. universities)
Industry
Community benefits (financial, environmental, sustainability, health)
Information sources
Threats (External
Disbelief within the community
Current 2026 goal maybe unachievable
Too much to do…may get lost
Seen as an “arm” of Noosa Council; who does what (vis a vis ZEN / Council)
Funding resources
ESG (Environmental, Social and Governance)
Changing government priorities
Insufficient paid human resources
23
Page 24
Appendix C - 2024 -2025 ZEN E Working Group Action Plan (5)
ZEN Inc. 2024 -2025 ZEN E Working Group Plan Action Plan Reviewed & Updated Aug., 2024 v. 5. KPI’s updated Feb., 2024
See notes below re links from Council’s Corporate Plan Themes & associated plans to the ZEN E Working Group Action Plan.
Goal 1 (As per ZEN Inc. Strategic Plan): Promoting community actions to achieve net zero emissions
OBJECTIVE 1.1 Reduced business and household stationary energy emissions
ZEN Inc. STRATEGIES ZEN e Projects Timeframe / KPI Project Lead & Group Noosa Council
(What) (How) Members (Who) Climate Change
Response Plan
(CCRP) Themes &
Economic
Development
Strategy 2021-2030:
Outcomes & Benefits
1. Undertake targeted, All projects See KPI’s for each project Theme 1: Leadership
large impact projects to below and governance
maximise emissions 1.1 Mobilise community
reduction for climate action
Community Batteries 1.2 Action for low
Rewiring Noosa - carbon economy &
“Electrify Everything” resilient
Solar for Strata community
1.3 Council is a
2. Encourage All projects See KPI’s for each project powerful influencer for
community below climate action
initiatives that support
24
Page 25
uptake of renewable
energy
Solar for Strata
Rewiring Noosa -
“Electrify Everything”
3. Develop the a.Rewiring Noosa - Advocate/promote to
“electrify “Electrify Everything” – external organisations & Theme 2: Energy
everything” concept Stage 2 - roll out to trades speak at 4 forums by June efficiency and
across the Noosa Shire people (Rewiring Noosa Surfers for Climate - renewable energy
2025
Rewiring Noosa - “Trade Up” (Anne) 1.1 & 1.2
Plan says 655 x local jobs - Clean Energy Council
“Electrify Everything” -
Stages 1 & 2 available) roadshows. Cleantech Network Theme 3: Clean low
e.g. Surfers for Climate - In progress (Anne) emissions industries
“Trade Up”; 3.1 & 3.2
-Cleantech Network; TAFE & Environmental
-TAFE Education Hub (Anne); Theme 7: Resilient &
-Environmental Education adaptive communities
ZENDURO project &
Hub - STEM subjects;
(Gillian Carter); built environments
- ZENDURO project – Electrical Trades 7.1 & 7.2
STEM subjects; Association (Mark)
- Electrical Trades Plumbing Trades Theme 6: Sustainable
Association; Association (Mark) agriculture and food
- Plumbing Trades systems
Association; 6.3 Support agri-
businesses &
- Electrical wholesalers in
landholders a & b
Noosa e.g. Lawrence &
Hanson Increased number of
high value jobs that
retain local talent
A skilled and talented
workforce driving
innovation
25
Page 26
b. Powershare (Powervolt) By March 2026 (if ARENA Ewan Theme 3: Clean low
A concept being funded) emissions industries
developed for potential 3.1& 3.2
funding from the ARENA Did not go head.
Solar Scale Up Theme 7: Resilient &
Not Funded
Competition to bring the adaptive communities
cost of large scale solar to &
less than 30c/watt built environments
installed, with a potential 7.1 & 7.2
site in Noosa.
Collaborative and
connected business
Ecosystems are
created
Relevant and
impactful
support provided to
our businesses
4. Ensure battery a.Community Batteries: Noosa Comm Battery Anne & Colin & ZEN E Theme 2: Energy
initiatives i.Noosa Community installed by 30 Jun 2025. Working Group members efficiency and
are delivered within Battery renewable energy
agreed timeframes a. Assist with community By 30 May, 2024 Anne/Colin 1.2 & 1.3
Community Batteries consultation in park In progress but delayed
due to lengthy
negotiations with Energex Anne/Colin Theme 3: Clean low
emissions industries
b.Advocacy for 100 – 200 Ongoing advocacy to 3.1 & 3.2.
community batteries in Energy Qld. through LREZ
Noosa LGA consultation for more Theme 7: Resilient &
community adaptive communities
batteries/community energy & built environments
resources. Done & Ongoing 7.1 & 7.2
By 30 September, 2024 Infrastructure
Done accelerates
26
Page 27
c.Follow up AER response By mid-December, 2024 Anne/Colin & consult industry development
to Tariff review Done Vivien Griffin and
submissions. Smart Precincts
By 30 September, 2024 Anne/Colin & consult Collaborative and
d. Follow up Energy Done Vivien Griffin connected business
Queensland re final Ecosystems are
submission of TSS to AER created
e. Follow up Ausgrid From Aug. 2024 to Anne/Colin & consult Expanded and
LUOS tariff approach to completion early 2026 Vivien Griffin /Annie specialised
Ongoing Nolan education and
encourage uptake of
research
Community Batteries. opportunities
(Ausgrid have a positive
approach to encourage Relevant and
uptake of Community impactful
Batteries) support provided to
our
businesses
f. Participate in AEMC
To be Done Anne/Mark/Colin Businesses
Pricing Review TOR maximising the
development. global opportunities
and
g.Continue advocating to By March, 2025 selling to the world
Energy Qld. for ZEN Inc. Done in Oct.,2024 & is Anne/Colin
Ongoing
to be represented on a
possible Qld. Consumer
Energy Roadmap
consultative group.
h.Follow up existing Ongoing Anne
relationships with Solar
Citizens and Re-Alliance
re Local Energy Hubs.
27
Page 28
i.Look for opportunities for Done Jan. 2025 & Colin/Anne
future battery cross over Ongoing
See d & f below
with the Solar for
Business project
(apartment batteries).
ii. Qld. Govt. Community As above
Battery Roadmap –
Business Plan for a
Roadmap of Community
Batteries in Noosa LGA
a. Distribute to key
ZEN Inc. By 30 Sept.,2024 Anne
stakeholders Done
b. Follow up with By 30 Nov., 2024 Anne, Colin & Mark
Dept. of Energy & Done.
Climate re
distribution of key
stakeholders State
-wide
5. Assist for Low Income c.Energy Efficiency Colin & Jenny Theme 2: Energy
households Assessments & efficiency and
Upgrades of 20 Low renewable energy
Income Homes By 30 Dec. 2024 1.3 & 1.4
i. Follow up with Coast 2 Done but with very limited
Bay; St Vinnies; success due to difficulty Theme 3: Clean low
Community Health; You engaging low income emissions industries
Turn, etc. for client’s clients through social 3.1 & 3.2
homes to work with welfare agencies.
Colin Theme 7: Resilient &
ii. Contact Gary at Energy adaptive communities
Flex & QCOSS By 30 Sept., 2024 &
(Queensland Council of Done built environments
28
Page 29
Community Services) 7.1 & 7.2
for recommendations of
an assessor to take part in Enhancing our
the project natural
Colin assets with
iii. Appoint assessor(s) for Assessments by a qualified technology
energy audits energy assessor driving value
Delayed due to difficulty
engaging low income Colin/Jenny
clients through social
welfare agencies.
iv. Energy efficiency Upgrades by 30 June 2025
upgrades e.g. LED lights; Council Grant variation to
curtains & external blinds now fit solar due to
for shading; difficulty engaging low
income clients through
agencies
6. Implement Solar for Strata d. Solar for Strata- “value By 30 June, 2025 - Jenny & Colin Theme 2: Energy
initiatives add” Presentations to Noosa efficiency and
Promoting on line toolkit & Chamber of Commerce & renewable energy
video by: Tourism Noosa 1.4 & 1.5
i.Forums for bodies Tourism Noosa done.
corporates, incl. Theme 3: Clean low
a. Commercial/ industrial Promotion of Online toolkit ‘Jenny & Colin emissions industries
& videos in newsletter, 3.1 & 3.2
strata case studies
July/Nov., 2024
(Chambers of Commerce) Discussions ongoing. Theme 7: Resilient &
adaptive communities
c.Tourism Strata Possible forum with Jenny & Colin &
complexes (Tourism Tourism Noosa built environments
Noosa) Done in Oct., 2024. 7.1 & 7.2
Possible forum with Noosa Jenny & Colin Increased number of
d.Residential (Team Body
Chamber of Commerce high value jobs that
Corporate) Discussions ongoing. retain local talent
29
Page 30
e.Advocate for LREZ to Ongoing as opportunities Anne/Colin/Mark/ A skilled and talented
relax Strata Requirements arise with development of workforce driving
the LREZ Pilots innovation
Done.
Infrastructure
f. Investigate Standalone Dec., 2024, investigate Colin with Matt Harold accelerates
Batteries as an alternative suitability for ZEN E industry development
to solar Projects and
Ongoing Smart Precincts
Collaborative and
connected business
Ecosystems are
created
Relevant and
impactful
support provided to
our
businesses
7. Assist with EV & a.EV & Electrify By June, 2025 Expo Working group Theme 2: Energy
Electrify Everything Expo Everything Expo In Progress efficiency and
Work in conjunction with renewable energy
Expo Working group for 2.1 & 1.6
“Electrify Everything”
component Theme 3: Clean low
EV mini expos (show & 2 mini expos show & tell Expo Working group emissions industries
tell) – book location, invite by 30 Jun 2025 3.1 & 3.2
EV owners to come, invite Not go ahead due to
public to come insufficient volunteers Theme 7: Resilient &
adaptive communities
& built environments
7.1 & 7.2
As for no. 6 above
30
Page 31
8. Solar For a. Solar For Ongoing, including Colin & Anne Theme 2: Energy
Business/Community Business/Community connection to community efficiency and
Buildings Buildings - Energy batteries project renewable energy
Sharing with VPP’s
Vivien to send Colin original Colin & Anne Theme 3: Clean low
Solar/Energy Sharing emissions industries
database by 15 Sept., 2024
i.explore stakeholders & 3.1 & 3.2
opportunities in: Done
a. residential Colin Theme 7: Resilient &
neighbourhoods adaptive communities
b. C&I estates e.g. Noosa Delayed due to shortage Anne &
Chocolate Factory as a of volunteers built environments
case study; [email protected] & 7.2
Cooroy
For info. on possible C&I As for no. 6 above
ii.Liaise with Cleantech Colin
Network members & clustering by 30 Nov., 2024
Chamber of Commerce. Ongoing
iii. Use Nearmaps (to
assess and identify Check ZEN’s subscription Colin
businesses within Noosa to Nearmaps
Shire which do not Done
currently have solar)
iv. Schools – Follow up
from Race 2 Zero Schools Liaise with Dalia @ Noosa
EE Hub by 30 Nov., 2024 Colin & Anne
(large roof areas usage
only during schools hours Not done due to volunteer
e.g. Good Shephard & St overload
Therese’s). Do a Financial Mark P
ROI feasibility Mark to develop a Financial
presentation to show the ROI / Feasibility
financial reward of Presentation by 30 Nov.,
31
Page 32
installing large scale solar 2024 Not done due to
and batteries to create volunteer overload
additional income stream
v.Investigate potential to By 30 Nov., 2024 Colin
work with Sollar Alliance / Delayed due to of
Clear Sky Solar. LINKS: volunteer overload
ClearSky Solar
Investments, Solar
Alliance - Solar Alliance
9. Gather Data & data a. Data By Dec., 2024 Rosemary Theme 2: Energy
Analysis i. Develop usage vs Delayed due to efficiency and
savings calculator matrix. volunteers stepping back renewable energy
from ZEN Inc. 2.2 & 1.7
UQ have data available
for general usage. Brian Theme 3: Clean low
ii. Gamify Local Data Description - Colin to
emissions industries
provide
3.1 & 3.2
Theme 7: Resilient &
adaptive communities
&
built environments
7.1 & & 7.2
Theme 6: Sustainable
agriculture and food
systems
6.3 Support agri-
businesses &
landholders to:
a. Reduce their
emissions
technology
implementation
32
Page 33
b. Take up
opportunities for
income
generation
through carbon
drawdown
As for no. 3 above
10. Examine Emissions reduction Work with Noosa Council Noosa Council Theme 3: Clean low
methodologies barometer Discussions starting with emissions industries
for carbon accounting NBRF & Council 3.1 & 3.2
Theme 7: Resilient &
adaptive communities
&
built environments
7.1 & 7.2
As for 6a above.
OBJECTIVE 1.3 Increased community awareness of initiatives to reduce emissions
STRATEGIES ZEN e Projects Timeframe / KPI Project Lead & Group
(What) (How) Members (Who)
1. Greater direct Community engagement i.Libraries – one per quarter Mark, Colin, Anne, Theme 2: Energy
engagement forums on: till 30 June, 2025 Rosemary efficiency and
initiatives with the Noosa a. Rewiring Noosa - In progress renewable energy
Shire community “Electrify Everything” - & 2.3 & 1.8
promotion of On Line
. “Electrify Everything” Theme 3: Clean low
Toolkit & Videos emissions industries
3.1 & 3.2
b. Community Group ii.3 presentations by 30 Jun Colin, Mark, Adrian,
Forums on: 2025 to Clubs e.g. Rotary, Brian, Anne, ZEN E Theme 7: Resilient &
Rewiring Noosa - Probus, Lions, U3A, etc Working Group members adaptive communities
“Electrify Everything” - & In progress with U3A. &
promotion of On Line Probus & service Clubs built environments
“Electrify Everything” not interested. 7.1 & 7.2
Toolkit & Videos
33
Page 34
As for no. 3 above
C i. Community 2 presentations by 30 Jun Colin/ Mark Theme 2: Energy
Education Forums e.g. 2025 efficiency and
Energex’s planned 2 way renewable energy
pricing & “Demand” Presentations by Mark/Colin Colin/ Mark 2.4 & 1.9
pricing; Controlled load bill Delayed due to volunteer
reading; overload Theme 3: Clean low
household & business emissions industries
energy efficiencies; smart 3.1 & 3.2
home products &
solutions for timing energy Theme 7: Resilient &
use (solar & use of smart adaptive communities
meters) for time of use; &
Better estimates of pay built environments
back periods & More 7.1 & 7.2
information about feed-in
tariffs; complete off grid As for nos. 6 & 9
set up; cheaper chargers above
for work solar carparks;
EV comparison websites;
Grants or government
rebates; Financing; Green
energy purchasing;
Rebates for people to
change to
electrify.
ii. Solar/storage & Incorporated into Solar for Matt Harold/Gareth/
electrification for Strata, Strata talks Ewan As for nos. 6 above
Businesses & Residential
(includes stand- alone
batts)
iii. Carbon Footprint Delayed due to volunteer Colin
Presentation to Board & overload As for nos. 6 above
associated ZEN reps. &
business
34
Page 35
b.EV & Electrify By June, 2025 Expo Project Working
Everything Expo In progress group As for nos. 6 above
c. Community Batteries By Dec., 2024 Vivien Griffin, Anne
– community consultation Preparation in progress. Kennedy & Annie Nolan
for Noosaville Battery Delayed due to lengthy (Council) As for nos. 4 above
negotiations with Energex
2. Promote online a.Rewiring Noosa - As for no. 1a above.
toolkits/reports to “Electrify
facilitate energy transition Everything” – see 1a
and emissions reduction above
b. Solar for Strata – See 3a above. As for 1d above.
Toolkit & Videos As for nos. 6 above
c.Community Batteries - Distribute to key Anne Kennedy & ZEN As for no. 1bi & ii
a Business Plan for a stakeholders & other LGAs Inc. Admin. Coordinator above.
Network of Community as needed.
Batteries in Noosa LGA Done & in progress As for nos. 4 above
3. Effectively a.Work with Comms. & Ongoing so all project Chair ZEN E & Chair Theme 2: Energy
disseminate Advocacy Committee to promoted at least x2 per C&A & ZEN Comms. efficiency and
information through ZEN promote all ZEN E year Officer renewable energy
Inc’s website and other projects using: In progress 2.5 & 1.10
communication channels.
i. Print media i. Fortnightly columns in Theme 3: Clean low
Noosa Today & monthly emissions industries
columns in Your Local 3.1 & 3.2
Lifestyle In progress
ii. Social media ii.Fortnightly posts about Theme 7: Resilient &
one ZEN Inc. project adaptive communities
In progress &
iii. Website iii. Ongoing project updates built environments
In progress 7.1 & 7.2
iv. Newsletters iv. Feature a ZEN Inc.
project every month As for nos. 6 & 9
35
Page 36
In progress above
A. Noosa Council’s Corporate Plan themes & Associated Plans relevant to the ZEN E Working Group Action Plan
Corporate Plan theme Relevant Associated Plans to ZENTAG Action Plan
1. Environment Noosa Environment Strategy 2019
Climate Change Response Plan
Noosa Transport Strategy 2017 - 2027 - development of a new movement and connectivity strategy.
2. Liveability Noosa Transport Strategy 2017 - 2027 - development of a new movement and connectivity strategy
- Cycling and Walking Strategy and Implementation Plan 2020
- Noosa Trails Masterplan and Implementation Plan 2020.
Noosa Housing Strategy 2021
Noosa Social Strategy and Social Justice Charter – new Community Strategy.
- Noosa Health and Wellbeing Plan 2019 -2024.
3. Prosperity Economic Development Strategy 2021 – Smart Biosphere
Waste to Resource Strategy
4. Future Community Strategy – New Community Strategy.
Climate Change Response Plan
Noosa Design Principles
Disaster Management Plan
Local Disaster Recovery Plan
Destination Management Plan
Economic Development Strategy
Waste Strategy (currently under development)
5. Excellence Community Engagement Framework
B. Noosa Council Climate Change Response Plan (CCRP) Themes relevant to the ZEN E Working Group Action Plan
Theme 2: Energy efficiency and renewable energy
1.1 ….100% renewable energy incl. low income & vulnerable residents, businesses, incl. strata tenants
1.2 ….Develop a climate aware and empowered community for reducing climate risks & emissions
1.3 Develop a climate aware and empowered community for reducing climate risks & emissions
1.4 Develop a climate aware and empowered community for reducing climate risks & emissions
1.5 Develop a climate aware and empowered community for reducing climate risks & emissions
1.6 Develop a climate aware and empowered community for reducing climate risks & emissions
36
Page 37
1.7 Develop a climate aware and empowered community for reducing climate risks & emissions
1.8 Develop a climate aware and empowered community for reducing climate risks & emissions
1.9 Develop a climate aware and empowered community for reducing climate risks & emissions
1.10 Develop a climate aware and empowered community for reducing climate risks & emissions
Theme 3: Clean low emissions industries
3.1 …..shift to clean, green low emission industries & technology
3.2 ….. Facilitate emissions reduction & environmental sustainability for local businesses
Theme 7: Resilient & adaptive communities &
built environments
7.1 Create a resilient built environment for householders, businesses, vulnerable people, property & infrastructure
7.2 Build community awareness & preparedness for climate change & extreme weather events
Theme 6: Sustainable agriculture and food systems
6.3 Support agri-businesses & landholders to:
a. Reduce their emissions technology implementation
b. Take up opportunities for income generation through carbon drawdown
C. Noosa Council Economic Development Strategy 2021-2030: Outcomes & Benefits relevant to the ZEN E Working Group Action Plan
1. Increased number of high value jobs that retain local talent
2. A skilled and talented workforce driving innovation
3. Infrastructure accelerates industry development and Smart Precincts
4. Collaborative and connected business Ecosystems are created
5. Expanded and specialised education and research opportunities
6. Relevant and impactful support provided to our businesses
7. Businesses maximising the global opportunities and selling to the world
8. Enhancing our natural assets with technology driving valu
37
Page 38
Appendix D - ZEN Inc. 2024 – 2025 ZENTAG Working Group Action Plan (4)
ZEN Inc. 2024 ZENTAG Working Group Action Plan Reviewed & Updated Sept.., 2024 v. KPI’s updated Feb., 2024
*Subject to funding – application has been submitted. Awaiting outcome.
See notes below re links from Council’s Corporate Plan Themes & associated plans to the ZENTAG Working Group Action Plan.
Goal 1 (As per ZEN Inc. Strategic Plan): Promoting community actions to achieve net zero emissions
OBJECTIVE 1.2 Reduced transport energy Emissions
ZEN Inc. STRATEGIES ZENTAG Projects Timeframe / KPI Project Lead & Group Noosa Council Climate
(What) (How) Members (Who) Change Response
Plan (CCRP) Themes
& Economic
Development Strategy
2021-2030: Green
Economy Plan
1. Promote transport a. *E-bike Library (Subject 30 Nov, 2025 & then possibly Jenny Clement, Phil Theme 1: Strong
initiatives that reduce to funding that has been ongoing. Goldsmith, Darren Walters leadership and
greenhouse gas applied for) Trail started Feb., 2025. governance
emissions Launch in June, 2025 1.1 Mobilise community for
b.*E-bike tours (Subject to 30 June, 2025 (Subject to Jenny Clement, Darren climate action
Council funding that has funding) & then ongoing. Walters 1.2 Action for low carbon
been applied for) – see no. Not running, as ZEN Inc. was economy & resilient
2a below unsuccesful in 2024 community
Community Grants for this 1.3 Council is a powerful
6. Advocate for, and project. May merge into an influencer for climate action
demonstrate, sustainable activity under the E-bike
transport options for Library Theme 2: Energy
transport that reduces c.ZENDURO (with Cooroy End of term 1, 2025 Anne Kennedy/John efficiency and renewable
greenhouse gas State School &/or Sunshine Previous volunteer project Fuller/Gwenn Davidson energy
emissions. Beach State High School) leader unable to assist in 2nd 1.3 Develop a climate
38
Page 39
half of 2024, due to work aware and empowered
commitments. New Project community for reducing
leader discussing with schools climate risks & emissions
for term 2 in 2025.
d.Idle free Noosa in school End of term 1, 2025 Phil Goldsmith & Carina Theme 3: Clean low
zones (Investigate) Research into Idle Free Anderson emissions industries
strategies completed. Need to 3.1 …..shift to clean, green
investigate if there is an low emission industries &
appetite for this in schools, technology
Council and ZEN., but not
progressing at this stage due 3.2 ….. Facilitate
to lack of volunteers time. emissions reduction &
e.Transport Advocacy Review Dec., 2024 Vivien Griffin/Jenny environmental
(incl. Noosa Council's In progress after deputation to Clement sustainability for
transport plan, Kinetic Council in Jan.,2025. local businesses
contract/people movers & E 3 consultations end Feb/early
buses at Expo) (Investigate) March Theme 4: Sustainable
i. Deputation to Council Transport Summit with Transport
ii. Community community and business 4.1 Accelerate public &
forums/Workshops sectors planned to March. active transport
iii. Council Workshop infrastructure investment &
iv. Transport Summit community usage through
v. the implementation of
f.EV Chargers - Investigate Presentations to tourism / Colin Lambie Council’s Transport
promotion of destination EV strata / business orgs. by Strategy and Walking and
chargers to raise June, 2025 Cycling Plan.
awareness; Good EV In progress, Options paper
comparison websites; Solar being developed; articles 4.2 Transition Council &
panels over car parks planned for Noosa Today community to sustainable
(Investigate & Subject to Will be discussed at March transport use
funding being available) consultations. and zero-emissions
vehicles
g.*Electrify Noosa River June, 2025 Gillian Carter/ Carina
project proposal Not progressing at this stage Anderson Theme 7: Resilient &
(Investigate & Subject to as volunteers had to withdraw adaptive communities &
funding being available) due to heavy work built environments
commitments. 7.1 Create a resilient built
h.*ZEN certification June 2025 Gillian Carter environment for
concept (Investigate & Not progressing at this stage householders, businesses,
subject to funding) Liaise as volunteers had to withdraw vulnerable people, property
39
Page 40
with Anthony Wynne due to heavy work & infrastructure
Holcher re Plastic Free commitments.
Noosa @ Tourism Noosa & 7.2 Build community
Jordan Vance in Ec. Dev. @ awareness & preparedness
Council for climate
change & extreme weather
events
Infrastructure
accelerates industry
development and Smart
Precincts
Enhancing our natural
assets with technology
driving value
2. Encourage walking a. See 1b above 30 June, 2025 (Subject to Jenny Clement, Darren Theme 4: Sustainable
and funding) & then ongoing. Walters, Carina Anderson Transport
cycling initiatives In progress. 4.1 & 4.2 as above.
Theme 7: Resilient &
adaptive communities
&
built environments
7.1 as above
b.*Shade trees to promote Dec. 2024 Carina Anderson Theme 5: Healthy &
active transport Progressing as part of resilient natural systems
(Investigate & Subject to Transport Advocacy. & carbon drawdown
funding being available) 5.1 Increase revegetation,
restoration & urban
greening, reduce urban
heating
Infrastructure
accelerates industry
development and Smart
Precincts
Enhancing our natural
40
Page 41
assets with technology
driving value
3. Promote carbon a. See in no. 1a above As above
capture
technologies and
initiatives to offset car b. Tree planting X2 yearly with Tourism Anne Kennedy Theme 6: Sustainable
travel Trees for Tourism & Noosa/Noosa Landcare. agriculture and food
Landcare tree plantings 1 Trees for Tourism in 2024. systems
In progress. 1 planned on 02 6.3 Support agri-
April. businesses & landholders
to:
a. Take up
opportunities for
income generation
through carbon
drawdown
c. Landcare tree data for Dec. 2024 Carina Anderson Theme 5: Healthy &
promotion (Investigate) Not progressing at this stage resilient natural systems
as volunteers had to withdraw & carbon drawdown
due to heavy work 5.1 as above.
commitments.
4. Review Noosa a. Transport Advocacy To be reviewed Dec. 2024. Vivien Griffin/Jenny Theme 4: Sustainable
Council’s (incl. Noosa Council's Progress as per 1 e above. Clement Transport
Transport Strategy and transport plan, Kinetic As above
make recommendations contract & People Movers);
Smaller electric buses, more Infrastructure
electric public transport; accelerates industry
more active and public development and Smart
transportation Precincts
routes (Investigate)
Enhancing our natural
assets with technology
driving value
5. EV & Electrify a.2025 EV & Electrify By Sept. 2024. Expo Working group incl. Theme 4: Sustainable
Everything Expo. Everything Expo In Progress. Only one ZEN Inc. Program/Project Transport
ZENTAG Reps. to be part of volunteer available as other Manager, plus Paul Lewis. As above
Expo Working group volunteers have stepped away
due to work commitments. Enhancing our natural
41
Page 42
assets with technology
driving value
OBJECTIVE 1.3 Increased community awareness of initiatives to reduce emissions
1. Greater direct a. See 1a above As for 1a above As for 1a above All themes previously
engagement mentioned above
initiatives with the Noosa
Shire community
EV & Electrify Everything
b. See 1b above
c. See 1c above As for 1c above As for 1c above
d. See 1 d above As for 1d above As for 1d above
e. See no. 1f above As for 1e above As for 1e above
f. See no. 1g above As for 1g above As for 1g above
a.2025 EV & Electrify As for 5a above As for 5a above
Everything Expo see 5a.
above
2. Develop online See ZEN E Working Group By 30 June, 2024. Mark Purcell - See Rewiring
toolkits to Rewiring Noosa - “Electrify Completed. Noosa - “Electrify
facilitate emissions Everything” Toolkit that Everything” Toolkit
reduction includes EV’s
3. Effectively a.Work with Comms. & Ongoing so all project Chair ZEN E & Chair C&A
disseminate Advocacy Committee promoted at least x2 per year & Chair ZENTAG
information through ZEN using the Comms. & Ongoing
Inc’s website and other Advocacy Plan to promote
all ZEN E projects using:
communication channels
i. Print media
42
Page 43
ii. Social Media
iii. Website
iv. Newsletter
C. Noosa Council’s Corporate Plan themes & Associated Plans relevant to the ZENTAG Working Group Action Plan
Corporate Plan theme Relevant Associated Plans to ZENTAG Action Plan
6. Environment Noosa Environment Strategy 2019
Climate Change Response Plan
Noosa Transport Strategy 2017 - 2027 - development of a new movement and connectivity strategy.
7. Liveability Noosa Transport Strategy 2017 - 2027 - development of a new movement and connectivity strategy
- Cycling and Walking Strategy and Implementation Plan 2020
- Noosa Trails Masterplan and Implementation Plan 2020.
Noosa Social Strategy and Social Justice Charter – new Community Strategy.
- Noosa Health and Wellbeing Plan 2019 -2024.
8. Prosperity Economic Development Strategy 2021 – Smart Biosphere
New Waste Strategy
9. Future Community Strategy – New Community Strategy.
Climate Change Response Plan
Disaster Management Plan
Local Disaster Recovery Plan
Destination Management Plan
Economic Development Strategy
Urban Greening Project
10. Excellence Community Engagement Framework
D. Noosa Council Climate Change Response Plan (CCRP) Themes Relevant to the ZENTAG Working Group Action Plan
Theme 2: Energy efficiency and renewable energy
1.1 ….100% renewable energy incl. low income & vulnerable residents, businesses, incl. strata tenants
1.11 ….Develop a climate aware and empowered community for reducing climate risks & emissions
1.12 Develop a climate aware and empowered community for reducing climate risks & emissions
1.13 Develop a climate aware and empowered community for reducing climate risks & emissions
1.14 Develop a climate aware and empowered community for reducing climate risks & emissions
43
Page 44
1.15 Develop a climate aware and empowered community for reducing climate risks & emissions
1.16 Develop a climate aware and empowered community for reducing climate risks & emissions
1.17 Develop a climate aware and empowered community for reducing climate risks & emissions
1.18 Develop a climate aware and empowered community for reducing climate risks & emissions
1.19 Develop a climate aware and empowered community for reducing climate risks & emissions
Theme 3: Clean low emissions industries
3.1 …..shift to clean, green low emission industries & technology
3.2 ….. Facilitate emissions reduction & environmental sustainability for local businesses
Theme 4: Sustainable Transport
4.1 Accelerate public & active transport infrastructure investment & community usage through the implementation of Council’s Transport Strategy and
Walking and Cycling Plan.
4.2 Transition Council & community to sustainable transport use and zero-emissions vehicles
Theme 6: Sustainable agriculture and food systems
6.3 Support agri-businesses & landholders to:
c. Reduce their emissions technology implementation
d. Take up opportunities for income generation through carbon drawdown
Theme 7: Resilient & adaptive communities &
built environments
7.1 Create a resilient built environment for householders, businesses, vulnerable people, property & infrastructure
7.2 Build community awareness & preparedness for climate change & extreme weather events
a. Take up opportunities for income generation through carbon drawdown
C. Noosa Council Economic Development Strategy 2021-2030: Outcomes & Benefits relevant to the ZEN E Working Group Action Plan
1. Infrastructure accelerates industry development and Smart Precincts
2. Enhancing our natural assets with technology driving value
44
Page 45
45
Page 46
Appendix E - 2025 EV & Electrify Everything Work-plan
Task Allocation DRAFT v1 (Oct. 2024)
Start
Objective / Tasks Allocated to Status Deadline Notes/Comments
date
2024 EV EXPO REVIEW, EVALUATION
RECOMMENDATIONS
ZEN - shared /
Compilation, analyse and report on Survey data Completed
tbc
Review and summarise debrief meetings with NSC, ZEN - shared /
Completed
NJA & other key stakeholders tbc
Prepare report for Council & Board ZEN Chair Completed
BOARD CONSULTATION
Prepare and present final Expo report to Board ZEN Chair Completed
Board agreed to go ahead with 2025 EV &
Consider and decide on report recommendations ZEN Board Completed
Electrify Expo
ZEN - shared /
Oversee completion of Board-approved changes Completed
tbc
THANK YOU & FOLLOW UP TO PATRONS,
PARTNERS, SPONSORS, & EXHIBITORS
E Mails, photos, video link & survey results sent to
above, plus a report on how we sgowcaysed them in ZEN Assist Completed Meghan
markiting & media
NOOSA SHIRE COUNCIL (NSC) - TEMPORARY
EVENT PERMIT (TEP)
Meet with NSC staff to determine preliminaries (event NSC = Renee Black & Julie Duncan &
date, MOU, letter of support, cash and in-kind In Anne Nolan
ZEN Chair
support, communications, temporary event permit Progress ZEN = Anne Kennedy, Tony Clark &
(TEP) application process & documents) Thorsten Kels
ZEN Event Co-
Lodge preliminary TEP application (to secure date) Completed
ord.
46
Page 47
Complete all tasks related to the finalisation of the
Event To be
TEP application (inc. attach EMP, TMP, site plans,
Manager done
permits etc)
Act as the primary contact with Council on all Event To be
matters related to the TEP Manager done
Prepare a post-event report with recommendations to Event To be
ZEN related to the TEP Manager done
SITE PLAN
Event
review number and size options for sites.
Manager & To be
Review previous and confirm new event Site Plan Confirm access Zones, with input from
ZEN Event Co- done
ZEN Inc. Chair
ord.
Event
Visit site and identify all access areas, infrastructure, Manager & To be
site/zone locations, car parks, public toilets, power ZEN Event Co- done
ord.
Update CAD site plan map as needed to reflect Event To be
? NSC updates site plan $95/hr.
approved changes Manager done
Allocate exhibitors and expo infrastructure (stage,
Event To be
barriers, toilets, bins, water filling station etc) to site May
Manager done
plan
Event To be
Infrastructure planning i.e toilets, barriers
Manager done
Noosa To be
Encourage cafés & dining businesses to stay open
Junction Ass done
ZEN Chair &
To be
Confirm continuation Trial Ride zone ZEN Event Co-
done
ord.
Event To be
Book site infrastructure as per below
Manager done
TRAFFIC MANAGEMENT PLAN (TMP)
Review previous TMP and any recommendations, Event To be
amend (if needed) and confirm TMP with contractor, Manager done
47
Page 48
send to ZEN
Adopt finalised TMP. Respond to TMP inquiries, Event To be
oversee delivery with TMP contractor Manager done
Report on TMP post-event & make recommendations Event To be
if needed Manager done
ZEN Event Co- To be
ZEN Inc. sign off on final TMP
ord. done
EVENT MANAGEMENT PLAN (EMP)
Event
Review existing EMP, adopt Board-approved Manager & To be
changes. Finalise EMP and circulate to stakeholders ZEN Event Co- done
ord.
Notify Translink event inc. re-routing, change bus Event To be
stops,. Confirm approval. Manager done
Event To be
Adopt ZEN Waste Management Plan
Manager done
Event To be
Adopt ZEN Noise Management Plan
Manager done
Event
Adopt ZEN Sustainability Plan Completed
Manager
Event
Prepare Site Evacuation plan and issue to relevant Manager & To be scenarios, assembly points, incident
participants / stakeholders ZEN Event Co- done control,
ord.
Review and issue run-sheet/s (lead up, delivery and Event To be
wind down of the event.) Manager done
EMERGENCY SERVICES
Notify Police, oversee issuing of road closure permit. Event To be Contact SC Michael Phelan. Meet with all
Circulate permit to relevant event stakeholders. Manager done parties early February.
Notify QAS of event. Attend to any issued conditions Event To be
/ requests. Manager done
Notify QFES of event. Attend to any issued Event To be
conditions / requests. Manager done
48
Page 49
RISK MANAGEMENT PLAN - (RMP)
Event
Review, recommend changes, amend, adopt and Manager & To be
revise RMP ZEN Event Co- done
ord
Distribute, present, Implement RMP to relevant Event To be
stakeholders Manager done
Adopt Event Sustainability Plan into event planning Event To be
decisions Manager done
Confirm current insurance policies are in place for Event To be
the event (Pub&Prod, PersonAcc, Assoc'n) Manager done
Keep record of Trial Ride exhibitors' insurance CoC Event To be
exhibitor database includes "CoC"
which notes ZEN and NSC as interested parties Manager done
VOLUNTEERS
Event
Manager & To be
Determine and monitor required Volunteer Roles
ZEN Event Co- done
ord.
ZEN Event Co-ord. & Expo Assist. For
ZEN Event Co- To be
Develop and undertake volunteer recruitment plan past volunteers, ZEN membership,
ord. done
GoVolunteer, FB,
Maintain Volunteer database (availability, role To be
ZEN Assist ZEN Event Co-ord. & Expo Assist.
interest, ZEN inc. T Shirts), done
To be
Develop and maintain Volunteer Roster ZEN Assist
done
Assess Volunteer Uniform ZEN inc. T Shirts and To be
ZEN Assist
source done
Volunteer Booklet, roles identified and described, Event To be
With ZEN Inc. Assist.
maps, rosters Manager done
Communicate with Volunteers to ensure they are well Event To be
With ZEN Inc. Assist.
informed and engaged Manager done
Create and distribute Volunteer Information Event To be
With ZEN Inc. Assist.
document Manager done
49
Page 50
Event To be
Conduct Volunteer Induction & Information session With ZEN Inc. Assist.
Manager done
Event To be
Establish and manage volunteer hub (check-in/out) marquee or vacant shop provided by NJA
Manager done
To be
Record volunteers hours ZEN Assist
done
To be
Provide report on Volunteers ZEN Assist With ZEN Inc. Assist.
done
To be
Provide volunteers thank-you function ZEN - shared
done
EVENT MANAGER
ZEN - shared / In
Seek and secure Event Manager ZEN Expo Working Group
tbc Progress
Event
Manager & To be
Finalise Contract Event Manager ZEN Expo Working Group
ZEN Event Co- done
ord.
POLICY
ZEN Chair &
To be ZEN Inc. Expo Coordinator prepare for
Adopt Event Accessibility and Inclusion Plan ZEN Event Co-
done Dec. Board meeting
ord.
NOOSA JUNCTION ASSOC. (NJA)
ZEN Chair &
Meet with NJA and confirm commitment to upcoming To be
ZEN Event Co-
event, finalise MOU done
ord.
Revise and circulate event notification to local Noosa To be
Judi Lalor @NJA
businesses Junction Ass done
Liaison with and confirm NJA in-kind sponsors, Noosa To be
notify ZEN of secured sponsors Junction Ass done
50
Page 51
Add NJA sourced sponsors to sponsors and ZEN Event Co- To be Liaise with Anne & Colin as Sponsor
exhibitors list. ord done Coordinators
Encourage local Cafés & Restaurants to stay open Noosa To be
and expect good business Junction Ass done
SITE INFRASTRUCTURE
ZEN Chair &
To be
Confirm need for stage. ZEN Event Co-
done
ord.
ZEN Event Co- To be
Seek quotes & Book stage (if agreed))
ord. done
Event To be
Seek quotes & Book Bins x 7 @ Only if cannot be provided by NJA
Manager done
Event To be
Seek quotes & Book Toilets x 5 @
Manager done
Seek quotes & Book Chairs stage TBC if have Event To be 200 Only of have a stage or 12 if just have
Speakers Stage Manager done opening ceremony on small platform
To be
Seek quotes & Book First-aid services ZEN Assist
done
Event To be
Seek quotes & Power Supply V2L used from Evs
Manager done
Seek quotes & Book exhibitor-requested marquees if Event
needed, paid at exhibitors expense & added to Manager & To be for exhibitors travelling from afar, or
exhibitor fees, (not paid by ZEN Inc.who then had to ZEN Event Co- done Sponsors
seek reimbursement as in 2023) ord.
Event
Seek quotes & Book other infrastructure as identified Manager & To be
and approved ZEN Event Co- done
ord.
ZEN Event Co- To be
Book Unitywater bottle filling van on-line booking open 1-Jan-24.
ord. done
Event
Confirm event signage requirements, seek quotes, To be
Manager & Some 2024 signage that can be reused
oversee delivery, erect signs done
ZEN Event Co-
51
Page 52
ord.
as per TMP, install 2 wks prior . (add Expo
Book VMS board, oversee delivery & and collection, To be Info. as community info. for as well as
Council
displayed text, done road closure details) ZEN inc. Coordinator
to check Expo is mentioned.
EXHIBITOR MANAGEMENT
ZEN Event Co- To be In consultation with ZEN E Working Group
Identify new prospective exhibitors (esp Electrify)
ord done Leader & ZEN Inc. Chair
ZEN Chair &
Review and Confirm Exhibitor Pricing Schedule To be
ZEN Event Co-
@ZEN done
ord.
Event
Manager & To be include option for accommodation and
Update, finalise Exhibitor Invitation package
ZEN Event Co- done shade tent
ord.
To be
Invite Exhibitors ZEN Assist
done
Maintain exhibitor database (prospects, confirmed, To be
ZEN - shared Anne, Colin Lambie & ZEN Inc. Treasurer
invoice request, @ZEN done
To be
Prepare invoices for confirmed exhibitors ZEN Treasurer invoices issued with exhibitor agreement
done
Review, amend, confirm and distribute Exhibitor On- Event To be
Bump In & Out etc
Day Logistics Information Manager done
Obtain Trial Rides Exhibitors Cert. of Currency with Event To be
ZEN and NSC noted as interested parties Manager done
Event
Manager & To be With input from ZEN Event Coordin. &
Create Exhibitor location plan / site plan
ZEN Event Co- done ZEN Inc. Chair who is sponsor liasion
ord.
Event To be
Act as contact point for exhibitors re event logistics
Manager done
To be
Exhibitor listing (on line, newsletters, socials) ZEN - shared
done
Notify ZEN of Exhibitor Invoice Requests @ZEN ZEN - shared To be
52
Page 53
done
VIP INVITES & OPENING SPEAKERS, OPENING
CERMENONY
ZEN Chair &
To be
Seek Welcome to Country representative ZEN Event Co- Lyndon Davis
done
ord.
ZEN Chair &
To be
Review VIP Invite List ZEN Event Co-
done
ord.
To be
Invitee Update @ZEN ZEN Chair
done
EVENT SURVEY
include number of night stays,
Identify key survey data topics and target survey ZEN Event Co- To be
stakeholder related data, tourism, spends,
groups to be analysed. ord done
purchase etc
Create event survey/s, and method of collecting
To be ?Google forms or similar. Ease of use by
survey (paper, QR code, volunteers, on-line form and ZEN - shared
done vols. ? Random prizes.
device collection) @ZEN vols
Conduct survey/s to target groups at optimal time for To be
ZEN - shared
each group @ done
ZEN - shared / To be
Maintain database of responses @ZEN
tbc done
ZEN Event Co- To be
Provide a report of key survey findings @ZEN
ord done
DATA MANAGEMENT
Ownership by ZEN, with provide set access rights to To be
ZEN - shared
EvMgr done
SPONSORSHIP
53
Page 54
ZEN Chair &
To be ask NJA and TN for feedback on
Review Sponsorship Proposal package ZEN Event Co-
done prospectus
ord.
ZEN Chair &
Identify/develop prospective sponsors (EV industry To be
ZEN Event Co- Anne & Colin
and "electrify" industry). Update database done
ord.
Make contact with potential sponsor, Send To be
ZEN Chair Anne & Colin
prospectus as requested. Follow up.Update database done
Event To be
Issue agreements
Manager done
ZEN - shared / To be
Invoices to secure sponsors
tbc done
To be
Prepare sponsor invoices ZEN Treasurer invoice sent with sponsor agreement
done
Event
Manager & To be
Prioritise Sponsor preferred Site Allocations Input from Anne also
ZEN Event Co- done
ord.
To be
Ensure In-kind Sponsorships deliverables are met ZEN - shared Anne & Colin
done
ZEN - shared / To be
Update secured sponsors onto Exhibitor database
tbc done
MAIN STAGE (if agreed))
ZEN Event Co- To be
Infrastructure quotes
ord. done
ZEN Event Co- To be
Stage TBC
ord. done
Event
Marquee ?????? Not sure why this is in here????
Manager
Event To be Or was this done by ZEN Expo Co-
AV equipment
Manager done ordinator?
In past speakers program has been done
ZEN - shared /
Speakers TBC/MC On Hold by a ZEN Inc. volunteer. Is not
tbc
recommended for 2025 Expo.
54
Page 55
Event
Manager & To be
Signage Done jointly as it is sponsor signage.
ZEN Event Co- done
ord.
Event
In past speakers program has been done
Manager &
Program Development On Hold by a ZEN Inc. volunteer. Is not
ZEN Event Co-
recommended for 2025 Expo.
ord.
MARKETING / BRANDING /
ZEN Chair &
Update event logos and livery on logos, graphics, To be
ZEN Event Co- add "Electrify", update 2024 date
letterhead, website, newspaper advert copy etc done
ord.
Develop a marketing strategy / plan that identifies ZEN - shared / To be
target demographics, promotion plan, etc tbc done
PROMOTION
ZEN - shared / To be
Newsletter Process
tbc done
ZEN - shared / To be
JAN EDM
tbc done
ZEN - shared / To be
FEB EDM
tbc done
ZEN - shared / To be
MARCH EDM
tbc done
ZEN - shared / To be
APRIL EDM
tbc done
ZEN - shared / To be
MAY EDM
tbc done
ZEN - shared / To be
JUNE EDM
tbc done
SOCIAL MEDIA
ZEN - shared / To be
Facebook posts
tbc done
55
Page 56
ZEN - shared / To be
Instagram posts
tbc done
WEBSITE
ZEN - shared / To be
Website updated with dates and links @ZEN
tbc done
ZEN - shared / To be
Website updated with exhibitors
tbc done
ZEN - shared / To be
Website updated with sponsors
tbc done
ZEN - shared / To be
Website updated with program
tbc done
ZEN - shared / To be
Website updated with Event time
tbc done
ZEN - shared / To be
Website updated with registration
tbc done
Website updated with sustainability and disability ZEN - shared / To be
section tbc done
ZEN - shared / To be
Event Logo updated
tbc done
ADVERTISING
ZEN Chair &
To be
Identify newspaper ZEN Event Co-
done
ord.
Event To be
Seek quotes, submit to ZEN Event Co-ord. Done by ZEN Expo Co-ordinator?
Manager done
ZEN Chair &
To be
Approve quotes and advert schedule ZEN Event Co-
done
ord.
Book adverts and supply copy as per agreed Event To be
Done by ZEN Expo Co-ordinator?
schedule Manager done
Event To be
Sunny Coast Times Done by ZEN Expo Co-ordinator?
Manager done
Advertisements Noosa Today Event To be Done by ZEN Expo Co-ordinator?
56
Page 57
Manager done
Event To be
IN Noosa - maybe not Not in 2025
Manager done
Event To be
Your local lifestyle: Noosa Hinterland Done by ZEN Expo Co-ordinator?
Manager done
Event To be
Eumundi Voice Done by ZEN Expo Co-ordinator?
Manager done
Event To be
Coolum Advertiser Done by ZEN Expo Co-ordinator?
Manager done
Event To be
Sunshine Coast Daily Done by ZEN Expo Co-ordinator?
Manager done
ZEN - shared / To be
Noosa Today advertising feature Done by ZEN Expo Co-ordinator?
tbc done
ZEN Social To be
Facebook paid boosts
Media done
GRANTS
ZEN Chair &
To be
Identify and apply for suitable grants ZEN Event Co-
done
ord.
ZEN Event Co- To be
Ensure to grant deliverables are fully met
ord. done
ZEN Event Co- To be
Report on and Acquit grants
ord. done
BUDGET & FINANCIALS
ZEN Chair &
To be
Set and monitor event budget ZEN Event Co-
done
ord.
ZEN Chair &
Seek quotes related to the Event Manager tasks and To be
ZEN Event Co-
submit for approval done
ord.
Attend to financial transactions, invoice generation, To be
ZEN Treasurer
A/R, A/P, P&L, cash flow, financial reports done
57
Page 58
ENTERTAINMENT
Event
Manager & To be
Confirm buskers and entertainers
ZEN Event Co- done
ord.
Event To be
Book and manage buskers on-site logistics
Manager done
COMMUNICATIONS & DATA
Communicate with stakeholders e.g. Translink, Event To be
Police, Ambulance, etc Manager done
Maintain on-line data sharing & access rights of key ZEN - shared /
Event Manager to be provide access rights
event documents, database, graphics, photos tbc
Set and maintain databases to help manage ZEN - shared / To be
volunteers, exhibitors, sponsors, surveys, etc. tbc done
Communicate as required to stakeholders, sponsors, Event To be
exhibitors, volunteers to ensure delivery of the event Manager done
ZEN Chair &
To be
Communicate with media. ZEN Event Co-
done
ord.
Event
Maintain timely communications on all matters Manager & To be
related to the successful delivery of the event ZEN Event Co- done
ord.
Opening event or media launch TBC
58
Page 59
Appendix F
Use of Alliance Partnership Funds from Council for 2024
The revised Administrator/Coordinator role for Jan. 01, 2024 to Nov. 30, 2024 was Admin. for
21 hours per week and Communications for 3 hours per week for a total of $ 55,018.67 made up of
$50,577.76 wages & on costs & ($44,584.01 Gross pay + Superannuation $4,972.37. Workcover $1,021.38)
and $4440.62 Operating Expenses. The budgeted amount was $50,000 per annum for Admin. & some Comms.
component. However, as the same person did both roles, and that person did not start
until late Oct., 2023, the amount paid has all come out of the admin. part of the funding.
The Communications Package $15,000 - while $15,000 was budgeted out of the Alliance funds for marketing
advice for ZEN Inc. overall $7,958.07 was used for marketing advice for the EV Expo due to the issues outlined
in section 6 above. $4440.62 was used for communications related operating expenses as outlined in the
admin. package and the admin. overrun of $577.76 was also covered from this Comms. Package. Therefore
there is a balance of $6,464.17 from the 2023-2024 Alliance Partnership Communications Package remaining
to put towards this work in 2025.
1. Administration & Communications Package $50,000
A. Administration (80 hours per month)
Activity or Event Date/Time Amount of Impact/Outcome
Time Per
Month
1. Board and 35 hours per Strengthen ZEN Inc’s
Working Group month internal Operations so
a. Attend Board & volunteers can
Working group concentrate on projects
meetings Sec. resigned and unable
b. Working group to be replaced so this
notes task went to this position
c. Board meeting
minutes &
follow
up/actions
2. Membership 5 hours per Building
a. Keeping month membership/volunteer
membership base to assist with
records project work/education
b. Contact with /advocacy
members
3. Operations 10 hours per Strengthen ZEN Inc’s
a. Governance & month internal Operations so
Operations volunteers can
Manual concentrate on projects
b. Updating
Shared Drives &
E files
59
Page 60
4. General Admin. 25 hours per Strengthen ZEN Inc’s
& Following Up month internal Operations so
Queries volunteers can
concentrate on projects
5. Governance Strengthen ZEN Inc’s
a. AGM 5 hours per internal Operations so
Preparation month volunteers can
concentrate on projects
B. Communications Total = 3 hours per week or 12 hours per month
Activity or Event Date/Time/Location Amount of Impact/Outcome
Time Per
Month
1. Newsletter Developing & 4 hours per Public education & Advocacy
Coordinating content month
2. Coordinating Writing them and 6 hours per Public education & Advocacy
Noosa Today coordaining others month
articles or writing them
media releases
3. Website Minor updates to ZEN 2 hours
updates Inc. & Expo websites
Total $50,000
2. Communications Package $15,000
Task Action $ Amount
Upgrade & Update Update outdated Info. $3,000
website to be more Review & Re organise information
user friendly for ease of access
Did not occur in 2024 Add project info. & regular updates -
Expand Partner’s page
Videos Commercially produced Major $2,500
Were done from Project videos
project budgets • Community Batteries
Telling ZEN Inc’s story Strengthening ZEN Inc’s $1,800
Outreach by communication through:
monitoring for 1. Newsletter Production &
trolls/provocative Media Releases
posts– currently only 2. Professionally written
posting, no social media presence
monitoring possible
with volunteers.
Marketing ZEN inc. & Marketing advice and developing $7,700 (up to)
EV Expo and implementing a marketing plan
Only done to a very
limited extent.
$15,000
60
Page 61
Appendix G
Additional Funding Components - Itemised budget for Council Alliance Partnership
Funding for 2025-2026
1. ZEN Inc. Program/Project Manager Role $49,400 for 2025 - 2026
Tasks currently done by Move to ZEN Inc. Frees ZEN Inc. Board
ZEN Inc. Chair /Board Program/Project Manager members up to do
members
Additional Finances & funding
Some sponsorship & Full sponsorship & Work on diversifying ZEN
coordination of the EV & coordination of the EV & Inc. Income sources
Electrify Expo Electrify Expo
Some Financial monitoring Full Financial monitoring of Expand sponsorship and
of projects, including project projects, including project donations so EV Expo is
budgeting & grant budgeting & grant self- sustaining by 2025.
coordination coordination Council MOU expires 2024.
Additional Program/Project Coordination
Assist project leaders with Assist all project leaders Revisit & revise MOU’s with
monitoring, coordination and with monitoring, partners & develop
implementation coordination and collaborative projects
implementation
Project Admin. and reporting Project Admin. and reporting Work on strategic direction
e.g. including project e.g. including project of organisation & projects
budgeting budgeting (that are at cutting edge of
renewable energy/E
transport development)
$49,400
Additional Admin./Secretariat Role - Internal relations – Building a stronger
organisation
Admin. for Recruitment of Admin. for recruitment of Building relationships with
new Board members new Board members Board & ZEN Inc. members
annually, including annually Find linkages between
organising short listing, members skill sets for better
interviewing & reference AGM preparation project leverage
checks & AGM preparation
Annual report Input, formatting & photo
layout of Annual report Strengthen ZEN Inc.
Membership internally
Operations Manual Operations Manual
$5,200
Additional to Marketing & Comms. Role - External relations (Education & Advocacy)
Implement our strategic Developing strategic
marketing plan for the relationships
organisation as a whole,
(not just for the Expo) by More extensive networking
engaging a professional & relationship building
marketing person for
additional hours per month More time on advocacy of
to help us better engage strategic issues
61
Page 62
with our audience and get
them to ACT!.
$12,000
Total Additional “Ask” Amount $66,400
Anne Kennedy, Colin Lambie & Mark Purcell
Feb., 2024
62
Page 63
P&L For Jan. – Dec., 2024 Appendix H
Profit and Loss
Zero Emissions Noosa Inc
For the year ended 31 December
2024
Cash Basis
Account 2024
Trading Income
Donations 7,361.10
Exhibitor Fees 8,086.36
Grant Funding 225,100.00
Interest Income 2,039.28
Member Fees 1,789.14
Sponsorship 45,000.00
Total Trading Income 289,375.88
Cost of Sales
Grant Associated Expenses 94,507.02
Total Cost of Sales 94,507.02
Gross Profit 194,868.86
Operating Expenses
Advertising 50.00
Bank Fees 18.56
Consulting & Accounting 3,585.68
General Expenses 23.45
Membership Fees 162.50
Office Expenses 325.00
Subscriptions 696.06
Superannuation 5,404.75
Wages and Salaries 50,600.40
Workcover 657.29
Total Operating Expenses 61,523.69
Net Profit 133,345.17
63
Page 64
Appendix I
Profit and Loss by Project
Zero Emissions Noosa Inc
For the 3 years ended 31 December 2024
Cash Basis
Noosaville QLD Gov -
Alliance Alliance Energy
EV Expo Battery Community
Account Agreement Agreement Eff Total
2025 Project - Battery
1 2 Assess
YEF Project
Trading Income
Grant Funding 65,000.00 125,000.00 29,000.00 10,000.00 10,000.00 48,831.38 287,831.38
Total Trading Income 65,000.00 125,000.00 29,000.00 10,000.00 10,000.00 48,831.38 287,831.38
Cost of Sales
Grant Associated
9,066.27 686.80 0.00 2,208.55 10,000.00 43,362.72 65,324.34
Expenses
Total Cost of Sales 9,066.27 686.80 0.00 2,208.55 10,000.00 43,362.72 65,324.34
Gross Profit 55,933.73 124,313.20 29,000.00 7,791.45 0.00 5,468.66 222,507.04
Operating Expenses
Advertising 0.00 45.45 0.00 0.00 0.00 0.00 45.45
Bank Fees 18.55 0.01 0.00 0.00 0.00 0.00 18.56
Consulting & Accounting 2,745.68 840.00 0.00 0.00 0.00 0.00 3,585.68
Credit card surcharge
1.69 0.00 0.00 0.00 0.00 0.00 1.69
fees
General Expenses 335.45 0.00 0.00 0.00 0.00 0.00 335.45
Membership Fees 50.00 0.00 0.00 0.00 0.00 0.00 50.00
Office Expenses 431.02 0.00 0.00 0.00 0.00 0.00 431.02
Recruitment 925.00 0.00 0.00 0.00 0.00 0.00 925.00
Subscriptions 279.78 582.42 0.00 0.00 0.00 0.00 862.20
Superannuation 4,972.37 1,073.76 0.00 0.00 0.00 0.00 6,046.13
Wages and Salaries 44,584.01 11,847.13 0.00 0.00 0.00 2,039.65 58,470.79
Website 568.80 0.00 0.00 0.00 0.00 0.00 568.80
64
Page 65
Workcover 1,021.38 0.00 0.00 0.00 0.00 0.00 1,021.38
Total Operating
55,933.73 14,388.77 0.00 0.00 0.00 2,039.65 72,362.15
Expenses
Net Profit (0.00) 109,924.43 29,000.00 7,791.45 0.00 3,429.01 150,144.89
65
Workcover 1,021.38 0.00 0.00 0.00 0.00 0.00 1,021.38 Total Operating Expenses 55,933.73 14,388.77 0.00 0.00 0.00 2,039.65 72,362.15 65Page 66
Balance Sheet Appendix J
Balance Sheet
Zero Emissions Noosa Inc
As at 31 December 2024
Cash Basis
Account 31 Dec 2024
Assets
Bank
Business Account 241,858.52
Debit Card Account 410.09
Public Fund Account 2,306.41
Total Bank 244,575.02
Total Assets 244,575.02
Liabilities
Current Liabilities
GST 14,219.62
PAYG Withholdings
1,852.00
Payable
Rounding 0.10
Superannuation Payable (585.52)
Suspense (2,290.47)
Total Current Liabilities 13,195.73
Total
13,195.73
Liabilities
Net Assets 231,379.29
Equity
Current Year Earnings 133,345.17
Retained Earnings 98,034.12
Total Equity 231,379.29
66
Page 67
Appendix K
Association Report
Zero Emissions Noosa Inc
For the year ended 31 December 2024
67
Appendix K Association Report Zero Emissions Noosa Inc For the year ended 31 December 2024 67Page 68
Contents 3 Committee's Report 4 Income and Expenditure Statement 5 Assets and Liabilities Statement 6 Notes to the Financial Statements 7 True and Fair Position 8 Auditor's Report Association Zero Emissions Noosa Page 2 of Report Inc 76
Page 69
Committee's Report
Zero Emissions Noosa Inc
For the year ended 31 December 2024
Committee's Report
Your committee members submit the financial report of Zero Emissions Noosa Inc for the financial
year ended 31 December 2024.
Operating Result
The surplus for the financial year amounted to: $84,891
Going Concern
This financial report has been prepared on a going concern basis which contemplates continuity of
normal business activities and the realisation of assets and settlement of liabilities in the ordinary
course of business. The ability of the association to continue to operate as a going concern is
dependent upon the ability of the association to generate sufficient cashflows from operations to
meet its liabilities. The members of the association believe that the going concern assumption is
appropriate.
Signed in accordance with a resolution of the Members of the Committee on:
(President)
Date 16 / 02 / 2025
(Treasurer
)
Date 14//2/20/25
Association Zero Emissions Noosa Page 3 of
Report Inc 76
Page 70
Income and Expenditure Statement
Zero Emissions Noosa Inc
For the year ended 31 December 2024
2024 2023
Income
Income
Interest Income 2,039 1,140
Grants 190,492 115,462
Donations 7,361 17,793
Exhibitor Fees 9,436 5,100
Membership 1,789 2,118
Sponsorship 45,000 34,091
Total Income 256,118 175,704
Total Income 256,118 175,704
Cost of Sales
Project/Grant Expenses
Projects Other 109,708 73,052
Total Project/Grant Expenses 109,708 73,052
Total Cost of Sales 109,708 73,052
Gross Surplus 146,410 102,652
Other Income
Other Revenue - 2,662
Total Other Income - 2,662
Expenditure
Audit Fees 500 500
Bank Fees 19 2
Consultant Fees 3,086 914
General Expenses 231 134
Insurance 657 -
Office Expenses 325 101
Superannuation 5,405 2,449
Wages and Salaries 50,600 23,147
Recruitment Expenses - 925
Website Expenses - 244
Subscriptions 696 166
Total Expenditure 61,519 28,582
Current Year Surplus/ (Deficit) 84,891 76,732
Association Zero Emissions Noosa Page 4 of
Report Inc 76
Page 71
Assets and Liabilities Statement
Zero Emissions Noosa Inc
As at 31 December 2024
NOTES 31 DEC 2024 31 DEC 2023
Assets
Current Assets
Cash at Bank 241,859 95,463
Public Fund Account 2,306 1,726
Direct Debit Account 410 -
Sundry Debtors 26,116 62,700
Total Current Assets 270,691 159,889
Total Assets 270,691 159,889
Liabilities
Current Liabilities
Sundry Creditors 16,721 -
GST Payable 13,554 1,500
GST on Creditors (1,520) -
GST on Debtors 2,374 5,700
PAYG Withholdings Payable 1,852 678
Employee Entitlements 1,451 641
Total Current Liabilities 34,431 8,519
Total Liabilities 34,431 8,519
Net Assets 236,260 151,369
Member's Funds
Capital Reserve 236,260 151,369
Total Member's Funds 236,260 151,369
Association Zero Emissions Noosa Page 5 of
Report Inc 76
Page 72
Notes to the Financial Statements
Zero Emissions Noosa Inc
For the year ended 31 December 2024
1. Summary of Significant Accounting Policies
The financial statements are special purpose financial statements prepared in order to satisfy the
financial reporting requirements of the Associations Incorporation Act QLD. The committee has
determined that the association is not a reporting entity.
The financial statements have been prepared on an accruals basis and are based on historic costs and
do not take into account changing money values or, except where stated specifically, current
valuations of non-current assets.
The following significant accounting policies, which are consistent with the previous period unless stated
otherwise, have been adopted in the preparation of these financial statements.
Cash on Hand
Cash on hand includes cash on hand, deposits held at call with banks, and other short-term highly
liquid investments with original maturities of three months or less.
Revenue and Other Income
Revenue is measured at the fair value of the consideration received or receivable after taking into
account any trade discounts and volume rebates allowed. For this purpose, deferred
consideration is not discounted to present values when recognising revenue.
Interest revenue is recognised using the effective interest method, which for floating rate financial
assets is the rate inherent in the instrument. Dividend revenue is recognised when the right to
receive a dividend has been established.
Grant and donation income is recognised when the entity obtains control over the funds, which is
generally at the time of receipt.
If conditions are attached to the grant that must be satisfied before the association is eligible to receive
the contribution, recognition of the grant as revenue will be deferred until those conditions are
satisfied.
All revenue is stated net of the amount of goods and services tax.
Goods and Services Tax (GST)
Revenues, expenses and assets are recognised net of the amount of GST, except where the amount of
GST incurred is not recoverable from the Australian Taxation Office (ATO). Receivables and
payables are stated inclusive of the amount of GST receivable or payable. The net amount of GST
recoverable from, or payable to, the ATO is included with other receivables or payables in the
assets and liabilities statement.
Association Zero Emissions Noosa Page 6 of
Report Inc 76
Page 73
True and Fair Position
Zero Emissions Noosa Inc
For the year ended 31 December 2024
Annual Statements Give True and Fair View of Financial Position and Performance of the
Association
We, Anne , and Colin , being members of the committee of Zero
Kennedy Emissions
Lambie
Noosa Inc, certify that –
The statements attached to this certificate give a true and fair view of the financial position and
performance of Zero Emissions Noosa Inc during and at the end of the financial year of the
association ending on 31 December 2024.
Signed:
Dated: 16//02//2025
Signed:
Dated:
/ / 14/02/2026
Association Zero Emissions Noosa Page 7 of
Report Inc 76
Page 74
Auditor's Report
Zero Emissions Noosa Inc
For the year ended 31 December 2024
Independent Auditors Report to the members of the Association
We have audited the accompanying financial report, being a special purpose financial report, of Zero
Emissions Noosa
Inc (the association), which comprises the committee’s report,the assets and liabilities statement as at
31 December 2024, the income and expenditure statement for the year then ended, cash flow
statement, notes comprising a summary of significant accounting policies and other explanatory
information, and the certification by members of the committee on the annual statements giving a
true and fair view of the financial position and performance of the association.
Committee’s Responsibility for the Financial Report
The committee of Zero Emissions Noosa Inc is responsible for the preparation and fair presentation of
the financial report, and has determined that the basis of preparation described in Note 1 is
appropriate to meet the requirements of the Associations Incorporation Act QLD and is
appropriate to meet the needs of the members. The committee’s responsibility also includes such
internal control as the committee determines is necessary to enable the preparation and fair
presentation of a financial report that is free from material misstatement, whether due to fraud or
error.
Auditor’s Responsibility
Our responsibility is to express an opinion on the financial report based on our audit. We have
conducted our audit in accordance with Australian Auditing Standards. Those standards require
that we comply with relevant ethical requirements relating to audit engagements and plan and
perform the audit to obtain reasonable assurance whether the financial report is free from material
misstatement.
An audit involves performing procedures to obtain audit evidence about the amounts and disclosures in
the financial report. The procedures selected depend on the auditor’s judgment, including the
assessment of the risks of material misstatement of the financial report, whether due to fraud or
error. In making those risk assessments, the auditor considers internal control relevant to the
association’s preparation and fair presentation of the financial report, in order to design audit
procedures that are appropriate in the circumstances, but not for the purpose of expressing an
opinion on the effectiveness of the association’s internal control. An audit also includes evaluating
the appropriateness of accounting policies used and the reasonableness of accounting estimates
made by the committee, as well as evaluating the overall presentation of the financial report.
We believe that the audit evidence we have obtained is sufficient and appropriate to provide a basis for
our audit opinion.
Opinion
In our opinion, the financial report presents fairly, in all material respects (or gives a true and fair view
–refer to the applicable state/territory Act), the financial position of Zero Emissions Noosa Inc as
at 31 December 2024 and (of) its financial performance for the year then ended in accordance
with the accounting policies described in Note 1 to the financial statements, and the requirements
of the Associations Incorporation Act QLD.
Basis of Accounting and Restriction on Distribution
Without modifying our opinion, we draw attention to Note 1 to the financial statements, which describes
the basis of accounting. The financial report has been prepared to assist Zero Emissions Noosa Inc
to meet the requirements of the Associations Incorporation Act QLD. As a result, the financial
report may not be suitable for another purpose.
Association Zero Emissions Noosa Page 8 of
Report Inc 76
Page 75
Auditor’s signature: Louise McNeich
Auditor’s address: PO Box 563, Cooroy Qld 4563
Dated: 14/ 02 /2025
Association Zero Emissions Noosa Page 9 of
Report Inc 76
Page 76
28