MCU13/0069 - Adopted Infrastructure Charge Notice 0584 - Rev 0

of 2

Page text shows just the words. Original shows the document exactly as it was published.

                                                                                 Locked Bag 72, Sunshine Coast Mail Centre, QLD 4560
                                                                                 Phone (07) 5475 7272         Fax (07) 5475 7277
                                                                                 ABN 37 876 973 913



                ADOPTED INFRASTRUCTURE CHARGE NOTICE
To:        Ogilvie Bacon Partnership
           C/- Martoo Consulting
           PO Box 1684                                                                      Date of Issue:   17 December 2013
           NOOSA HEADS         4567                                                         Adopted Charge Notice No: 584
                                                                                            Rev No: 0


 LAND TO WHICH THE INFRASTRUCTURE CHARGE APPLIES:
 Planning Scheme:                The Noosa Plan
 Property Description:           Lot 32 N 21854
 Property Address:               Park - Sps # Nh10 90 Noosa Pde NOOSA HEADS

 DEVELOPMENT TO WHICH THE ADOPTED INFRASTRUCTURE CHARGE APPLIES
 The adopted infrastructure charge applies to the following development type: Material Change of Use
 Development Approval/Compliance reference number: MCU13/0069

 AMOUNT OF THE ADOPTED INFRASTRUCTURE CHARGE
      The adopted infrastructure charge has been calculated in accordance with an adopted infrastructure charges resolution
       under the Sustainable Planning Act 2009.
  The amount of the adopted infrastructure charge is to be escalated in accordance with relevant legislation from the date on
       the notice to the date of payment.

  ADOPTED INFRASTRUCTURE CHARGE AMOUNT (@ Sep 2013 index) = $34,010.00

 APPORTIONMENT OF ADOPTED INFRASTRUCTURE CHARGE:

                              Allocation of adopted infrastructure charge to trunk infrastructure networks
      Entity
                                                                                           Charge          Offset / Rebate        Net Payable
                                                                                                                                (@ Sep 2013 Index)

                 Water Supply                                                                 $1,289.00               $0.00              $1,289.00
 Unitywater
                 Sewerage                                                                     $1,933.00               $0.00              $1,933.00
                 Transport                                                                   $24,648.00               $0.00            $24,648.00
                 Public Parks & Land for Community Facilities                                 $4,350.00               $0.00              $4,350.00
      Council
                 Stormwater (Residential)                                                         $0.00               $0.00                   $0.00
                 Stormwater (Non-Residential)                                                 $1,790.00               $0.00              $1,790.00
                                                                          TOTAL =
                                                                                             $34,010.00               $0.00            $34,010.00
                                (Subject to indexation applicable at date of payment)

 Basis of rebate:

 PAYMENT OF THE ADOPTED INFRASTRUCTURE CHARGE
      The adopted infrastructure charge is payable in accordance with the Sustainable Planning Act 2009.
      The due date for payment of the adopted infrastructure charge is: Before the Change of Use happens.
      The charge is to be paid to Sunshine Coast Regional Council via the Infrastructure Charges Officer, tel: (07) 5441 8679.
       Please contact Sunshine Coast Regional Council, Infrastructure Policy Branch, prior to making payment.
      Compound annual interest at 11% calculated daily is to be applied on an overdue charge.

 Notice is hereby given under the Sustainable Planning Act 2009 and the Local Government Act 2009 that the adopted infrastructure charge
 notice is levied by the Sunshine Coast Regional Council on the described land. The adopted infrastructure charge is DUE AND PAYABLE BY
 THE ABOVE DATE. The adopted infrastructure charge plus any arrears and interest may be recovered by legal process without further notice if
 unpaid after the expiration of the DUE DATE.

 SPECIAL NOTE:
                                                                                                                     st
 De-amalgamation of the Noosa area from the Sunshine Coast Regional Council will occur on 1
                                                                                        January 2014.
           st
 From 1 JANUARY 2014, all infrastructure charges applying to development under the planning scheme “The
 Noosa Plan” are to be PAID to the new Noosa Council at the Tewantin Office.
Log in to download the original file

MCU13_0069 - Adopted Infrastructure Charge Notice 0584 - Rev 0.pdf · 32 KB (small file)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

Full text of the other 1 page

Page 2

             ADOPTED INFRASTRUCTURE CHARGE NOTICE
                        IMPORTANT NOTICE

    1. PAYMENT
         This notice is due and payable by the due date shown. Cheques, money orders or postal
         notes should be made payable to Sunshine Coast Regional Council and crossed “Not
         Negotiable”. Change cannot be given on cheque payments. Property owners will be liable for
         any dishonour fees.
    2. ADOPTED INFRASTRUCTURE CHARGES TAKEN TO BE A RATE:
       An adopted infrastructure charge levied by a local government is, for the purposes of recovery,
       taken to be a rate within the meaning of the Local Government Act 1993. This means:
       a.   an adopted infrastructure charge may be recovered by court action for a debt;
       b.   an adopted infrastructure charge may be recovered from the person for the time being
            owning the relevant land, regardless of who was the owner or other person upon whom
            the charges was imposed;
       c.   Interest is payable on overdue payments; and
       d.   If charges are unpaid for 3 years, the land can be sold to recover the outstanding
            charges.
    3. INTEREST:
       Compound interest at the rate of 11% per annum calculated daily is payable on all
       infrastructure charges outstanding after the due date shown on this charges notice.
    4. OVERSEAS PAYEES:
       Please forward your infrastructure charges payment by way of a bank draft for the required
       amount in Australian dollars.
    5. GOODS AND SERVICES TAX:
       The federal government has determined that rates and utility charges levied by local
       government will be GST free. Accordingly, no GST is included in this infrastructure charges
       notice.
    6. ADOPTED INFASTRUCTURE CHARGE IS SUBJECT TO PRICE VARIATION:
       The amount of the adopted infrastructure charge is subject to escalation in accordance with
       relevant legislation from the date of the notice until the date the payment is made.
         PLEASE CONTACT THE INFRASTRUCTURE CHARGES OFFICER BEFORE MAKING
         PAYMENT FOR UPDATED CURRENT AMOUNT
    7. INFRASTRUCTURE CHARGES ENQUIRIES:
       Enquiries regarding this infrastructure charges notice should be directed to Council’s office,
       Phone (07) 5441 8679, during office hours or e-mail: [email protected] OF PAYMENT
PAYMENT BY MAIL                                 PAYMENT AT COUNCIL OFFICES                    PAYMENTS METHODS NOT ACCEPTED
Confirm the current applicable Infrastructure   Present this notice intact with an updated    Payments via credit card transactions will
Charge and mail immediately with your           payment advice notice to Sunshine Coast       not be accepted for payment of
payment to:                                     Regional    Council    Customer     Service   Infrastructure Charges.
Sunshine Coast Regional Council,                Counter.
Locked Bag 72,
Sunshine Coast Mail Centre QLD 4565.



SPECIAL NOTE:
                                                                                                            st
De-amalgamation of the Noosa area from the Sunshine Coast Regional Council will occur on 1
                                                                                       January 2014.
        st
From 1 JANUARY 2014, all infrastructure charges applying to development under the planning scheme “The
Noosa Plan” are to be PAID to the new Noosa Council at the Tewantin Office.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.