Delegated Report - Code - Planning OPW26 0079 (As Published)

of 8
               DEVELOPMENT ASSESSMENT DELEGATED REPORT

               Author                  Senior Development Engineer, Daniel Epps
                                       Development Assessment



                    APPLICATION DETAILS

                    Application No.                OPW26/0079

                    Applicant                      PermaBuild

                    Proposal                       Operational Works - Vehicle Crossover

                    Properly Made Date             12 June 2026

                    Information Request Date        Not Applicable

                    Information Response Date      Not Applicable

                    Decision Due Date              27 August 2026

                    Report Reviewed &              Will Lowe - 25 August 2026
                    Finalised By


                    PROPERTY DETAILS

                    Property Address               18 Shearwater St Peregian Beach Qld 4573

                    RP Description                 Lot 424 P 93116

                    Land Area                       546.0000 m²

                    Existing Use of Land           Residential


                    STATUTORY DETAILS

                    SEQRP Designation              Urban Footprint

                    Zone                           Low Density Residential

                    Precinct                       Not applicable

                    Local Plan Area                Coastal Communities

                    Overlays                       Land Subject Acid Sulphate Soils, Bushfire Hazard, Coastal
                                                   Protection, Landslide Hazard

                    Assessment Type                Code

               1.      PROPOSAL
               The application seeks approval for Operational Works - Vehicle Crossover.
               The locality and proposal plan are included below.



Document Set ID: 25060057
Version: 4, Version Date: 25/08/2026

Log in to download the original (Delegated Report - Code - Planning OPW26 0079 (As Published).pdf)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

Full text of the other 7 pages

Page 2

                                       Figure 1 – Locality




                                       Figure 2 – Site Plan


               2.     SITE DETAILS
               2.1. Site Description
               Residential.

                                                              Page 2 of 8

Document Set ID: 25060057
Version: 4, Version Date: 25/08/2026

Page 3

               2.2. Surrounding Land Uses
               Low Density Residential, Environmental Management and Conservation.
               3.      ASSESSMENT
               3.1. Instruments for Statutory Assessment
               Under the Planning Act 2016 the application must be assessed against each of the following
               statutory planning instruments to the extent they are relevant to the development:
               •       State Planning Policy;
               •       South East Queensland Regional Plan;
               •       Planning Regulation 2017; and
               •       Noosa Plan 2020 (20 March 2026).
               3.2. Noosa Plan 2020
               The following codes from the Noosa Plan 2020 are applicable to this development:
               •       Low Density Housing Zone Code;
               The application has been found to generally comply with all applicable statutory instruments. The
               pertinent issues arising out of the assessment are discussed below:
               The site recently cleared of the previous dwelling, associated structures and vegetation has a
               single street frontage, Shearwater Street. The proposal is for the instatement of a new vehicle
               crossover replacing a pre-existing decommissioned crossover. The proposed vehicle crossover is
               intended to facilitate access to a future dwelling that does not from part of this application.
               The plan submitted as part of the application material is deemed to sufficiently detail the extent of
               work and engineering considers that the proposed vehicle crossover is consistent with existing
               crossovers in Shearwater Street, Peregian Beach.
               4.      CONSULTATION
               4.1. Referral Agencies
               Not Applicable
               4.2. Internal Council Referrals
               Not applicable
               5.      CONCLUSION & REASONS FOR DECISION
               The proposed development generally complies with the requirements of the planning scheme and
               does not raise any significant issues that cannot be addressed by reasonable and relevant
               conditions. The application is therefore recommended for approval.
               The report is provided in accordance with Section 63(5) of the Planning Act 2016.
               RECOMMENDATION
               With regard to Application No OPW26/0079 for Operational Works - Vehicle Crossover situated at
               18 Shearwater St Peregian Beach Qld 4573 and described as Lot 424 P 93116, it is recommended
               the application be approved in accordance with the following details for the Decision Notice:
               1.      APPLICATION DETAILS

                   Application No:              OPW26/0079

                   Street address:              18 Shearwater St Peregian Beach Qld 4573

                   Real property description:   Lot 424 P 93116



                                                                                                       Page 3 of 8

Document Set ID: 25060057
Version: 4, Version Date: 25/08/2026

Page 4

                   Planning Scheme:                Noosa Plan 2020 (20 March 2026)

               2.      DECISION DETAILS

               Council decided to issue the following type of approval:
               •       Development Permit for Operational Works - Vehicle Crossover
               3.      CURRENCY PERIOD OF APPROVAL

               The currency period for this development approval is stated in the conditions below.
               4.      ASSESSMENT MANAGER CONDITIONS

               APPROVED PLANS
               1.      Development undertaken in accordance with this approval must generally comply with the
                       approved plans of development. The approved plans are listed in the following table unless
                       otherwise amended by these conditions.

                            Plan No.           Rev.     Plan/Document Name                          Date

                            WD - 1.02          -        Driveway Crossover Details                  11/06/2026
                                                        – Project No. 23-021
                                                        Prepared by Applicant

               CURRENCY PERIOD
               2.      The Currency Period for this development approval lapses if the development has not
                       substantially started by 25 August 2028, unless an application to extend the currency period
                       is approved by Council.
               SITE SPECIFIC CONDITIONS
                       Bonds
               3.      A site control and/or compliance bond of $5000 is to be submitted to Council prior to the pre-
                       start meeting. The pre-start meeting will only be held once Council's Construction
                       Engineering Officer has confirmation that the bond monies have been received by Council.
               4.      The bond will be refunded less any costs incurred by Council in ensuring compliance with
                       these conditions or any additional inspections incurred for substandard work or work
                       undertaken not in accordance with this permit.
               GENERAL CONDITIONS
                       Engineering
               5.      A condition report including photographs of the frontage of the site must be completed and
                       submitted to Council at the prestart meeting.
               6.      The principal contractor must have all the appropriate insurance and public liability
                       documentation to carry out the works. The principal contractor is also responsible to ensure
                       that any subcontractors also have the appropriate insurance and public liability
                       documentation. Certificates demonstrating currency of public liability insurance and works
                       insurance covering the works must be submitted to Council prior to the prestart meeting.
               7.      Council must be contacted at least 5 working days prior to any works commencing to
                       organise a prestart. The contact number to arrange a pre-start meeting is 5329 6500. The
                       pre-start meeting must include the relevant parties for the following aspects of the works:
                       a.      Civil engineering works;



                                                                                                        Page 4 of 8

Document Set ID: 25060057
Version: 4, Version Date: 25/08/2026

Page 5

               8.     A Construction Management Plan must be submitted to Council prior to the pre-start meeting
                      and must specifically address the following:
                      a.      Traffic Management during the construction phase.
                      b.      Appropriate traffic signage in accordance with the Manual of Uniform Traffic Control
                              Devices (MUTCD)
                      c.      Provision for safe pedestrian access across the frontage of the site both.
               9.     Any conflict between the development and an existing or proposed service must be referred
                      to the relevant service authority for determination prior to commencement of works.
               DURING CONSTRUCTION
                      Engineering
               10.    The integrity and condition of any existing public or Council infrastructure and services
                      (above ground and/or underground) must not be adversely affected by the proposed works
               11.    The developer must meet any costs to repair damage to any Council asset during
                      construction, where damage is a result of the development works. Damage to assets must
                      be repaired immediately where it creates a hazard to the community. In circumstances where
                      the damage does not create a hazard to the community, it must be repaired immediately on
                      completion of the works associated with the development.
               12.    All works must be constructed and work procedure undertaken in accordance with:
                      a.      the approved plans/documents and conditions detailed in this Decision Notice
                      b.      all relevant Noosa Council Planning Scheme Policies, standard drawings, standard
                              specifications and guidelines
                      c.      the latest version of the Healthy Waterways document “Water Sensitive Urban Design
                              Technical Design Guidelines for South East Queensland” for all water quality devices
                              to be constructed on site.
                     Works within Road Reserves
               13.    No removal of street trees is permitted without Council’s prior written approval.
               14.    Safe pedestrian access on all streets in the vicinity of the development must be maintained
                      at all times. Should footpath/road closures be necessary to carry out construction works,
                      Council’s Engineering Officer must be notified prior to the proposed closure and all
                      requirements complied with.
               15.    All works must match neatly with existing road and verge/footpath features. Additional works
                      beyond the frontage may be required to provide an acceptable transition to existing road and
                      verge/footpath profiles.
                     Driveways
               16.    Driveway crossovers must be constructed generally in accordance Council’s Standard
                      Drawings RS-049, RS-050 and any associated addendum.
               17.    Any existing unnecessary or redundant property accesses must be removed, and the kerb,
                      footpath and verge area reinstated to match the existing footpath and/or verge treatments.
                      Grassed verge areas to be reinstated must be provided with 100 mm topsoil and grass seed
                      or turf, and must be maintained by the developer until established.
               18.    The following must be complied with during the construction of the required
                      crossover/driveway:
                      a.      the driveway surfacing must consist of either an approved hot mixed asphaltic concrete
                              or patterned/plain concrete.
                      b.      the driveway must be in accordance with the requirements of AS2890.1 Off-Street Car
                              Parking for longitudinal and crossfall gradients.

                                                                                                           Page 5 of 8

Document Set ID: 25060057
Version: 4, Version Date: 25/08/2026

Page 6

                      c.      the driveway must be constructed so as to not concentrate or direct stormwater runoff
                              onto neighbouring properties
                      d.      underground service conduits for water supply, electricity and any other services must
                              be provided as part of the access driveway
                      e.      where there is an existing pedestrian path, a matching crossfall must be provided for
                              the driveway on the alignment of the path, for the full width of the path
                      f.      have a minimum clearance of 500mm from any Unitywater/Energex/Telstra asset,
                              unless a written approval is obtained from Unitywater/Energex/Telstra and submitted
                              to Council.
                      g.      any stormwater kerb outlet in close proximity to the edge of the new driveway must be
                              provided with an approved kerb adaptor
                      h.      any existing kerb sections requiring removal due to the works must be saw-cut and
                              removed to allow for a smooth and neat finish with the new driveway
               19.    Pavement design for privately owned works must be undertaken in accordance with the
                      relevant standards. Structural integrity of the driveway and car park areas will remain the
                      responsibility of the property owner/developer.
                      Stormwater Drainage
               20.    The constructed driveway must not cause additional ponding on the road formation or the
                      road reserve.
                      Environment (Erosion and Sediment Control)
               21.    Prescribed Water Contaminants (as defined in the Environmental Protection Act 1994) must
                      not be released from the site or to waters within the site, or be likely to be released should
                      rainfall occur, unless all reasonable and practicable measures are taken to prevent or
                      minimise the release and concentration of contamination.
               22.    The contractor must ensure non-essential exposure of soil is prevented by restricting the
                      extent of works and minimising the duration of soil exposure to adverse weather conditions.
                      Exposed areas must be suitably covered/stabilised/reinstated as soon as practicable and
                      prior to any predicted rainfall occurring.
               23.    Erosion and sediment control measures must be installed and maintained to minimise
                      erosion on the site and to minimise the export of sediment and associated pollutants from
                      the site. The erosion and sediment control measures must be designed, installed and
                      maintained in accordance with current best practice standards (refer to advisory notes).
               FOLLOWING CONSTRUCTION
               24.    A final inspection and approval of the new driveway and completed reinstatement works by
                      Council’s Inspector is required. Please contact Council on 5329 6500 to arrange for the
                      inspection.
                      Bonds
               25.    Bonds must:
                      a.      meet the requirements of council’s relevant Planning Scheme Policy for performance
                              and uncompleted works.
                      b.      be calculated using a schedule of works and relevant bond equation
                      c.      include GST
                      d.      have approval of the bond calculations and amount from Council prior to lodgement
                      e.      be lodged with Council and accompanied by the Bond Administration Fee/s.
                      f.      be requested for release by writing to Council, when relevant approval requirements
                              have been met.

                                                                                                        Page 6 of 8

Document Set ID: 25060057
Version: 4, Version Date: 25/08/2026

Page 7

               5.     REFERENCE DOCUMENTS

               Not applicable.
               6.     REFERRAL AGENCIES

               Not applicable.
               7.     ADVISORY NOTES

               The following notes are included for guidance and information purposes only and do not form part
               of the assessment manager conditions:
                      General Advisory Notes
               1.     As this driveway is a private structure, the owner bears full responsibly for the standard of its
                      construction, maintenance and any liabilities associated with its construction. It is
                      recommended that professional advice be sought for the construction of the driveway to
                      ensure that the driveway is constructed in accordance with standard drawing RS-049 and
                      RS-050.
               2.     Council reserves the right to call up any performance bond held or levy charges against the
                      property, should emergency works be required to be undertaken by Council to make the site
                      safe due to inactivity on the development site for extended periods of time.
               3.     Should any changes or modifications to the approved plans be required as a result of
                      construction constraints, a “Request to change an existing approval” under the Planning Act
                      2016 must be made. Amended plans clearly indicating the changes must be lodged with this
                      application along with the appropriate fees.
                      Prestart Inspections Request
               4.     Contact Council on 5329 6500 to arrange a prestart or an inspection giving a minimum of 5
                      business days notice of preferred inspection time.
                      It should be noted prior to arranging a pre-start meeting the Appeal Period of 20 business
                      days must have passed or the applicant must have provided Council with written confirmation
                      that the applicant has accepted the conditions of Decision Notice and waived their appeal
                      rights.
               5.     If Council officers are required to undertake additional inspections of the same works, a
                      reinspection fee will be applicable in accordance with Council’s Fees and Charges register
                      applicable at the time.
                      Environmental Advisory Notes
               6.     The Environmental Protection Act 1994 states that a person must not carry out any activity
                      that causes, or is likely to cause, environmental harm unless the person takes all reasonable
                      and practicable measures to prevent or minimise the harm. Environmental harm includes
                      environmental nuisance. In this regard persons and entities, involved in the civil, earthworks,
                      construction and landscaping phases of this development are to adhere to their ‘general
                      environmental duty’ to minimise the risk of causing environmental harm.
                      Erosion and Sediment Control
               7.     Accepted best practice standards include International Erosion Control Association
                      Australasia Best Practice Erosion and Sediment Control
                      Road Reserve Permit
               8.     This development permit provides the applicant with written authority to undertake the
                      prescribed works. Any additional activities that are undertaken inside Council’s road reserve
                      for the purpose of acting on this development permit may require a Road Reserve Permit.
                      These additional activities may include, but are not limited to, hoarding, pedestrian
                      diversions, laneway closures, etc. To apply for a Road Reserve Permit, or for more
                      information, Contact Council’s Road Reserve Officer at [email protected] 7 of 8

Document Set ID: 25060057
Version: 4, Version Date: 25/08/2026

Page 8

                      Biosecurity Act 2014 – Fire Ant Control
               9.     Developers must remain vigilant for the presence of fire ants. Under the Biosecurity Act 2014,
                      individuals and businesses are responsible for ensuring that they follow the movement
                      controls for specific organic materials to help prevent the spread of fire ants within South
                      East Queensland’s fire ant biosecurity zones. Movement of a fire ant carrier from within a fire
                      ant biosecurity zone may need a biosecurity instrument permit. More information is available
                      on https://www.fireants.org.au/treat/business-andindustry/movement-controls
                      Performance Bond Agreement
               10.    An applicant for a development application may make an agreement with an assessment
                      manager, referral agency or other person to establish the responsibilities, or secure the
                      performance, of a party to the agreement about a development condition.
               8.     PROPERTY NOTES

               Not applicable.
               9.     VARIATION APPROVAL DETAILS

               Not applicable.
               10.    FURTHER DEVELOPMENT PERMITS REQUIRED

               Not applicable.
               11.    SUBMISSIONS

               Not applicable.
               12.    RIGHTS OF APPEAL

               You are entitled to appeal against this decision. A copy of the relevant appeal provisions from the
               Planning Act 2016 is attached.
               During the appeal period, you as the applicant may suspend your appeal period and make written
               representations to Council about the conditions contained within the development approval. If
               Council agrees or agrees in part with the representations, a negotiated decision notice will be
               issued. Only one negotiated decision notice may be given.
               13.    OTHER DETAILS

               If you wish to obtain more information about the decision, electronic copies are available online at
               www.noosa.qld.gov.au or at Council Offices.




                                                                                                        Page 8 of 8

Document Set ID: 25060057
Version: 4, Version Date: 25/08/2026

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.