Council archive · source document
Negotiated Report (Representations made) MCU24 0153 (As Published) · MCU24/0153
REQUEST FOR NEGOTIATED DECISION REPORT
Author Senior Development Planner, Andrew Gaffney
Development Assessment
APPLICATION DETAILS
Application No. MCU24/0153 and OPW24/0202
Development Approval Material Change of Use - Multiple dwelling
Applicant Archend
Representations Received On 26 September 2025
Negotiated Decision Due Date 12 December 2025
Report Reviewed & Finalised Nadine Gorton 15.12.2025
By
Number of Submissions for Not applicable.
Original Application
PROPERTY DETAILS
Property Address 51 Elanda St Sunshine Beach Qld 4567
RP Description Lot 403 RP 48112
Land Area 754.0000 m²
Existing Use of Land Dwelling house
STATUTORY DETAILS
SEQRP Designation Urban Footprint
Zone High Density Residential zone
Precinct Not applicable
Local Area Plan Coastal Communities
Overlays Landslide Hazard Overlay (Moderate Hazard)
Assessment Type Code
1. BACKGROUND
A development approval for a Material Change of Use - Multiple dwelling was issued on 11 August
2025.
Page 1 of 20
Document Set ID: 24188054
Version: 10, Version Date: 18/12/2025
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalFull text of the other 19 pages
Page 2
The applicant suspended the appeal period and made representations on 26 September 2025 to
the development approval conditions. The representations are detailed below but primarily relate
to converting the Preliminary approval for Operational Works to a Development permit and
updating the approved plans for the Material change of use for six small dwellings to accommodate
Council requested amendments.
The submission includes revised architectural, landscape, and engineering plans addressing
conditions in the original decision notice, such as adjustments to gross floor area calculations,
increased screening and setbacks, and confirmation that building height remains compliant. It also
details updates to stormwater and access designs, incorporating climate change allowances and
basement manoeuvring compliance.
An assessment in relation to each of the submitted representations is provided below:
Existing Section 2 - Decision Details
While not specifically requested by the Applicant the Decision Notice ‘Development Description’ is
required to be amended to reflect the change in the Operational works approval from a Preliminary
approval to a Development permit.
Assessment of Request
Development engineering have reviewed the additional and updated operational works information
and agree a Development permit for operational works can now be issued.
Recommendation
It is recommended existing Section 2 be amended to read as follows:
• Development Permit for Operational Works - Roadworks, Stormwater, Landscaping and
Earthworks.
Existing Condition 3 of Material Change of Use (MCU 24/0153)
Approved Plans
3. Development authorised by this approval must be undertaken generally in accordance with
the Approved Plans listed in the tables below. The plans must be amended to incorporate
the amendments listed within the table below and resubmitted to Council prior to the issue
of any Development Permit for Operational Works*.
Plan No. Rev. Plan/Document Name Date
- - - -
The following plans require amendment.
Plan No. Rev. Plan/Document Name Date
08 C Site Plan prepared by Archend 01.06.205
C Site Plan – landscaping areas prepared by 01.06.205
Archend
15 C Floor Plan – Basement prepared by 01.06.205
Archend
Page 2 of 20
Document Set ID: 24188054
Version: 10, Version Date: 18/12/2025
Page 3
16 C General Arrangement - Ground Floor 01.06.205
prepared by Archend
17 C Floor Plan - Level 1 prepared by Archend 01.06.205
18 C Floor Plan - Level 2 prepared by Archend 01.06.205
23 C North Elevation - prepared by Archend 01.06.205
24 C South Elevation - prepared by Archend 01.06.205
25 C West and East Elevation - prepared by 01.06.205
Archend
26 C Section A - prepared by Archend 01.06.205
27 C Section A2 - prepared by Archend 01.06.205
28 C Section B & B2 - prepared by Archend 01.06.205
19 C Floor Plan – Roof - prepared by Archend 01.06.205
Amendments Plot ratio
1) Reduce the development’s plot ratio to achieve a 0:75:1 / total
gross floor area no greater than 565.7m2. The laundry areas in
Unit 1 and 2 and kitchen areas in Units 3 - 6 are to be included
in gross floor area calculations
Building Setbacks
2) Unit 1 - Courtyard screening is to be increase to 3.5 metres in
length along northern alignment;
3) Unit 3 - Northern external curved blade wall outside Bed 3 and
Living and dining area is to be removed.
4) Unit 5 - the ‘garden bed’ along the northern side setback to be
increased to 2.0 metres.
Building Height
5) Provide revised plans reduce the building height to 12 metres
above ground level, except where relating to minor elements i.e.,
part of balustrade on rooftop terrace.
Rooftop Terrace
6) Unit 5’s rooftop terrace platform is to achieve a minimum setback
of 2.5 metres (this includes the pool, terrace and planter box).
*(Refer to Advisory Note)
Applicant’s Request
The applicant has requested existing Condition 3 be amended to endorse approved plans for the
development application as they have been amended to include the required changes:
Page 3 of 20
Document Set ID: 24188054
Version: 10, Version Date: 18/12/2025
Page 4
Assessment of Request
The applicant submits that the requested Council amendments are satisfied on the basis that the
Architectural Plans have been amended to include:
• laundry and kitchen areas within the site gross floor area calculations, confirming a maximum
plot ratio of 0.75:1.
• courtyard screening for Unit 1, deletion of a curved blade wall for Unit 3, and adjustments to
garden beds and rooftop terrace setbacks for Unit 5; and
• confirmation that the building height remains under 12 metres above ground level, except for
minor rooftop elements.
It is agreed that the submitted plans and elevations have been amended to include the above listed
Council amendments.
Additional amendments were requested regarding the rooftop terrace design to ensure that the
more active areas (plunge pool and terrace area) are located towards the middle and western
portion of the roof to assist with centralising areas of rooftop recreation to one location and to
restrict overlooking opportunities occurring across the roof area.
The rooftop includes landscaping directly around the pool and terrace aeras which contributes to
the local skyline from Elanda Street and avoids boxy profiles at the rooftop level. As indicated in
the diagram below the rooftop terrace will be setback 4.0 metres from the northern side boundary
and includes a 1.5 metre high battened screening (blue highlight). The screening does not exceed
maximum building height and assists with reducing direct overlooking to neighbouring properties.
Recommendation
It is recommended existing condition 3 be amended to read as follows:
Approved Plans
3. Development undertaken in accordance with this approval must generally comply with
the approved plans of development. The approved plans are listed in the following
table unless otherwise amended by these conditions.
Plan No. Rev. Plan/Document Name Date
Page 4 of 20
Document Set ID: 24188054
Version: 10, Version Date: 18/12/2025
Page 5
08 E Site Plan, prepared by Archend 28/11/2025
11 E Site Plan - Landscaping Areas, prepared 28/11/2025
by Archend
15 E Floor Plan - Basement, prepared by 28/11/2025
Archend
16 E General Arrangement - Ground Floor, 28/11/2025
prepared by Archend
17 E Floor Plan - Level 1, prepared by 28/11/2025
Archend
18 E Floor Plan - Level 2, prepared by 28/11/2025
Archend
19 E Floor Plan - Roof, prepared by Archend 28/11/2025
20 E Floor Plan - Ground GFA, prepared by 28/11/2025
Archend
21 E Floor Plan - Level 1 GFA, prepared by 28/11/2025
Archend
22 E Floor Plan - Level 2 GFA, prepared by 28/11/2025
Archend
23 E North Elevation, prepared by Archend 28/11/2025
24 E South Elevation, prepared by Archend 28/11/2025
25 E West and East - Elevation, prepared by 28/11/2025
Archend
26 E Section A, prepared by Archend 28/11/2025
27 E Section A2, prepared by Archend 28/11/2025
28 E Section B and B2, prepared by Archend 28/11/2025
Page 5 of 20
Document Set ID: 24188054
Version: 10, Version Date: 18/12/2025
Page 6
Existing Condition 1 of the Preliminary Approval for Operational Works (OPW 24/0202)
PRELIMINARY APPROVAL FOR OPERATIONAL WORKS (OPW24/0202)
1. Amended plans and associated reports must be submitted to Council prior to any further
development applications being made and must include the following to the reasonable
satisfaction of the Manager, Development Assessment:
1.1. Provide updated stormwater and engineering drawings including:
a. Additional detail demonstrating that the post-development peak flow rate
discharging to structure “7/1” does not exceed the pre-development peak flow
rate. The detail must clearly demonstrate that the development and calculations
incorporate appropriate climate change allowances in accordance with AO2.4 of
the Water Quality and Drainage Code.
Additional detail confirming an appropriate climate change allowance has been
applied to the sizing of all detention tanks.
A stormwater design calculation table.
Details of detention outlet orifices / controls.
Engineering documentation showing the materials, stair treatment and handrails
along the pedestrian pathway adjacent to the southern frontage;
Prepared by a suitably qualified person (RPEQ)
1.2. Provide updated access drawings/documents including:
a. Appropriate manoeuvring areas for access to the car stackers in accordance with
AS2890.1:2004 and the manufacturers specifications.
b. Linemarkings for the car stackers.
c. Prepared by a suitably qualified person (RPEQ).
Applicant’s Request
The applicant submits;
‘In accordance with Condition 1 of the Preliminary Approval for Operational Works, the Engineering
and Landscape Plans have been revised to reflect the Architectural Plans. In addition to this, the
Engineering and Landscape Plans have been amended to include the following:
● Updated stormwater and engineering drawings including:
a. Additional detail demonstrating that the post-development peak flow rate discharging to structure
“7/1” does not exceed the pre-development peak flow rate. The detail must clearly demonstrate
that the development and calculations incorporate appropriate climate change allowances in
accordance with AO2.4 of the Water Quality and Drainage Code.
b. Additional detail confirming an appropriate climate change allowance has been applied to the
sizing of all detention tanks.
c. A stormwater design calculation table.
d. Details of detention outlet orifices / controls.
e. Engineering documentation showing the materials, stair treatment and handrails along the
pedestrian pathway adjacent to the southern frontage; f. Prepared by a suitably qualified person
(RPEQ)
● Updated access drawings/documents including:
Page 6 of 20
Document Set ID: 24188054
Version: 10, Version Date: 18/12/2025
Page 7
a. Appropriate manoeuvring areas for access to the car stackers in accordance with
AS2890.1:2004 and the manufacturers specifications.
b. Linemarkings for the car stackers.
c. Prepared by a suitably qualified person (RPEQ).
It is requested that standard conditions are applied to the Development Permit’.
Assessment of Request
Development engineering have reviewed the representation from the applicant and advise:
The conditions of the preliminary approval were applied to seek additional information regarding
stormwater detention and functionality of the proposed car stackers.
With respect to preliminary condition 1.1, the applicant’s engineer has provided additional detail
that is generally successful in demonstrating that the pre-development peak flowrate will not
exceed post-development of the existing field inlet in the road reserve (labelled as “7/1”).
Engineering notes that the existing catchment of the footpath (and adjoining areas of verge) has
not been considered in these calculations. This exclusion, although undesirable, is considered
acceptable in this instance since the catchment currently exists, is not being worsened as part of
these works, and remains consistent with QUDM (i.e., minor storm flows to be managed via
stormwater pipes versus major storm flows to be managed via overland flow).
With respects to preliminary condition 1.2, additional information has been provided demonstrating
linemarking of the car stackers in accordance with AS2890.1-2004 and that the B85 design vehicle
can access each park.
Recommendation
It is recommended that:
• OPW condition 1 be amended to reflect the revised plans;
• New operational works conditions are added to the approval
• Advisory notes are included and updated to reflect operational works requirements under
Section 5;
• the reference documents and future development permits required tables are updated to
reflect Sections 6 & 7.
The recommendation has been updated to include the new suite of conditions and advisory notes
2. CONCLUSION & REASONS FOR DECISION
The proposed development generally complies with the requirements of the planning scheme. The
requested changes to the conditions do not raise any significant issues and are therefore
supported. The application is therefore recommended for approval.
The report is provided in accordance with Section 76 of the Planning Act 2016.
RECOMMENDATION
With regard to Application No. MCU24/0153 OPW24/0202 and the representations made, Council
on 15 December 2025 decided to:
A. Agree to amend the ‘Decision Details’ to read as follows:
• Development Permit Material Change of Use - Multiple dwelling (6 small dwellings);
• Development Permit for Operational Works - Roadworks, Stormwater, Landscaping and
Earthworks.
B. Agree to the representations and amend Condition 3 of the Material change of use approval
(MCU24/0153) to read as follows:
Page 7 of 20
Document Set ID: 24188054
Version: 10, Version Date: 18/12/2025
Page 8
Approved Plans
3. Development undertaken in accordance with this approval must generally comply with the
approved plans of development. The approved plans are listed in the following table unless
otherwise amended by these conditions*.
Plan No. Rev. Plan/Document Name Date
08 E Site Plan, prepared by Archend 28/11/2025
11 E Site Plan - Landscaping Areas, prepared by 28/11/2025
Archend
15 E Floor Plan - Basement, prepared by 28/11/2025
Archend
16 E General Arrangement - Ground Floor, 28/11/2025
prepared by Archend
17 E Floor Plan - Level 1, prepared by Archend 28/11/2025
18 E Floor Plan - Level 2, prepared by Archend 28/11/2025
19 E Floor Plan - Roof, prepared by Archend 28/11/2025
20 E Floor Plan - Ground GFA, prepared by 28/11/2025
Archend
21 E Floor Plan - Level 1 GFA, prepared by 28/11/2025
Archend
22 E Floor Plan - Level 2 GFA, prepared by 28/11/2025
Archend
23 E North Elevation, prepared by Archend 28/11/2025
24 E South Elevation, prepared by Archend 28/11/2025
25 E West and East - Elevation, prepared by 28/11/2025
Archend
26 E Section A, prepared by Archend 28/11/2025
Page 8 of 20
Document Set ID: 24188054
Version: 10, Version Date: 18/12/2025
Page 9
27 E Section A2, prepared by Archend 28/11/2025
28 E Section B and B2, prepared by Archend 28/11/2025
C. Agree to the representations to grant a Development permit for Operational Works and
amend Condition 1 to read as follows;
DEVELOPMENT PERMIT FOR OPERATIONAL WORKS (OPW24/0202) ROAD WORK,
DRAINAGE WORK, STORMWATER, EARTHWORKS, CAR PARKING & LANDSCAPING
Approved Plans
1. Development undertaken in accordance with this approval must generally comply with the
approved plans of development. The approved plans are listed in the following table unless
otherwise amended by these conditions.
Plan No. Rev. Plan/Document Name Date
010 B Siteworks Overall Layout Ground 26 August
2025
Prepared by RECOR
As Annotated by Council
011 B Siteworks Overall Layout Basement 26 August
2025
Prepared by RECOR
012 B Detailed Ground Level Layout 26 August
2025
Prepared by RECOR
014 B Vehicle Crossover Longitudinal Section 26 August
2025
Prepared by RECOR
015 B Footpath Longitudinal Section 26 August
2025
Prepared by RECOR
As Annotated by Council
016 B Roadworks Details 26 August
2025
Prepared by RECOR
017 B Driveway Vertical Vehicle Tracking 26 August
2025
Prepared by RECOR
020 B Bulk Earthworks Layout Plan 26 August
2025
Prepared by RECOR
021 B Bulk Earthworks Sections Sheet 1 26 August
2025
Prepared by RECOR
Page 9 of 20
Document Set ID: 24188054
Version: 10, Version Date: 18/12/2025
Page 10
022 B Bulk Earthworks Sections Sheet 2 26 August
2025
Prepared by RECOR
042 B Stormwater Longitudinal Sections Sheet 1 26 August
2025
Prepared by RECOR
043 B Stormwater Longitudinal Sections Sheet 2 26 August
2025
Prepared by RECOR
041 B Stormwater Catchment Layout 26 August
2025
Prepared by RECOR
044 A Stormwater Details 26 August
2025
Prepared by RECOR
LD1 F General Notes, Sheet Layout & Site 02/12/2025
Location prepared by Anembo Consultants
LD2 F Project Specifications prepared by Anembo 02/12/2025
Consultants
LD3 F Project Specifications, Annual 02/12/2025
Maintenance & Finishes Schedule
prepared by Anembo Consultants
LD4 F Plant Schedules prepared by Anembo 02/12/2025
Consultants
LD5 F Typical Details prepared by Anembo 02/12/2025
Consultants
LP1 F Landscape Plan (Ground 1/2) prepared by 02/12/2025
Anembo Consultants
LP2 F Landscape Plan (Ground 2/2) prepared by 02/12/2025
Anembo Consultants
LP3 F Landscape Plan (First Level) prepared by 02/12/2025
Anembo Consultants
LP4 F Landscape Plan (Second Floor) prepared 02/12/2025
by Anembo Consultants
LP5 F Landscape Plan (Roof) prepared by 02/12/2025
Anembo Consultants
D. Agree to the representations and include Conditions 3 - 56 for Operational Works
(OPW24/0202) to read as follows;
SITE SPECIFIC CONDITIONS
Bonds
Page 10 of 20
Document Set ID: 24188054
Version: 10, Version Date: 18/12/2025
Page 11
3. A site control and/or compliance bond of $10,000 is to be submitted to Council prior to the
pre-start meeting. The pre-start meeting will only be held once Council's Construction
Engineering Officer has confirmation that the bond monies have been received by Council.
The bond will be refunded less any costs incurred by Council in ensuring compliance with
these conditions or any additional inspections incurred for substandard work or work
undertaken not in accordance with this permit.
4. Bonds must:
a. meet the requirements of Council’s relevant Planning Scheme Policy for performance
and uncompleted works;
b. be calculated using a schedule of works and relevant bond equation;
c. be lodged with Council and accompanied by the Bond Administration Fee/s; and
d. be requested for release by writing to Council, when relevant approval requirements
have been met.
PRIOR TO COMMENCEMENT OF WORKS
Engineering
5. All necessary approvals from external service providers (e.g., Unitywater) and external
parties on which the development works are proposed have been obtained and a copy
supplied to Council.
6. A condition report of the drainage system must be completed for agreement at the prestart
meeting. The condition report is to include a CCTV inspection of the existing field inlet
(labelled as “7/1”) to the next downstream structure, inclusive.
7. A condition report including photographs of the frontage of the site must be completed and
submitted to council at the prestart meeting / prior to any works commencing.
8. Certificates demonstrating currency of public liability insurance and works insurance covering
the works must be submitted to Council prior to the prestart meeting.
9. Council must be contacted at least 5 working days prior to any works commencing to
organise a prestart. The contact number to arrange a pre-start meeting is 5329 6500. The
pre-start meeting must include the relevant parties for the following aspects of the works:
a. Civil engineering works;
b. Landscape works;
c. Erosion and sediment control works; and
d. Other relevant parties.
10. A Construction Management Plan must be submitted to Council prior to the pre-start meeting
and must specifically address the following:
a. Traffic Management during all aspects of the construct phase including:
i. A Traffic Management Control Plan in accordance with Manual of Uniform Traffic
Control Devices (MUTCD) detailing all temporary signage and traffic control
measures prior to construction.
ii. Maintenance of safe vehicle and pedestrian access across the frontage of the
site both during daily construction and after daily construction has ceased.
iii. Proposed fencing to the site during the construction phase of the development.
iv. Adequate parking arrangements for construction workers.
v. No queuing of trucks is permitted on residential streets, especially prior to
7.00am. Further parked trucks must have engines turned off
Page 11 of 20
Document Set ID: 24188054
Version: 10, Version Date: 18/12/2025
Page 12
Maintenance and protection of water quality and existing drainage lines through the
construction site through the implementation of appropriate erosion and sediment control
measures.
Works programme identifying key components of the works and their respective durations.
Establishment of a communication protocol with the general public, adjoining owners,
emergency services and local businesses to advise of agreed construction times, impacts
on traffic and services and other relevant issues.
Include a post out to the local residents and businesses advising of the proposed
development, the expected time frames and the site contact details.
Include signage in prominent locations on the boundaries of the site advising of the proposed
development, the expected time frames and the site contact details.
identification of complaint management procedures including:
i. contact details for the on-site manager; and
i. dispute resolution procedures.
11. Any changes to the details associated with the supervising RPEQ or Principal Contractor
during construction, must be notified to council in writing within five business days of the
change occurring.
12. Any conflict between the development and an existing or proposed service must be referred
to the relevant service authority for determination prior to commencement of works.
DURING CONSTRUCTION
Engineering
13. The developer must meet any costs to repair damage to any Council asset during
construction, where damage is a result of the development works. Damage to assets must
be repaired immediately where it creates a hazard to the community. In circumstances where
the damage does not create a hazard to the community, it must be repaired immediately on
completion of the works associated with the development.
14. All works must be supervised by a Registered Professional Engineer of Queensland (RPEQ)
who is independent of the Developer and Principal Contractor, and they must certify that all
works conform to the Operational Works permit. Where municipal works are involved, such
confirmation must be submitted for the respective hold points prior to any site inspection by
Council Officers.
15. All works must be constructed and work procedure undertaken in accordance with:
a. The approved plans/documents and conditions detailed in this Decision Notice.
b. All relevant Noosa Council Planning Scheme Policies, standard drawings, standard
specifications and guidelines.
c. The relevant conditions of the higher order Material Change of Use approval viz
MCU24/0153 to which this approval relates.
d. The latest version of the Healthy Waterways document “Water Sensitive Urban Design
Technical Design Guidelines for South East Queensland” for all water quality devices
to be constructed on site.
Retention of Existing Trees and Vegetation
16. All trees and vegetation identified for retention must be protected in accordance with AS
4970, Protection of trees on development sites.
17. A qualified person * must be engaged for the duration of the works to:
Page 12 of 20
Document Set ID: 24188054
Version: 10, Version Date: 18/12/2025
Page 13
a. Supervise tree protection within the development site and frontages, prior to, during
and following construction in accordance with AS 4970, Protection of trees on
development sites.
b. Supervise and undertake necessary tree protection for all trees affected by the
development on neighbouring Lots. This includes tree identified in the approved
arborist report as outside project scope within the neighbouring properties east of the
development site. Where trees within neighbouring properties are found to be unsafe
due to works relating to this development approval, the developer is solely responsible
for the removal and replacement of these trees.
c. Oversee approved tree removal in proximity to retained trees.
*(Refer to Advisory Note)
Vegetation Clearing
18. Removal of trees and vegetation must be undertaken by a qualified person* and must
include:
a. No damage to vegetation for retention.
b. Legal disposal of all removed vegetation and debris.
Fauna Management
19. Prior to felling or pruning, all trees are to be checked for wildlife (i.e. koalas, possums, birds
etc.) If wildlife is present, the tree vegetation must not be felled or pruned until the wildlife
has left vegetation or has been relocated by a qualified fauna spotter catcher.
*(Refer to Advisory Note)
Landscaping Works
20. Landscape works must be supervised, undertaken and certified by qualified persons*. All
works must be completed in accordance with this Decision Notice.
(* Refer to Advisory Note)
21. Public amenity trees* must:
a. Meet AS 2302 – Tree Stock for landscape use.
b. Be located in accordance with engineering requirements for safe vehicle and
pedestrian sight lines.
*(Refer to Advisory Note)
22. Turfed areas must be free of pest, diseases and weeds and level with adjoining surfaces.
Roadworks (External Roadworks & Road Widening Works)
23. All pavement widening or construction of new pavement must join neatly to the existing
pavement so that there are no irregularities in line or level resulting at or adjacent to the join
for the length of the construction. Where necessary the existing pavement must be brought
to a satisfactory standard to allow for the above.
24. All street surfacing must consist of a minimum depth of 30mm of an approved hot mixed
asphaltic concrete, unless other pavement types are approved as feature areas in
intersection thresholds, speed control devices, turning areas, indented parking etc.
Pavement Design and Construction
25. The pavement designs shown on the engineering drawings are not approved. To attain
approval for the pavement design, the following details must be submitted and certified by
an RPEQ with the proposed pavement design.
a. The design CBR must be based on the four day soaked CBR value for the subgrade
material.
Page 13 of 20
Document Set ID: 24188054
Version: 10, Version Date: 18/12/2025
Page 14
b. The design subgrade CBR must be representative of each homogenous insitu section
of finished subgrade. With respect to each section:
i. For four or less test results, the design CBR must be taken as the least estimated
insitu CBR result.
i. For five or more test results, the design CBR must be taken as the 10th percentile
of all estimated insitu CBR results.
c. The samples must be taken generally in the position of the outer wheel path on both
sides of the proposed road. A sketch plan showing the location of all tests must be
submitted with the test results for pavement design approval.
d. Where imported material has been (or is proposed to be) used for subgrade
replacement, and the depth of the imported material is less than 300mm, the pavement
design CBR must be based on the testing results of the insitu material and not the
imported material.
26. At the time of subgrade inspection, the subgrade must exhibit no visible signs of deformation
under proof rolling by a fully loaded water truck. The pavement subgrade will not be passed
until this requirement has been achieved.
27. Pavement design for privately owned works must be undertaken in accordance with the
relevant standards. Structural integrity of the driveway and car park areas will remain the
responsibility of the property owner/developer and must be certified by an RPEQ.
Works within Road Reserve/Reinstatement
28. Safe pedestrian and vehicle access on all streets in the vicinity of the development must be
maintained at all times. Should footpath/road closures be necessary to carry out construction
works, Council’s Engineering Officer must be notified prior to the proposed closure and all
requirements complied with.
29. All frontage works must match neatly with existing road and verge/footpath features.
Additional works beyond the frontage may be required to provide an acceptable transition to
existing road and verge/footpath profiles.
30. Electrical conduits or other services proposed to be installed within existing and proposed
road reserves under existing sealed carriageways, concrete pathways, concrete/sealed
driveways or significant vegetation must be installed by boring. Trenching is not permitted,
unless specifically approved by Council.
Pathways
31. All pathways must be constructed in accordance with the following requirements:
a. All footpath/cycleway must comply with Council’s Standard Drawing SEQ R-065.
b. Provision must be made for disabled access at all kerb crossings associated with
pathways, in accordance with Council's current standards.
c. All paths must have a slip resistant surface.
d. Expansion and contraction joints must provide a flush finish. Installation of joints by
saw cutting is preferred to ensure a smooth ride for cyclists.
e. The required work includes any modifications to ensure the footpath finishes flush with
all existing service covers and the like, or alternatively these services are raised or
altered, so as not to create a pedestrian safety hazard.
32. Pathways must:
a. terminate in a manner that ensures smooth transition to existing surfaces for public
safety.
Page 14 of 20
Document Set ID: 24188054
Version: 10, Version Date: 18/12/2025
Page 15
b. be designed and constructed to comply with the Disability Discrimination Act (DDA),
Access to Premises Standard, Austroads and relevant sections of AS1428 Design for
access and mobility.
Site Access and Driveways
33. Driveway crossovers must be constructed in accordance with council’s Standard Drawings
RS-049, RS-050 and any associated addendum.
34. Any existing unnecessary or redundant property accesses must be removed, and the kerb,
footpath and verge area reinstated to match the existing footpath and/or verge treatments.
Grassed verge areas to be reinstated must be provided with 100 mm topsoil and grass seed
or turf and must be maintained by the developer until established.
35. The following must be complied with during the construction of the required
crossover/driveway:
a. The driveway surfacing must consist of either an approved hot mixed asphaltic
concrete or patterned/plain concrete.
b. The driveway must be constructed so as not to concentrate stormwater runoff onto
neighbouring properties.
c. Underground service conduits for water supply, electricity and any other services must
be provided as part of the access driveway.
d. Where there is an existing pedestrian path, a matching crossfall must be provided for
the driveway on the alignment of the path, for the full width of the path.
e. The property access must be located a minimum of 1m clear of existing power poles,
streetlights or other signage. The developer is responsible for any necessary relocation
of existing services to provide this clearance and must contact the relevant service
authorities and comply with their requirements in relation to these works.
Earthworks and Retaining Walls
36. All earthworks shall be undertaken in accordance with the provisions of AS 3798 Guidelines
on Earthworks for Commercial and Residential Development, with geotechnical testing
undertaken in accordance with Section 8 of the Standard, and to a minimum of ‘Level 1’ as
defined in Appendix B. Test results as required by AS 3798, and a certificate of quality and
uniformity of fill shall be provided by a RPEQ and submitted to Council prior to the
commencement of the use.
37. All earthworks and associated batters/retaining structures, both above and below ground
level, both temporary and permanent, must be contained entirely within the subject site
unless written permission from the respective landowner(s) is provided to Council.
38. Fall protection must be provided to retaining walls that are over 1m high.
39. Slope and batters are a maximum grade of:
a. 1 in 6 where in proximity to waterbodies.
b. 1 in 4 for grassed areas.
c. 1 in 3 for planted areas.
d. 1 in 2 for combined structural engineering and planting solutions.
Stormwater Drainage
40. Appropriate scour protection must be provided at the outlet of all stormwater pipes including
temporary outlets.
41. Works associated with this permit must not adversely impact on the existing drainage
conditions on other properties (e.g., by blocking or interfering with natural overland flows).
Page 15 of 20
Document Set ID: 24188054
Version: 10, Version Date: 18/12/2025
Page 16
42. Construction of all internal stormwater drainage works must comply with the relevant
section/s of Australian Standard AS/NZS 3500.3.
Erosion and Sediment Control
43. Prescribed Water Contaminants (as defined in Schedule 10 of Environmental Protection
Regulation 2019) must not be released from the site or to waters within the site, or be likely
to be released should rainfall occur, unless all reasonable and practicable measures are
taken to prevent or minimise the release and concentration of contamination.
44. Sediment and erosion control measures must be in place prior to works commencing. If such
measures are not in place or are not satisfactory, “on the spot” fines may be issued. Such
fines can be issued if sediments from the site are found to enter or have the potential to enter
Council’s stormwater system, natural waterways, any downstream stormwater filtration
system or adversely impacting on other properties. The sediment and erosion control design
and measures have NOT been approved, it is the site's Supervising Engineer who is
responsible for ensuring that the sediment and erosion control measures have:
a. Been duly designed by an RPEQ or CPESC and constructed in accordance with "best
practise" methods;
b. Been revised by an RPEQ or CPESC to address the issues raised by changes in the
projected construction schedule and/or methods;
c. Been revised to address predicted rainfall events; and
d. Achieve the desired environmental outcomes.
Council may request further controls to be installed should the implemented measures be
found inefficient.
45. The erosion and sediment control measures must be designed, installed and maintained in
accordance with the supervising engineer instructions and the current best practice
standards.
(*) Refer to Advisory Note
46. The developer must ensure non-essential exposure of soil is prevented by restricting the
extent of disturbance and minimising the duration of soil exposure to adverse weather
conditions and effectively turf, cover or stabilise any disturbed area without delay and prior
to rainfall occurring.
47. The developer must ensure sediment does not leave the site or enter onto adjoining
properties or Council’s drainage system due to surface runoff or on tyres of vehicles and/or
machinery. It is essential to implement appropriate approved erosion and sediment control
measures throughout the site during all phases of construction including vehicle shakedown
pad/grid (or similar) at the access to the construction site. Where sediments or other
contaminants are deposited on a road, they must be removed so as not to enter Council’s
drainage system or waterways.
48. Prior to the completion of the development and commencement of use, all site surfaces must
be effectively stabilised using methods which have achieved effective short-term stabilisation
and which will continue to achieve effective stabilisation in the medium to long-term.
For the purpose of this condition, an effectively stabilised surface is defined as one that does
not, or is not likely to result in visible evidence of soil loss caused by sheet, rill or gully erosion
or lead to sedimentation, or lead to water contamination.
Damage to Services and Assets
49. Any damage caused to existing services and assets as a result of the development works
must be repaired at no cost to the asset owner at the following times:
a. where the damage would cause a hazard to pedestrian or vehicle safety, immediately;
or
Page 16 of 20
Document Set ID: 24188054
Version: 10, Version Date: 18/12/2025
Page 17
b. where otherwise, upon completion of the works associated with the development.
Any repair work which proposes to alter the alignment or level of existing services and assets
must first be referred to the relevant service authority for approval.
FOLLOWING CONSTRUCTION AND PRIOR TO THE COMMENCEMENT OF THE USE
Supervision/Certification
50. Prior to commencement of use the following (prepared by respective qualified persons* and
certifying compliance with approvals) must be submitted to Council:
a. Landscaping certification confirming all works have been constructed in accordance
with conditions of approval.
Certification
51. Upon completion of the work a certificate must be issued by an RPEQ certifying that the
works have been constructed in accordance with the Operational Works permit.
As Constructed Plans and ADAC XML Files (Council)
52. Prior to acceptance of civil works to become Council assets “On Maintenance”, satisfactory
“As-Constructed” records must be submitted to Council. The bundle of “As Constructed”
information shall include:
a) As-Constructed Engineering Drawings. Data is to be submitted in an electronic drawing
file format (.dwg), with all plans clearly endorsed “As-Constructed”, along with the
accompanying hardcopies (PDFs of the As-Constructed .dwg drawing files), and;
b) ADAC XML Digital File. ADAC File format (ADAC - Asset Design As Constructed)
prepared in accordance with industry standards and recorded in “MGA - UTM56 /
GDA94” projection.
Please Note: Further information and advice relating to the as-constructed
drawing presentation, as-constructed survey capture and associated guidelines
for preparation of a compliant ADAC XML digital file are available on the webpage
titled “As-Constructed Guidelines” and accessible at the Noosa Council Website:
Planning & Development / Development Tools & Guidelines / As-Constructed
Guidelines.
c) The “As-Constructed” drawings will require certification by a:
i. Qualified experienced Civil Engineer (RPEQ) confirming design intent and
conformance with applicable standards and specifications, along with the
relevant descriptions of assets, services and structures and;
i. Registered Cadastral Surveyor (Qld) in regard to the cadastral and locational
information, levels and applicable survey datum.
d) The data must be in accordance with Council’s “Planning Scheme Policy 6 – Engineering
Design Standards”, and fully detail the levels for all engineering works including but not
limited to the drainage network and structures, finished ground and pavement surface
levels.
On Maintenance
53. All municipal works must be accepted ‘On Maintenance’ by Council in accordance with
Council’s relevant Planning Scheme Policy prior to the commencement of the use. To
achieve ‘On Maintenance’, the supervising RPEQ must submit to Council:
a) certification that all works have been undertaken and completed in accordance with the
requirements of this Permit.
b) as Constructed details in accordance with Council’s Planning Scheme Policy.
c) maintenance and operational manuals for all proprietary or site-specific devices
Page 17 of 20
Document Set ID: 24188054
Version: 10, Version Date: 18/12/2025
Page 18
Off Maintenance
54. Prior to requesting an Off Maintenance inspection, the developer must provide a written
request for the Off Maintenance inspection.
55. A re-inspection fee in accordance with Council’s Fees and Charge Register will be charged
where:
a. a Council inspection reveals works do not comply with approval requirements.
b. submitted certification falsely states works comply with approval requirements.
56. A final inspection and approval of the new driveway and completed reinstatement works by
Council’s Inspector is required. Please contact Council on 5329 6500 to arrange for the
inspection.
E. Agree to amend Section 5 Reference Documents to read as follows;
Plan No. Rev. Plan/Document Name Date
24265-001 0 Proposed Unit Development prepared by 30/09/2024
tectonic
- - Technical Memorandum 26 August
2025
Prepared by RECOR
LD1 D General Notes, Sheet Layout & Site 21/03/25
Location prepared by Anembo Consultants
LD2 D Project Specifications prepared by Anembo 21/03/25
Consultants
LD3 D Project Specifications, Annual 21/03/25
Maintenance & Finishes Schedule
prepared by Anembo Consultants
LD4 D Plant Schedules prepared by Anembo 21/03/25
Consultants
LD5 D Typical Details prepared by Anembo 21/03/25
Consultants
LP1 D Landscape Plan (Ground 1/2) prepared by 21/03/25
Anembo Consultants
LP2 D Landscape Plan (Ground 2/2) prepared by 21/03/25
Anembo Consultants
LP3 D Landscape Plan (First Level) prepared by 21/03/25
Anembo Consultants
LP4 D Landscape Plan (Second Floor) prepared 21/03/25
by Anembo Consultants
LP5 D Landscape Plan (Roof) prepared by 21/03/25
Anembo Consultants
Page 18 of 20
Document Set ID: 24188054
Version: 10, Version Date: 18/12/2025
Page 19
F. Agree to amend Section 7 - Advisory Notes to include additional operational works notations
14 – 26 to read as follows;
OPERATIONAL WORKS
Building and Construction Industry (Portable Long Service Leave) Levy
14. The QLeave levy must be paid prior to the issue of a development permit where it is required.
Council will not be able to issue a Decision Notice without receipt of details that the Levy has
been paid.
General Advisory Notes
15. As this driveway is a private structure, the owner bears full responsibly for the standard of its
construction, maintenance and any liabilities associated with its construction. It is
recommended that professional advice be sought for the construction of the driveway to
ensure that the driveway is constructed in accordance with standard drawings RS-049, RS-
050 and any associated addendum.
16. Council has undertaken an audit check of the Operational Works drawings in relations to the
proposed works. A detailed check of the calculations and drawings has not been undertaken,
as they have been certified by a RPEQ. The RPEQ bears full responsibility for all aspects of
the engineering design. Council reserves the right to require further amendments and/or
additions at a later date should design errors become apparent.
17. Council reserves the right to call up any performance bond held or levy charges against the
property, should emergency works be required to be undertaken by Council to make the site
safe due to inactivity on the development site for extended periods of time.
18. Should any changes or modifications to the approved plans be required as a result of
construction constraints, a “Request to change an existing approval” under the Planning Act
2016 must be made. Amended plans clearly indicating the changes must be lodged with this
application along with the appropriate fees.
Prestart, On and Off Maintenance Inspections Request
19. Contact Council on 5329 6500 to arrange a prestart or an inspection giving a minimum of 5
business days’ notice of preferred inspection time.
20. If Council officers are required to undertake additional inspections of the same works, a
reinspection fee will be applicable in accordance with Council’s Fees and Charges register
applicable at the time.
21. A minimum maintenance period of 12 months will apply to all municipal works and thereafter
until such time as the works are performing in accordance with the approved design unless
noted otherwise.
Environmental Advisory Notes
22. The Environmental Protection Act 1994 states that a person must not carry out any activity
that causes, or is likely to cause, environmental harm unless the person takes all reasonable
and practicable measures to prevent or minimise the harm. Environmental harm includes
environmental nuisance. In this regard persons and entities, involved in the civil, earthworks,
construction and landscaping phases of this development are to adhere to their ‘general
environmental duty’ to minimise the risk of causing environmental harm.
Erosion and Sediment Control
23. Accepted best practice standards include International Erosion Control Association
Australasia Best Practice Erosion and Sediment Control.
24. Qualified Person, for the purpose of erosion and sediment control is a Certified Professional
in Erosion and Sediment Control (CPESC) or suitably experienced Registered Professional
Engineer of Queensland (RPEQ).
Page 19 of 20
Document Set ID: 24188054
Version: 10, Version Date: 18/12/2025
Page 20
25. As a general rule, a site is determined to have achieved effective short-term stabilisation if
at the time of the plan sealing inspection:
a. Methods of stabilisation are:
• appropriate for slopes and slope lengths; and
• are consistent with best practice environmental management practices such as in
the Manual for Erosion and Sediment Control or the IECA Manual; and
b. Stormwater runoff from the site is not currently, and is not likely to result in visible
evidence of sedimentation or erosion, or lead to water contamination.
Biosecurity Act 2014 – Fire Ant Control
26. Developers must remain vigilant for the presence of fire ants. Under the Biosecurity Act 2014,
individuals and businesses are responsible for ensuring that they follow the movement
controls for specific organic materials to help prevent the spread of fire ants within South
East Queensland’s fire ant biosecurity zones. Movement of a fire ant carrier from within a fire
ant biosecurity zone may need a biosecurity instrument permit. More information is available
on https://www.fireants.org.au/treat/business-andindustry/movement-controls.
G. Agree to amend Section 10 - Further Development Permits Required to read as follows;
Type of Development Permit required Subject of the required Development
Development Permit for Building Works All building work.
Page 20 of 20
Document Set ID: 24188054
Version: 10, Version Date: 18/12/2025
Used in these records
Negotiated Report (Representations made) MCU24 0153 (As Published).pdfRelated documentApplication case desk ↗
Negotiated Report (Representations made) MCU24 0153 (As Published).pdfRelated documentApplication case desk ↗
About this file
- File size
- 555 KB (small file)
- File type
No other editions are linked here.