Council archive · source document
Negotiated Report (Representations made) MCU24 0153 (As Published) · MCU24/0153
022 B Bulk Earthworks Sections Sheet 2 26 August
2025
Prepared by RECOR
042 B Stormwater Longitudinal Sections Sheet 1 26 August
2025
Prepared by RECOR
043 B Stormwater Longitudinal Sections Sheet 2 26 August
2025
Prepared by RECOR
041 B Stormwater Catchment Layout 26 August
2025
Prepared by RECOR
044 A Stormwater Details 26 August
2025
Prepared by RECOR
LD1 F General Notes, Sheet Layout & Site 02/12/2025
Location prepared by Anembo Consultants
LD2 F Project Specifications prepared by Anembo 02/12/2025
Consultants
LD3 F Project Specifications, Annual 02/12/2025
Maintenance & Finishes Schedule
prepared by Anembo Consultants
LD4 F Plant Schedules prepared by Anembo 02/12/2025
Consultants
LD5 F Typical Details prepared by Anembo 02/12/2025
Consultants
LP1 F Landscape Plan (Ground 1/2) prepared by 02/12/2025
Anembo Consultants
LP2 F Landscape Plan (Ground 2/2) prepared by 02/12/2025
Anembo Consultants
LP3 F Landscape Plan (First Level) prepared by 02/12/2025
Anembo Consultants
LP4 F Landscape Plan (Second Floor) prepared 02/12/2025
by Anembo Consultants
LP5 F Landscape Plan (Roof) prepared by 02/12/2025
Anembo Consultants
D. Agree to the representations and include Conditions 3 - 56 for Operational Works
(OPW24/0202) to read as follows;
SITE SPECIFIC CONDITIONS
Bonds
Page 10 of 20
Document Set ID: 24188054
Version: 10, Version Date: 18/12/2025
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Negotiated Report (Representations made) MCU24 0153 (As Published).pdfRelated documentApplication case desk ↗
Negotiated Report (Representations made) MCU24 0153 (As Published).pdfRelated documentApplication case desk ↗
About this file
- File size
- 555 KB (small file)
- File type
No other editions are linked here.