47. The site must be provided with a stormwater drainage system connecting to a lawful
point of discharge. The works must be undertaken in accordance with an Operational
Works approval the Queensland Urban Drainage Manual, and must include in particular:
a. the works as generally described in the updated Stormwater Management Plan
required by this permit
b. collection and discharge of stormwater from the external catchment through the
development site, including provision of an overland flowpath which accounts for
severe storms or severe blockage of the underground network
c. provision of drainage easements over all flowpaths conveying catchments external
to the site, in accordance with QUDM. Easement dimensions and locations are to
be shown on the plans submitted with the development application for Operational
Works.
d. the use of gravity stormwater drainage and not surcharge pits
48. Stormwater Quality Management
A stormwater quality treatment system must be provided for the development in
accordance with the updated Stormwater Management Plan required by this permit. The
works must be undertaken in accordance with an Operational Works approval.
53. An easement for stormwater drainage purposes must be registered in favour of Council
against the title of the subject site. The easement must:
h. Extend through the site from the northern Serenity Close frontage to the south-
western Serenity Close frontage,
i. Be of sufficient width to fully contain the 1%AEP flows (year 2100) from the local
catchment encompassing the development,
j. Be clearly shown on any plans submitted for Operational Works approval, and
k. Be registered prior to the commencement of the use.
__________________________________________________________________________
A6769/25/SWMP/Rev OpW(A) – Feb 2025
SH/PL Page 3 of 9
Brah101 Pty Ltd t/as ALTA PROJECTS
Document Set ID: 23646596
Version: 1, Version Date: 21/03/2025
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
SUPERDEDED NEGOTIATED - OPW25 0042 - Approved Plans (As Published).pdfRelated documentApplication case desk ↗
About this file
- File size
- 36.5 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.