Our Performance
Capital Works Projects Disaster Recovery Works Projects
Project Project
Project Name Brief description
budget Project Name Brief description budget
(REPA)
NDSC Stage 1 McKinnon The Noosa District Sports Complex received an upgrade including four $1.95m
Drive Community Sports change rooms, a kitchen, six unisex toilets, storage space, first aid and Kin Kin, Upper Pinbarren This road sustained damage at three locations in the 2022 major storm event. $1.4m
Complex umpire rooms, large multi-purpose area and pickleball courts. These Creek Rd waterway This reconstruction project replaced the old culverts and road surface at two
facilities will support several sports clubs currently based at the complex crossing remediation sites on this road.
including Tewantin Noosa Cricket Club, Noosa District Netball Association,
and Noosa Beach Classic Car Club, with the opportunity to welcome new Noosa Heads, Weyba This site sustained damage in the 2022 major storm event. This road $0.5m
sports such as pickleball to the site. Esplanade landslip reconstruction project used bored piles and blocks to create a stable
remediation embankment allowing the road surface to be repaired.
Pomona, Bakers Rd This site sustained damage in the 2022 major storm event. This road $0.4m
landslip remediation reconstruction project saw the upslope embankment through excavation
and rock placement. Additional drainage was included.
Disaster Recovery Works Projects Ridgewood, Old This site sustained damage in the 2022 major storm event. This road $1.0m
Ceylon Road landslip reconstruction project used bored piles and concrete wall to create a stable
Project remediation embankment allowing for additional drainage to be constructed and the
Project Name Brief description budget road surface to be repaired.
(REPA)
Happy Jack Creek Road, This site sustained damage in the 2022 major storm event. This road $1.4m
Black Mountain, Black Three small landslips resulted from the 2022 major storm event at various $1.6m Ridgewood landslip sustained damage at three locations in the 2022 major storm event. This
Mountain Rd landslip locations on this road. They were stabilised by excavating benches, repairing remediation road reconstruction project had excavated slopes and block retaining wall
remediation drains, adding rock. The road surface was then repaired. constructed along with drainage structures to create a stable embankment
allowing the road surface to be repaired.
132 Note: this is not the large landslide. Works are still in progress. 133
Black Mountain, Cooroy This road sustained damage at three locations in the 2022 major storm $3.6m
Belli Creek Rd landslip event. This road reconstruction project used bored piles and soil anchors to
remediation stabilise the area. The road surface was rebuilt, and guardrail added.
Cooran, Shreibers Road These roads sustained damage at 4 locations in the 2022 major storm event. $2.7m
and Coles Creek Road The reconstruction replaced the old culverts and pipes and repaired road
waterway crossing surface.
remediation
Cooroy, Cooroy Belli This road sustained damage at three locations in the 2022 major storm event. $2.0m
Creek Rd landslip This road reconstruction project used bored piles and blocks to create a
remediation stable embankment allowing the road surface to be repaired.
Cootharaba, This road sustained damage at three locations in the 2022 major storm $3.3m
Cootharaba Road event. This road reconstruction project used bored piles and soil anchors to
landslide remediation stabilise the area. The road surface was repaired.
Noosa Council Annual Report 23/24
Cootharaba, Simpsons This road sustained damage at three locations in the 2022 major storm event. $0.9m
Road landslide This road reconstruction project used bored piles to stabilise the slope. The
remediation road surface was repaired.
Kin Kin, Gully Gully Road, This road sustained damage at three locations in the 2022 major storm event. $1.3m
waterway crossing This reconstruction project replaced the old culverts or pipes and road
remediation surface at three sites on this road.
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.