Decision Notice - 010.2006.00001065.001 [As Published] · 142006.1065
-3-
Plan / Rev. Plan / Document Name Date
Document No.
16076-OW2 C Driveway & Drainage – SCG Consulting 08.10.07
Engineers
16076-C1 A Sewer Main Relocation – SCG 19.12.06
Consulting Engineers
16076-OW1 C Operational Works – SCG Consulting 08.10.07
Engineers
WD.201 T1 Basement Floor Plan – Kidd Co Jan ‘07
Designers
or as modified herein.
16. Excavation of the site and the construction of the proposed works shall not have any adverse
affects on the stability of adjoining buildings and/or structures and/or services and/or lands. In
this regard a Registered Professional Engineer Queensland shall supervise the excavation of
the site and the construction of the new works to determine whether any additional measures
are required to protect the stability of adjoining buildings and/or structures and/or services
and/or lands.
17. The use of vibratory equipment of any kind, (including vibrating rollers and the use of vibrating
installation techniques for sheet piling and other construction vibrations caused by excavating,
earthmoving or demolition machinery or other similar construction techniques) shall be
supervised by a Certified Geotechnical Engineer. Under such circumstances the operator of
such equipment shall at all times comply with the directions of the Geotechnical engineer and
the reasonable and lawful directions of Council officers.
18. All parts of the works (including excavation, retaining structures, tie backs etc) are to be wholly
contained within the subject site. Any subground structures (support anchors, tie backs etc) to
be utilized into adjoining properties, shall only be used if written permission has been granted
by the adjoining property owners.
19. Certification of the completed works must be provided to Council by the supervising engineer.
The certification shall state that the completed works conform with all aspects of the design
and that the completed works will not have any adverse affects on the stability of adjoining
buildings and/or structures and/or services and/or lands.
20. Roof and surface runoff connection to Council’s kerb and channel shall be as shown on
drawing No. 16076-OW2C. Kerb adaptors shall be used in the kerb.
21. A Traffic Management Plan for the development addressing all construction phases shall be
prepared by suitably qualified persons and submitted to Council for approval prior to the pre
start meeting. The report shall address, but not be limited to, all items listed below, further the
plan shall be flexible that it addresses all stages of the development:-
21.1. A single nominated access location to from the site.
21.2. The plan should detail the routing of trucks to and from the site.
21.3. Provision of onsite parking for personnel working on this development, as there is
limited parking available in adjacent streets.
21.4. Provision of safe cycle and pedestrian movements around the development on
Henderson Street.
21.5. No queuing of trucks is permitted on residential streets, especially prior to 7.00am.
Further parked trucks must have engines turned off.
21.6. Provision of signage and traffic controllers in accordance with Manual of Uniform
Traffic Control Devices and Traffic Infrastructure (Roads) Act.
3 of 11
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Decision Notice - 010.2006.00001065.001 [As Published]Related documentApplication case desk ↗
About this file
- File size
- 74 KB (small file)
- File type
No other editions are linked here.