June 2006 -2- 06683025-1000(AA)

 

4.0 METHOD OF INVESTIGATION
4.1 Preliminary Assessment

To assist with planning the scope of work for this preliminary investigation a desktop study
was conducted. This comprised a review of available documents including plans on geology’
ASS distribution? (Department of Natural Resources & Mines, NR&M).

The results of the preliminary assessment are presented in Section 5.1.
4.2 Subsurface Investigation

An investigation program was planned to enable a preliminary ASS assessment of the site.
The ASS investigation was planned having consideration for State Government policies’ and
legislation to cover the proposed area of disturbance below RL 5 m AHD. The formulation of
our scope of work is discussed in Section 6.2.

Three boreholes (designated BH1 to BH3) were drilled using a 4WD-mounted flight auger rig
to 3 m depth. The borehole locations are shown on Figure 2 Site Plan. The boreholes were
located along an existing access track within the area of proposed commercial use.

ASS sampling protocols in the field were conducted to minimise oxidation prior to laboratory
testing and followed the Queensland Sampling Guidelines’ October 1998 (Revision 4.0) of
the “Guidelines for sampling and analysis of lowland Acid Sulfate Soils (ASS) in Queensland
1998” produced by the Queensland Acid Sulfate Soils Investigation Team (QASSIT).

A standpipe for groundwater monitoring was installed in borehole BH3. This was constructed
from 50 mm diameter PVC pipe slotted over the lower 2 m, and gravel packed to within about
0.4 m of the ground surface before sealing with bentonite. Reports of Boreholes are presented
in Appendix A, together with explanatory notes.

The subsurface investigation was conducted by experienced geotechnical personnel on 29
June 2006.

4.3, Groundwater Monitoring

The groundwater level in Borehole BH3 standpipe was measured by an environmental
scientist on 3 July 2006. Following the level measurement, the groundwater quality was
tested in the field, after purging, and then sampled for laboratory analysis. The field testing

! 1;100,000 Geological Map, GYMPIE SPECIAL, Sheet 9444 & Part 9545, DME, 1999
2 1:100,000 Redcliff to Teewah Acid Sulfate Soil Map 2, N&RM, 1999

> State Planning Policy SPP2/02 “Planning and Managing Development Involving Acid Sulfate Soils”.
4 Guidelines for Sampling and Analysis of Lowland ASS in Queensland, Qld ASS Investigation Team (QASSIT), Revision 4.0,
October 1998.

Golder Associates

Used in these records

About this file

File size
7.5 MB (large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Application part 2 [As Published].pdf · 7.5 MB (large file)

The download may take up to a minute.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.