Environmental Protection Act 1994
Chapter 5 Environmental authorities and environmentally relevant activities
Part 2 Application stage
[s 127]
(i) best practice environmental management for
managing the CSG water; and
(ii) alternative ways for managing the water; and
(b) the evaluation shows there is no feasible alternative to a
CSG evaporation dam for managing the water.
127 When application is a properly made application
An application for an environmental authority under section
116(1) is a properly made application if it complies with this
division.
Division 4 Notices about not properly made
applications
128 Notice about application that is not a properly made
application
(1) This section applies if an application is not a properly made
application.
(2) The administering authority must, within 10 business days
after receiving the application, give the applicant a notice
stating the following—
(a) it is not a properly made application;
(b) the reasons the administering authority is satisfied it is
not a properly made application;
(c) the action the administering authority is satisfied the
applicant must take for the application to be a properly
made application;
(d) the period of at least 20 business days after the notice is
given within which the applicant must give written
notice to the administering authority that the action has
been taken;
Current as at 20 February 2014 Page 111
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.