MCU14/0028 Appendix 2 EnvProtAct 1994
Original PDF page 124, section 1. The text section number identifies this passage in the reader.
Environmental Protection Act 1994
Chapter 5 Environmental authorities and environmentally relevant activities
Part 4 Notification stage
[s 151]
(3) However, a properly made submission about the EIS is taken
to be a properly made submission about the application.
151 When notification stage can start
The applicant may start the notification stage as soon as the
application stage ends for the application.
Division 2 Public notice
152 Public notice of application
(1) The applicant must give and publish a notice about the
application (the application notice).
(2) The application notice must be given and published—
(a) simultaneously or together with, and in the same way as,
any public notice for an application under resource
legislation for a relevant tenure for the application; or
(b) if public notice is not required to be given for an
application under resource legislation for a relevant
tenure for the application—
(i) in a newspaper circulating generally in the area
where the relevant resource activity is proposed to
be carried out; and
(ii) before the day that is 10 business days after the end
of the information stage for the application; or
(c) in another way prescribed under a regulation.
(3) The administering authority may decide an additional or
substituted way to give or publish the application notice if it
gives the applicant an information notice about the decision
before the application notice is given.
(4) This section is subject to section 159.
Page 122 Current as at 20 February 2014
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.