184 Application of sdiv 3
This subdivision applies to an application for a mining activity
relating to a mining lease if—
(a) an objection notice for a submission about the
application is given to the administering authority under
section 182(2); or
(b) the applicant has requested under section 183(1) that the
application be referred to the Land Court.
185 Referral to Land Court
(1) The administering authority must refer the application to the
Land Court for a decision under this subdivision (the
objections decision).
(2) The referral must be made within 10 business days after the
later of the following—
(a) the receipt of the last objection notice under section 182;
(b) the receipt of a request for referral under section 183.
(3) The referral must be made by filing with the registrar of the
Land Court—
(a) a notice, in the approved form, referring the application
to the Land Court; and
(b) a copy of the application; and
(c) a copy of any response to an information request; and
(d) a copy of any submission for the application; and
(e) a copy of the notice given under section 181(1),
including any draft environmental authority for the
application; and
(f) a copy of any objection notice given under section
182(2); and
Current as at 20 February 2014 Page 139
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.