MCU14/0028 Appendix 2 EnvProtAct 1994
Original PDF page 147, section 1. The text section number identifies this passage in the reader.
Environmental Protection Act 1994
Chapter 5 Environmental authorities and environmentally relevant activities
Part 5 Decision stage
[s 195]
(b) if a draft environmental authority was not given for the
application—
(i) comply with any relevant regulatory requirement;
and
(ii) subject to subparagraph (i), have regard to the
following—
(A) the application;
(B) any standard conditions for the relevant
activity or authority;
(C) any response given for an information
request;
(D) the standard criteria.
Division 4 Steps after deciding application
195 Issuing environmental authority
If the administering authority decides to approve an
application or makes a decision under section 170(2)(b) or
171(2)(b), it must issue an environmental authority to the
applicant—
(a) if the application for the authority is referred to the Land
Court under section 185—within 5 business days after a
final decision is made under section 194(2); or
(b) if notice of the decision is given under section 181 and
the application for the authority is not referred to the
Land Court under section 185—within 25 business days
after the notice is given under section 181; or
(c) if a development application is taken, under section 115,
to also be an application for an environmental
authority—
(i) if the administering authority is the assessment
manager for the development application under the
Current as at 20 February 2014 Page 145
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.