Environmental Protection Act 1994
Chapter 5 Environmental authorities and environmentally relevant activities
Part 12 General provisions
[s 287]
287 Plan of operations required before acting under
relevant lease
The environmental authority holder must not carry out, or
allow the carrying out of, an activity under the relevant lease
unless—
(a) a plan of operations for all relevant activities has been
given to the administering authority; and
(b) at least 20 business days, or a shorter period agreed in
writing by the administering authority and the holder,
have passed since the plan was submitted; and
(c) the plan complies with section 288.
Maximum penalty—100 penalty units.
288 Requirements for plan of operations
(1) A plan of operations must—
(a) describe the following—
(i) each relevant lease for the environmental authority;
(ii) the land to which each relevant lease applies;
(iii) the land to which the plan applies; and
(b) state the period to which the plan applies (the plan
period); and
(c) include the following—
(i) a plan showing where all activities are to be carried
out on the land;
(ii) an action program for complying with the
conditions of the environmental authority;
(iii) a rehabilitation program for land disturbed or
proposed to be disturbed under each relevant lease;
(iv) another matter prescribed under an environmental
protection policy or a regulation; and
Current as at 20 February 2014 Page 203
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.