MCU14/0028 Appendix 2 EnvProtAct 1994
Original PDF page 57, section 1. The text section number identifies this passage in the reader.
Environmental Protection Act 1994
Chapter 3 Environmental impact statements
Part 1 EIS process
[s 37]
Chapter 3 Environmental impact
statements
Part 1 EIS process
Division 1 Preliminary
Subdivision 1 Application
37 When EIS process applies
(1) This part applies for a project, other than a coordinated
project, if—
(a) an EIS requirement is in force in relation to an
application for an environmental authority for a mining
activity that is, or is part of, the project; or
(b) an EIS requirement is in force in relation to an
application for an environmental authority for a resource
activity, other than a mining activity; or
(c) an EIS has been required for the project under an Act as
follows for which it has, under the Act, been decided or
required that this part applies to the preparation of the
EIS—
(i) the Commonwealth Environment Act;
(ii) the State Development Act;
Note—
See the State Development Act, part 4, divisions 2
(Coordinated project) and 3 (EIS process).
(iii) another State Act or another Commonwealth Act;
or
Current as at 20 February 2014 Page 55
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.