MCU14/0028 Appendix 2 EnvProtAct 1994
Original PDF page 72, section 1. The text section number identifies this passage in the reader.
Environmental Protection Act 1994
Chapter 3 Environmental impact statements
Part 1 EIS process
[s 54]
Subdivision 2 Submissions
54 Right to make submission
A person may, within the submission period, make a
submission to the chief executive about the submitted EIS.
55 Acceptance of submissions
(1) The chief executive must accept a submission if it—
(a) is written; and
(b) is signed by or for each person (signatory) who made
the submission; and
(c) states the name and address of each signatory; and
(d) is made to the chief executive; and
(e) is received on or before the last day of the submission
period.
(2) A submission that complies with subsection (1) is called a
properly made submission.
(3) The chief executive may accept a written submission even if it
is not a properly made submission.
56 Response to submissions
(1) The chief executive must, within 10 business days after the
submission period ends, give the proponent a copy of all
submissions accepted by the chief executive.
(2) The proponent must, within the relevant period, consider the
submissions and give the chief executive—
(a) a summary of the submissions; and
(b) a statement of the proponent’s response to the
submissions; and
Page 70 Current as at 20 February 2014
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.