MCU14/0028 Appendix 2 EnvProtAct 1994
Original PDF page 81, section 1. The text section number identifies this passage in the reader.
Environmental Protection Act 1994
Chapter 3 Environmental impact statements
Part 2 Voluntary preparation of EIS
[s 69]
Part 2 Voluntary preparation of EIS
69 Purpose of pt 2
(1) The purpose of this part is to allow the proponent for a project
to voluntarily prepare an EIS for the project by using the EIS
process, if it is appropriate to do so.
(2) The purpose is achieved by providing for an approval process
for the voluntary preparation of an EIS.
70 Projects that may be approved for EIS
(1) The proponent for a project may apply to the chief executive
for approval to prepare an EIS for a project.
(2) However, an application can not be made for a project if—
(a) an EIS requirement is in force for an application under
this Act relating to the project; or
(b) the Commonwealth Environment Act requires the
project to be assessed under chapter 4, part 8 of that Act
and the EIS process has not been decided as an
accredited process under the Commonwealth
Environment Act; or
Editor’s note—
See the Commonwealth Environment Act, sections 47
(Agreement may declare classes of actions do not need
assessment) and 87 (Minister must decide on approach for
assessment).
(c) an EIS or similar statement, however called, must be
prepared for the project under another State Act and that
Act does not allow the EIS or statement to be prepared
under the EIS process.
71 Requirements for application
An approval application must be—
Current as at 20 February 2014 Page 79
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.